Beruflich Dokumente
Kultur Dokumente
Muqeem Ud Din
Umar Farooq
Supervised by:
Engr. Naveed Ullah
Muqeem Ud Din
Umar Farooq
_______________ ___________________
Engr. Naveed Ullah Prof. Saeed Javed Tajik
Project Supervisor Chairman
The total available hydro power potential in Khyber Pukhtunkhwa is about 30000MW
in which 18% has been harnessed. Local communities living in distant far and flung
mountainous areas are still in dark and lack resources and development. MHPPs could
bring revolutionary change in their lives and help in the development of society.
NGOs and local communities have installed MHPPs but most often with locally built
accessories and average expertise. The aim of this project was to analyze the already
installed MHPPs in KPK by considering a case study and to recommend for
improvement. In order to accomplish this objective, extensive literature review has
been carried out. For site selection and acquisition of data regarding MHPPs in KPK,
various GOVT. and Non-Govt. organizations have been consulted. Different sites
were visited and finally a 10 KW MHPP was selected in “Dapor Maidan” Dir (l). For
evaluation of the site, theoretical power output was calculated after finding site
parameters. Efficiency was calculated which was 21.76%. The much lower efficiency
than optimum range (60-75%) depicted shortcomings in civil structures and electro
mechanical components. Finally causes of limitations were identified and
recommendations were made for the improvement of efficiency.
3
ACKNOWLEDGMENT
4
CHAPTER 1
INTRODUCTION
The objective of a hydro power scheme is to convert the potential energy of a
mass of water, flowing in a stream with a certain fall (termed the head.), into electric
energy at the lower end of the scheme, where the powerhouse is located.
The power of the scheme is proportional to the flow and to the head. Micro-
hydro schemes produce power from streams and small rivers. The power can be used
to generate electricity, or to drive machinery. Micro-hydro can bring electricity to
remote communities for the first time, replacing kerosene for lighting, providing TV
and communications to homes and community buildings, and enabling small
businesses to start.
Micro-hydro schemes are already benefiting many remote communities and
hilly areas of Pakistan. In the developed world, micro-hydro schemes supply power to
existing mains electric grids.
5
1.1. HISTORY OF SMALL HYDRO POWER TECHNALOGY
Hydropower is a renewable, non-polluting and environmentally benign source of
energy. Hydropower is based on simple concepts. Moving water turns a turbine, the
turbine spins a generator, and electricity is produced. Many other components may be
in a system, but it all begins with the energy in the moving water. The use of water
falling through a height has been utilized as a source of energy since a long time. It is
perhaps the oldest renewable energy technique known to the mankind for mechanical
energy conversion as well as electricity generation. In the ancient times waterwheels
were used extensively, but it was only at the beginning of the 19th Century with the
invention of the hydro turbines that the use of hydropower got popularized.
Small-scale hydropower was the most common way of electricity generating in
the early 20th century. The first commercial use of hydroelectric power to produce
electricity was a waterwheel on the Fox River in Wisconsin in 1882 that supplied
power for lighting to two paper mills and a house. Within a matter of weeks of this
installation, a power plant was also put into commercial service at Minneapolis. India
has a century old history of hydropower and the beginning was from small hydro. The
first hydro power plant was of 130 kW set up in Darjeeling during 1897, marked the
development of hydropower in the country. Similarly, by 1924 Switzerland had nearly
7000 small scale hydropower stations in use. Even today, Small hydro is the largest
contributor of electricity from renewable energy sources, both at European and world
level. With the advancement of technology, and increasing requirement of electricity,
the thrust of electricity generation was shifted to large size hydro and thermal power
stations. However, it is only during the last two decades that there is a renewed
interest in the development of small hydro power (SHP) projects mainly due to its
benefits particularly concerning environment and ability to produce power in remote
areas. Small hydro projects are economically viable and have relatively short
gestation period. The major constraints associated with large hydro projects are
usually not encountered in small hydro projects. Renewed interest in the technology
of small scale hydropower actually started in China which has more than 85,000
small-scale electricity Hydropower stations which will continue to play important role
throughout the 21st Century, in world electricity supply. Hydropower development
does have some challenges besides the technical, economic introducing, hydropower
6
plants environmental advantages it shares above other power generation (fossil fuel
based) technologies.
