Sie sind auf Seite 1von 3

University of Guyana, Faculty of Technology

Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan

Draft Project Schedule


ID Task Name Duration Start Finish 3rd Quarter 1st Quarter
July September November January March May July
E M B E M B E M B E M B E M B E M B E
0 Structural Modelling, Analysis and Design of Science Pentagon 239 days Mon 26/08/13 Mon 21/07/14
1
2 1 Project Selection 20 days Mon 26/08/13 Fri 20/09/13
3 1.1 Topic Research 15 days Mon 26/08/13 Fri 13/09/13
4 1.2 Project Supervisor Selection 15 days Mon 26/08/13 Fri 13/09/13
5 1.3 Submission of Project Selection Form 5 days Mon 16/09/13 Fri 20/09/13 20/09
6
7 2 Preliminary Design Stage 26 days Mon 23/09/13 Mon 28/10/13
8
9 2.1 Data Collection 8 days Mon 23/09/13 Wed 02/10/13
10 2.1.1 Conceptual Model Collection 5 days Mon 23/09/13 Fri 27/09/13
11 2.1.2 Building Information Collection 5 days Mon 23/09/13 Fri 27/09/13
12 2.1.3 Site Data Collection (Weather Conditions) 8 days Mon 23/09/13 Wed 02/10/13
13 2.1.4 Grades of Steel Members available locally 7 days Mon 23/09/13 Tue 01/10/13
14 2.1.5 Concrete Mix Designs availably locally 7 days Mon 23/09/13 Tue 01/10/13
15
16 2.2 Selection of Building and Design Codes 7 days Thu 03/10/13 Fri 11/10/13
17 2.3 Selection of Building Materials (Available Locally) 7 days Mon 23/09/13 Tue 01/10/13
18
19 2.4 Modelling of chosen building 15 days Mon 30/09/13 Fri 18/10/13
20 2.4.1 Concept Model displaying temperature based data 15 days Mon 30/09/13 Fri 18/10/13
21 2.4.2 Concept Model displaying wind based data 15 days Mon 30/09/13 Fri 18/10/13
22
23 2.5 Compiling of structural element schedule 4 days Mon 21/10/13 Thu 24/10/13
24 2.6 Compiling of a preliminary estimate for structural members 2 days Fri 25/10/13 Mon 28/10/13
25
26 3 Project Proposal 50 days Mon 09/09/13 Fri 15/11/13
27
28 3.1 Design 39 days Mon 09/09/13 Thu 31/10/13
29 3.1.1 Title Page 5 days Mon 09/09/13 Fri 13/09/13
30 3.1.2 Abstract 5 days Mon 14/10/13 Fri 18/10/13
31 3.1.3 Table of Contents, List of Figures, List of Tables 5 days Wed 11/09/13 Tue 17/09/13
32 3.1.4 Introduction 5 days Thu 03/10/13 Wed 09/10/13
33 3.1.5 Scope of Works 5 days Mon 14/10/13 Fri 18/10/13
34 3.1.6 Literature Review 5 days Thu 26/09/13 Wed 02/10/13
35 3.1.7 Plan of Implementation 5 days Wed 18/09/13 Tue 24/09/13
36 3.1.8 Format 5 days Tue 10/09/13 Mon 16/09/13
37 3.1.9 Budget 4 days Mon 23/09/13 Thu 26/09/13
38 3.1.10 Schedule 5 days Tue 17/09/13 Mon 23/09/13
39 3.1.11 Reference 5 days Thu 17/10/13 Wed 23/10/13
40 3.1.12 Appendices 3 days Tue 29/10/13 Thu 31/10/13
41
42 3.2 Submission of Project Proposal 1 day Fri 01/11/13 Fri 01/11/13 01/11
43 3.3 Oral Presentation 1 day Fri 15/11/13 Fri 15/11/13 15/11

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Structural Modelling, Ana Split External Tasks Inactive Summary Manual Summary Progress


