Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
Page 1
University of Guyana, Faculty of Technology
Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
51
52 4.2 Model Creation 12 days Wed 01/01/14 Thu 16/01/14
53 4.2.1 Modeling of Grid Lines and Levels 2 days Wed 01/01/14 Thu 02/01/14
54
55 4.2.2 Modelling of Structural Elements 10 days Fri 03/01/14 Thu 16/01/14
56 4.2.2.1 Columns 5 days Fri 03/01/14 Thu 09/01/14
57 4.2.2.2 Beams 5 days Fri 10/01/14 Thu 16/01/14
58 4.2.2.3 Floor Slabs 5 days Fri 03/01/14 Thu 09/01/14
59 4.2.2.4 Roof Slabs 5 days Mon 06/01/14 Fri 10/01/14
60 4.2.2.5 Walls/Shear Walls 5 days Fri 03/01/14 Thu 09/01/14
61
62 4.3 Load Definitions 13 days Tue 24/12/13 Thu 09/01/14
63 4.3.1 Dead Loads (Non material) 5 days Tue 24/12/13 Mon 30/12/13
64 4.3.2 Live Loads 7 days Thu 26/12/13 Fri 03/01/14
65 4.3.3 Wind Loads 10 days Tue 24/12/13 Mon 06/01/14
66 4.3.4 Temperature Loads 10 days Tue 24/12/13 Mon 06/01/14
67 4.3.5 Accidental Loads 7 days Fri 27/12/13 Mon 06/01/14
68 4.3.6 Seismic Loads 7 days Wed 01/01/14 Thu 09/01/14
69
70 4.4 Load Assignment 9 days Fri 17/01/14 Wed 29/01/14
71 4.4.1 Dead Loads (Non material) 2 days Fri 17/01/14 Mon 20/01/14
72 4.4.2 Live Loads 5 days Tue 21/01/14 Mon 27/01/14
73 4.4.3 Wind Loads 5 days Wed 22/01/14 Tue 28/01/14
74 4.4.4 Temperature Loads 5 days Tue 21/01/14 Mon 27/01/14
75 4.4.5 Accidental Loads 5 days Thu 23/01/14 Wed 29/01/14
76 4.4.6 Seismic Loads 5 days Tue 21/01/14 Mon 27/01/14
77
78 4.5 Load Combinations Generation 7 days Thu 30/01/14 Fri 07/02/14
79
80 4.6 Model Analysis 30 days Fri 28/02/14 Mon 07/04/14
81
82 4.6.1 Dynamic Analysis 24 days Fri 28/02/14 Sun 30/03/14
83 4.6.1.1 Modal frequency analysis 10 days Fri 28/02/14 Wed 12/03/14
84 4.6.1.2 Floor vibration analysis 10 days Tue 04/03/14 Sun 16/03/14
85 4.6.1.3 Response Spectrum Analysis 10 days Thu 06/03/14 Tue 18/03/14
86 4.6.1.4 Time History Analysis 10 days Mon 10/03/14 Thu 20/03/14
87 4.6.1.5 P-Delta Analysis 10 days Wed 12/03/14 Mon 24/03/14
Page 2
University of Guyana, Faculty of Technology
Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
91
92 4.6.2 Construction Sequencing 10 days Wed 26/03/14 Mon 07/04/14
93
94 4.7 Element Design 20 days Tue 08/04/14 Mon 05/05/14
95 4.7.1 Columns 5 days Tue 08/04/14 Mon 14/04/14
96 4.7.2 Beams 5 days Tue 15/04/14 Mon 21/04/14
97 4.7.3 Floor Slabs 5 days Tue 22/04/14 Mon 28/04/14
98 4.7.4 Roof Slabs 5 days Tue 29/04/14 Mon 05/05/14
99 4.7.5 Shear Walls 5 days Tue 08/04/14 Mon 14/04/14
100 4.7.6 Composite Elements 7 days Tue 08/04/14 Wed 16/04/14
101 4.7.7 Connections (Optional) 5 days Tue 22/04/14 Mon 28/04/14
102
103 4.8 Model Optimization 10 days Tue 06/05/14 Mon 19/05/14
104
105 4.9 Documentation 21 days Tue 20/05/14 Tue 17/06/14
106 4.9.1 Final Model Generation 7 days Tue 20/05/14 Wed 28/05/14
107 4.9.2 Final Structural Model Documentation 14 days Thu 29/05/14 Tue 17/06/14
108 4.9.3 Final Analysis Documentation 14 days Tue 20/05/14 Fri 06/06/14
109
110 5 Final Report 31 days Mon 09/06/14 Mon 21/07/14
111
112 5.1 Design 14 days Mon 09/06/14 Thu 26/06/14
113 5.1.1 Title Page 1 day Mon 09/06/14 Mon 09/06/14
114 5.1.2 Executive Summary 3 days Mon 09/06/14 Wed 11/06/14
115 5.1.3 Abstract 4 days Mon 09/06/14 Thu 12/06/14
116 5.1.4 Acknowledgements 1 day Mon 09/06/14 Mon 09/06/14
117 5.1.5 Table of Contents, List of Figures, List of Tables, etc 1 day Mon 09/06/14 Mon 09/06/14
118 5.1.6 Introduction 3 days Mon 09/06/14 Wed 11/06/14
119 5.1.7 Method and Design Approach 7 days Mon 09/06/14 Tue 17/06/14
120 5.1.8 Results 6 days Mon 09/06/14 Mon 16/06/14
121 5.1.9 Conclusion 2 days Tue 17/06/14 Wed 18/06/14
122 5.1.10 Recommendations 6 days Thu 19/06/14 Thu 26/06/14
123 5.1.11 References 1 day Mon 09/06/14 Mon 09/06/14
124 5.1.12 Appendices 5 days Mon 09/06/14 Fri 13/06/14
125
126 5.2 Submission of Project Final Report 7 days Fri 20/06/14 Mon 30/06/14 30/06
127 5.3 Oral Presentation 1 day Mon 21/07/14 Mon 21/07/14 21/07