At the beginning of the new Millennium hydropower provided almost 20%
(2600 TWh/year) of the electricity world consumption (12900 TWh/year). It plays a
major role in several countries. According to a study of hydropower resources in 175
countries, more than 150 have hydropower resources. For 65 of them, hydro produces
more than 50% of electricity; for 24, more than 90% and 10 countries have almost all
their electricity requirements met through hydropower.
Hydro power projects are generally categorized in two segments i.e. small
and large hydro. Different countries are following different norms keeping the upper
limit of small hydro ranging from 5 to 50 MW. The world over, however, there is no
consensus on the definition of small hydropower. Some countries like Portugal, Spain,
Ireland, Greece and Belgium, accept 10 MW as the upper limit for installed capacity.
In Italy the limit is fixed at 3 MW (plants with larger installed power should sell their
electricity at lower prices) and in Sweden 1.5 MW. In France the limit has been
recently established at 12 MW, not as an explicit limit of MHPP, but as the maximum
value of installed power for which the grid has the obligation to buy electricity from
renewable energy sources. In the UK 20MW is generally accepted as the threshold for
small hydro. Though different countries have different criteria to classify hydro power
plants, a general classification of hydro power plants is as follows:
7
Table 1.1 Hydro power plants classification
Type Capacity
Large- hydro More than 100 MW and usually feeding into large electricity grid
Medium-hydro 15-100 MW usually feeding a grid
Small-hydro 1-15 MW usually feeding into a grid
Mini- hydro Above 100KW but below 1MW;either stand alone schemes or
more often feeding into the grid
Micro-hydro From 5KW up to 100KW;usually provided power for small
community or rural industry in remote areas away from grid
Pico-hydro From a few hundred watts up to 5KW
Apart from the above classification, some of the other terms in vogue
nowadays when describing very small hydro power plants are „Pico Hydro‟ (less than
5 kW) and „Tiny Hydro‟ (less than 1kW).Small hydro plants are also classified
according to the “Head” or the vertical distance through which the water is made to
impact the turbines. The usual classifications are given below:
These ranges are not rigid but are merely means of categorizing sites.
Run-of-river schemes
Schemes with the powerhouse located at the base of a dam
Schemes integrated on a canal or in a water supply pipe
8
Most of the small hydro power plants are “run-of-river” schemes, implying that
they do not have any water storage capability. The power is generated only when
enough water is available from the river/stream. When the stream/river flow reduces
below the design flow value, the generation ceases as the water does not flow through
the intake structure into the turbines. Small hydro plants may be stand alone systems
in isolated areas/sites, but could also be grid connected (either local grids or
regional/national grids). The connection to the grid has the advantage of easier control
of the electrical system frequency of the electricity, but has the disadvantage of being
tripped off the system due to problems outside of the plant operator‟s control.
Power generation from water depends upon a combination of head and flow.
Both must be available to produce electricity. Water is diverted from a stream into a
pipeline, where it is directed downhill and through the turbine (flow). The vertical
drop (head) creates pressure at the bottom end of the pipeline. The pressurized water
emerging from the end of the pipe creates the force that drives the turbine. The turbine
in turn drives the generator where electrical power is produced. More flow or more
head produces more electricity. Electrical power output will always be slightly less
than water power input due to turbine and system inefficiencies.
9
1.4 POWER FROM MHPP
To know the power potential of water in a stream it is necessary to know the
flow quantity of water available from the stream (for power generation) and the
available head. The quantity of water available for power generation is the amount of
water (in m3 or liters) which can be diverted through an intake into the pipeline
(penstock) in a certain amount of time. This is normally expressed in cubic meters per
second (m3/s) or in liters per second (l/s). Head is the vertical difference in level (in
meters) through which the water falls down.