Date: Thu 03/10/13 Milestone External Milestone Manual Task Start‐only
Summary Inactive Task Duration‐only Finish‐only

Page 1
University of Guyana, Faculty of Technology

Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan

Draft Project Schedule


ID Task Name Duration Start Finish 3rd Quarter 1st Quarter
July September November January March May July
E M B E M B E M B E M B E M B E M B E
44
45 4 Final Design Stage 129 days Tue 24/12/13 Tue 17/06/14
46
47 4.1 Material Definition 10 days Tue 24/12/13 Mon 06/01/14
48 4.1.1 Defining of Concrete Parameters 5 days Tue 24/12/13 Mon 30/12/13
49 4.1.2 Defining of Steel Parameters 5 days Fri 27/12/13 Thu 02/01/14
50 4.1.3 Defining of Other Material Parameters (Floor Deck Materials) 5 days Tue 31/12/13 Mon 06/01/14

51
52 4.2 Model Creation 12 days Wed 01/01/14 Thu 16/01/14
53 4.2.1 Modeling of Grid Lines and Levels 2 days Wed 01/01/14 Thu 02/01/14
54
55 4.2.2 Modelling of Structural Elements 10 days Fri 03/01/14 Thu 16/01/14
56 4.2.2.1 Columns 5 days Fri 03/01/14 Thu 09/01/14
57 4.2.2.2 Beams 5 days Fri 10/01/14 Thu 16/01/14
58 4.2.2.3 Floor Slabs 5 days Fri 03/01/14 Thu 09/01/14
59 4.2.2.4 Roof Slabs 5 days Mon 06/01/14 Fri 10/01/14
60 4.2.2.5 Walls/Shear Walls 5 days Fri 03/01/14 Thu 09/01/14
61
62 4.3 Load Definitions 13 days Tue 24/12/13 Thu 09/01/14
63 4.3.1 Dead Loads (Non material) 5 days Tue 24/12/13 Mon 30/12/13
64 4.3.2 Live Loads 7 days Thu 26/12/13 Fri 03/01/14
65 4.3.3 Wind Loads 10 days Tue 24/12/13 Mon 06/01/14
66 4.3.4 Temperature Loads 10 days Tue 24/12/13 Mon 06/01/14
67 4.3.5 Accidental Loads 7 days Fri 27/12/13 Mon 06/01/14
68 4.3.6 Seismic Loads 7 days Wed 01/01/14 Thu 09/01/14
69
70 4.4 Load Assignment 9 days Fri 17/01/14 Wed 29/01/14
71 4.4.1 Dead Loads (Non material) 2 days Fri 17/01/14 Mon 20/01/14
72 4.4.2 Live Loads 5 days Tue 21/01/14 Mon 27/01/14
73 4.4.3 Wind Loads 5 days Wed 22/01/14 Tue 28/01/14
74 4.4.4 Temperature Loads 5 days Tue 21/01/14 Mon 27/01/14
75 4.4.5 Accidental Loads 5 days Thu 23/01/14 Wed 29/01/14
76 4.4.6 Seismic Loads 5 days Tue 21/01/14 Mon 27/01/14
77
78 4.5 Load Combinations Generation 7 days Thu 30/01/14 Fri 07/02/14
79
80 4.6 Model Analysis 30 days Fri 28/02/14 Mon 07/04/14
81
82 4.6.1 Dynamic Analysis 24 days Fri 28/02/14 Sun 30/03/14
83 4.6.1.1 Modal frequency analysis 10 days Fri 28/02/14 Wed 12/03/14
84 4.6.1.2 Floor vibration analysis 10 days Tue 04/03/14 Sun 16/03/14
85 4.6.1.3 Response Spectrum Analysis 10 days Thu 06/03/14 Tue 18/03/14
86 4.6.1.4 Time History Analysis 10 days Mon 10/03/14 Thu 20/03/14
87 4.6.1.5 P-Delta Analysis 10 days Wed 12/03/14 Mon 24/03/14