The theoretical power (P) available from a given head of water is in exact proportion
to the head and the quantity of water available.
P= Q × H × e × 9.81 (kW) 1.1
Where,
P = Power at the generator terminal, in kilowatts (kW)
H = the gross head from the pipeline intake to the tail water in meters (m)
Q = Flow in pipeline, in cubic meters per second (m3/s)
e = the efficiency of the plant, considering head loss in the pipeline and the efficiency
of the
Turbine and generator, expressed by a decimal (e.g. 85% efficiency= 0.85)
9.81 is a constant and is the product of the density of water and the acceleration due to
gravity
This available power will be converted by the hydro turbine in mechanical power.
10
1.6 SYSTEM LAYOUT
The three types of waterway routes shown below are examples of possible
layouts of micro-hydropower system. The „short penstock‟ option, in most cases, is
considered the most economic scheme, but this is not necessarily the case.
In this case, the penstock is short but the channel is long. The long channel is
exposed to the greater risk of blockage, or of collapse or deterioration as a result of
poor maintenance. Installing the channel across a steep slope may be difficult and
expensive. The risk that the steep slope may erode makes the short penstock layout an
unacceptable option, because the projected operation and maintenance cost of the
scheme could be very expensive, and it may outweigh the benefit of initial purchase
cost.
In this case, the penstock follows the river. If this layout is necessary,
because the terrain would not allow the construction of a channel, certain precautions
must be taken. The most important consideration is to ensure that seasonal flooding of
the river will not damage or deteriorate the penstock. It is also important to calculate
the most economic diameter of penstock; in the case of a long penstock, the cost will
be particularly high.
11
1.9.3 MID-LENGTH PENSTOCK
The mid-length penstock may cost more than the short penstock, but the cost of
constructing channel that can safely cross the steep slope may also be avoided. Even
if the initial purchase and construction costs are greater in this case, this option may
be preferable in case there are signs of instability in the steep slope.
12
CHAPTER 2
HYDRAULIC STRUCTURES
2.1 WEIR & INTAKE
The large majority of small hydro schemes are of the run-of-river type, where
electricity is generated from discharges larger than the minimum required to operate
the turbine. In these schemes a low diversion structure is built on the streambed to
divert the required flow whilst the rest of the water continues to overflow it. When the
scheme is large enough this diversion structure becomes a small dam, commonly
known as a weir, whose role is not to store the water but to increase the level of the
water surface so the flow can enter into the intake. Sometimes, in remote hilly
regions, where annual flooding is common it may be prudent to build temporary weir
using local resources and manpower. The temporary weir is a simple structure at low
cost using local labor, skills and materials. It is expected to be destroyed by annual or
bi-annual flooding. However, advanced planning has to be done for rebuilding of the
weir. The intake of a MHPP is designed to divert only a portion of the stream flow or
the complete flow– depending upon the flow conditions and the requirement. MHPP
schemes use different types of intakes distinguished by the method used to divert the
water into the intake. For MHPP schemes, intake systems are smaller and simpler.
The following three types of intakes have been described here: side intake with and
without a weir and the bottom intake.
Side intake with weir: The weir used in this arrangement can be partly or
completely submerged into the water.
Bottom intake: At a bottom intake the whole weir is submerged into the
water. Excess water will pass the intake by flowing over the weir.