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Structural Modelling, Ana Split External Tasks Inactive Summary Manual Summary Progress


Date: Thu 03/10/13 Milestone External Milestone Manual Task Start‐only
Summary Inactive Task Duration‐only Finish‐only

Page 2
University of Guyana, Faculty of Technology

Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan

Draft Project Schedule


ID Task Name Duration Start Finish 3rd Quarter 1st Quarter
July September November January March May July
E M B E M B E M B E M B E M B E M B E
88 4.6.1.6 Buckling Analysis 10 days Fri 14/03/14 Wed 26/03/14
89 4.6.1.7 Pushover Analysis 10 days Sun 16/03/14 Thu 27/03/14
90 4.6.1.8 Concrete Shrinkage and Time Dependent Creep Analysis 10 days Tue 18/03/14 Sun 30/03/14

91
92 4.6.2 Construction Sequencing 10 days Wed 26/03/14 Mon 07/04/14
93
94 4.7 Element Design 20 days Tue 08/04/14 Mon 05/05/14
95 4.7.1 Columns 5 days Tue 08/04/14 Mon 14/04/14
96 4.7.2 Beams 5 days Tue 15/04/14 Mon 21/04/14
97 4.7.3 Floor Slabs 5 days Tue 22/04/14 Mon 28/04/14
98 4.7.4 Roof Slabs 5 days Tue 29/04/14 Mon 05/05/14
99 4.7.5 Shear Walls 5 days Tue 08/04/14 Mon 14/04/14
100 4.7.6 Composite Elements 7 days Tue 08/04/14 Wed 16/04/14
101 4.7.7 Connections (Optional) 5 days Tue 22/04/14 Mon 28/04/14
102
103 4.8 Model Optimization 10 days Tue 06/05/14 Mon 19/05/14
104
105 4.9 Documentation 21 days Tue 20/05/14 Tue 17/06/14
106 4.9.1 Final Model Generation 7 days Tue 20/05/14 Wed 28/05/14
107 4.9.2 Final Structural Model Documentation 14 days Thu 29/05/14 Tue 17/06/14
108 4.9.3 Final Analysis Documentation 14 days Tue 20/05/14 Fri 06/06/14
109
110 5 Final Report 31 days Mon 09/06/14 Mon 21/07/14
111
112 5.1 Design 14 days Mon 09/06/14 Thu 26/06/14
113 5.1.1 Title Page 1 day Mon 09/06/14 Mon 09/06/14
114 5.1.2 Executive Summary 3 days Mon 09/06/14 Wed 11/06/14
115 5.1.3 Abstract 4 days Mon 09/06/14 Thu 12/06/14
116 5.1.4 Acknowledgements 1 day Mon 09/06/14 Mon 09/06/14
117 5.1.5 Table of Contents, List of Figures, List of Tables, etc 1 day Mon 09/06/14 Mon 09/06/14
118 5.1.6 Introduction 3 days Mon 09/06/14 Wed 11/06/14
119 5.1.7 Method and Design Approach 7 days Mon 09/06/14 Tue 17/06/14
120 5.1.8 Results 6 days Mon 09/06/14 Mon 16/06/14
121 5.1.9 Conclusion 2 days Tue 17/06/14 Wed 18/06/14
122 5.1.10 Recommendations 6 days Thu 19/06/14 Thu 26/06/14
123 5.1.11 References 1 day Mon 09/06/14 Mon 09/06/14
124 5.1.12 Appendices 5 days Mon 09/06/14 Fri 13/06/14
125
126 5.2 Submission of Project Final Report 7 days Fri 20/06/14 Mon 30/06/14 30/06
127 5.3 Oral Presentation 1 day Mon 21/07/14 Mon 21/07/14 21/07

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Structural Modelling, Ana Split External Tasks Inactive Summary Manual Summary Progress


Date: Thu 03/10/13 Milestone External Milestone Manual Task Start‐only
Summary Inactive Task Duration‐only Finish‐only

Page 3

Das könnte Ihnen auch gefallen