13
2.1.1 SIDE INTAKE HEIGHT CALCULATION
In the case of side intake, following Case (a) or Case (b), whichever is higher, is
adopted.
a. Weir height (D1) determined in relation to the bed elevation of the scour gate of the
Intake weir
D1 = d1 + hi 2.1
b. Weir height (D2) determined by the bed gradient of the settling basin
D2 = d2 + hi+ L (ic – ir) 2.2
Where,
d1: height from the bed of the scour gate to the bed of the inlet (usually 0.5 – 1.0 m)
d2: difference between the bed of the scour gate of the settling basin and the river bed
at the same location (usually around 0.5 m) hi : water depth of the inlet (usually
determined to make the inflow velocity approximately 0.5 – 1.0 m/s)
L: length of the settling basin ic: inclination of the settling basin bed (usually around
1/20 – 1/30) ir: present inclination of the river
14
Figure 2.2 Sectional view of Tyrolean intake and weir
15
material, the greater the friction loss and higher is the elevation difference needed
between channel entry and exit. In hilly regions it is common that the power channel
would have to cross small streams. In such situations it is often prudent to build a
complete crossing over the channel, as during rainy season, flash floods and/or
rocks/mud may block the channel or worse still, wash away sections of the channel.
Sometimes just the provision of a drain running under the channel (in case of very
small streams along stable slope) is usually adequate.
16
Where;
Qd: design discharge for headrace (m3/s)
A: area of cross section (m2)
R: R=A/P (m)
P: length of wet sides (m) refers to next figure.
SL: longitudinal slope of headrace (e.g. SL= 1/100=0.01)
n: coefficient of roughness
17
Each of these sections has the following function.
Conduit section: Conduit section connects the intake with the settling basin.
It is necessary that the conduit section should be curtailing its length.
Widening section: This regulates water flow from the conduit channel to
prevent the occurrence of whirl pools and turbulent flow and reduces the flow
velocity inside the settling basin to a predetermined.
Settling section: This section functions to settle sediment above a certain size
and its required length (l) is calculated by the following formula based on the
relation between the settling speed, flow velocity in the settling basin and
water depth.
The length of the settling basin (Ls) is usually determined so as to incorporate a
margin to double the calculated length by the said formula
2.5
Where
l: minimum length of settling basin (m)
hs: water depth of settling basin (m)
U: marginal settling speed for sediment to be settled (m/s) usually around 0.1 m/s for
a target grain size of 0.5 – 1 mm.
V: mean flow velocity in settling basin (m/s) usually around 0.3 m/s but up to 0.6 m/s
is tolerated in the case where the width of the settling basin is restricted.
V = Qd/(B×hs) 2.6
Qd: design discharge (m3/s)
B: width of settling basin (m)
Sediment pit: This is the area in which sediment is deposited
2.2.4 SPILLWAYS
Spillways along the power channel are designed to permit overflow at
certain points along the channel. The spillway acts as a flow regulator for the channel.
During floods the water flow through the intake can be twice the normal channel
flow, so the spillway must be large enough to divert this excess flow. The spillway
can also be designed with control gates to empty the channel. The spillway should be
18
designed in such a manner that the excess flow is fed back to the river without
damaging the foundations of the channel.
Spillway drains the submerged inflow which flows from the intake. The sizes of
spillway will
be decided by following equation.
Qf= C×Bsp×hsp1.5 →hsp={Qf /(C×Bsp)}1/1.5 2.7
Where
Qf: inflow volume of submerged orifice (m3/s, see Figure 2.4)
C: coefficient =1.80
hsp: water depth at the spillway (m, see Figure 2.4)
Bsp: width of the spillway (m, see Figure 2.4)
19
Head tank capacity
Vsc = As×dsc=B×L×dsc 2.8
where
As: area of head tank
B : width of head tank
L: length of head tank
dsc: water depth from uniform flow depth of a headrace when using maximum
discharge (h0) to critical depth from top of a dike for sand trap in a head tank (hc)
In oblong section, uniform flow depth:
ho=H×0.1/(SLE)0.5 2.9
SLe: slope of tail end of the headrace
critical depth:
hc= {(α×Qd2) /(g×B2)}1/3 2.10
α: 1.1 g : 9.8
2.4 PENSTOCK
The penstock is the pipe which conveys water under pressure from the FBT to
the turbine. Penstock is a significant component of the MHPP scheme and needs to be
designed and selected carefully as it represents a major expense in the total budget
(for some high head installations this alone could cost as much as 30% of the total
costs). Here the main aspects to consider are head loss and capital cost. Head loss due
to friction in the pipe decreases dramatically with increasing pipe diameter.
Conversely, pipe costs increase steeply with diameter. Therefore a compromise
between cost and performance is considered for design and selection of pipe diameter
and material.
While designing penstocks, the first principle is to identify available pipe
options and then to decided upon acceptable head loss (5% of the gross head is
generally considered). The details of the pipes of various materials and diameters with
losses close to this target are then tabulated and compared for cost effectiveness. A
smaller penstock may be lighter on pocket, but the extra head loss may account for
lost revenue from generated electricity each year.
21
accessibility of the site
likelihood of structural damage availability
surface roughness,
design life and maintenance
method of jointing design pressure
Relative cost.
The following materials can be considered for use as penstock pipes in micro hydro
schemes:
wooden planks or tree bark (for very small installations)
Spun ductile iron
GI Pipes
mild steel,
unclassified polyvinyl chloride (UPVC),
high density polyethylene (HDPE),
asbestos cement,
Pre stressed concrete,
Glass reinforced plastic (GRP).
Mild steel, UPVC and HDPE are the most common used materials.
2.11
Where
T0: minimum thickness of pipe
P: design water pressure i.e. hydrostatic pressure + water hammer (kgf/cm2), in
Micro-hydro scheme P=1.1×hydrostatic pressure.
For instance, if the head (Hp, refer to following figure) which from FBT to
22
Turbine is 25m, P=2.5×1.1=2.75 kgf/cm2.
d: inside diameter (cm)
θa: admissible stress (kgf/cm2) SS400: 1300kgf/cm2
η: welding efficiency (0.85~0.9)
δt: margin (0.15cm in general)
The diameter is selected as the result of a trade-off between penstock cost and
power losses. A simple criterion for diameter selection is to limit the head loss to a
certain percentage. Loss in power of 4% is usually acceptable. A more rigorous
approach is to select several possible diameters, computing power and annual energy.
The present value of this energy loss over the life of the plant is calculated and plotted
for each diameter. In the other side the cost of the pipe for each diameter is also
calculated and plotted. Both curves are added graphically and the optimum diameter
would be that closest to the theoretical optimum. Actually the main head loss in a
pressure pipe are friction losses; the head losses due to turbulence passing through the
trashrack, in the entrance to the pipe, in bends, expansions, contractions and valves
are minor losses. Consequently a first approach will suffice to compute the friction
losses, using for example the Manning equation
2.12
2.13
2.14
Pipes are generally available in standard lengths (it is easier for transportation
also) and have to be joined together on site. There are several methods of joining
23
penstock pipes and the factors to be considered when choosing the best joint system
for a particular scheme are:
pipe material,
whether any degree of joint flexibility is required,
ease of installation
skill level of personnel,
Costs.
Generally, the pipes are joined by one of the following four methods:
flanged,
spigot and socket,
mechanical,
Welded.
24
built of rubble masonry or cement concrete. Sometimes, the anchor blocks may need
steel reinforcement (for long pipelines).
25
2.13
Where,
hc: water depth at after bay (m)
Qd: design discharge (m3/s)
b: width of tailrace channel (m)
The water level at the after bay should be higher than estimated flood water level.
Then in case of impulse turbine, the head between the center of turbine and water
level at the outlet became head loss.
26
Figure 2.8 Foundation of Powerhouse for Reaction turbine
27
CHAPTER 3
ELECTRO-MECHANICAL EQUIPMENT
3.1 HYDRAULIC TURBINES
Turbine is the main piece of equipment in the MHPP scheme that
converts energy of the falling water into the rotating shaft power. The selection of the
most suitable turbine for any particular hydro site depends mainly on two of the site
characteristics – head and flow available. All turbines have a power-speed
characteristic. This means they will operate most efficiently at a particular speed, head
and flow combination. Thus the desired running speed of the generator or the devices
being connected/ loading on to the turbine also influence selection. Other important
consideration is whether the turbine is expected to generate power at part-flow
conditions. The design speed of a turbine is largely determined by the head under
which it operates. Turbines can be classified as high head, medium head or low head
machines. They are also classified by the operating principle and can be either
impulse or reaction turbines. The basic turbine classification is given in the table
below:
Table 3.1 Turbine types
Type High Head Medium Head Low Head
28
The potential energy in the water is converted into mechanical energy in the turbine,
by one of two fundamental and basically different mechanisms:
The water pressure can apply a force on the face of the runner blades, which
decreases as it proceeds through the turbine. Turbines that operate in this way
are called reaction turbines. The turbine casing, with the runner fully
immersed in water, must be strong enough to withstand the operating pressure.
The water pressure is converted into kinetic energy before entering the runner.
The kinetic energy is in the form of a high-speed jet that strikes the buckets,
mounted on the periphery of the runner. Turbines that operate in this way are
called impulse turbines. As the water after striking the buckets falls into the
tail water with little remaining energy, the casing can be light and serves the
purpose of preventing splashing.
29
the runner is lost and so the buckets are designed to keep exit velocities to a
minimum. The turbine casing only needs to protect the surroundings against water
splashing and therefore can be very light.
30
be prevented for effective operation. A Turgo runner looks like a Pelton runner split
in half. For the same power, the Turgo runner is one half the diameter of the Pelton
runner, and so twice the specific speed. The Turgo can handle a greater water flow
than the Pelton because exiting water doesn't interfere with adjacent buckets.
31
Figure 3.3 CFT
CFTs are also often constructed as two turbines of different capacity that share
the same shaft. The turbine wheels are the same diameter, but different lengths to
handle different volumes at the same pressure. The subdivided wheels are usually
built with volumes in ratios of 1:2. The subdivided regulating unit (the guide vane
system in the turbine's upstream section) provides flexible operation, with ⅓, ⅔ or
100% output, depending on the flow. Low operating costs are obtained with the
turbine's relatively simple construction. The water flows through the blade channels in
two directions: outside to inside, and inside to outside. Most turbines are run with two
jets, arranged so that the two water jets in the runner will not affect each other. It is,
however, essential that the turbine, head and turbine speed are harmonized. The
turbine consists of a cylindrical water wheel or runner with a horizontal shaft,
composed of numerous blades (up to 37), arranged radially and tangentially. The edge
of the blades is sharpened to reduce resistance to the flow of water. A blade is made in
a part-circular cross-section (pipe cut over its whole length). The ends of the blades
are welded to disks to form a cage like a hamster cage and are sometimes called
"squirrel cage turbines"; instead of the bars, the turbine has trough-shaped steel
blades.
32
Figure 3.4 Horizontal/vertical inflows in CFT
The water flows first from the outside of the turbine to its inside. The
regulating unit, shaped like a vane or tongue, varies the cross-section of the flow.
These divide and direct the flow so that the water enters the runner smoothly for any
width of opening. The guide vanes should seal to the edges of the turbine casing so
that when the water is low, they can shut off the water supply. The guide vanes
therefore act as the valves between the penstock and turbine. The water jet is directed
towards the cylindrical runner by a fixed nozzle. The water enters the runner at an
angle of about 45 degrees, transmitting some of the water's kinetic energy to the
active cylindrical blades. The turbine geometry (nozzle-runner-shaft) assures that the
water jet is effective. The water acts on the runner twice, but most of the power is
transferred on the first pass, when the water enters the runner. Only ⅓ of the power is
transferred to the runner when the water is leaving the turbine.
The cross-flow turbine is of the impulse type, so the pressure remains constant
at the runner. The peak efficiency of a CFT is somewhat less than a Kaplan, Francis
or Pelton turbine. However, the CFT has a flat efficiency curve under varying load.
With a split runner and turbine chamber, the turbine maintains its efficiency while the
flow and load vary from 1/6th to the maximum.
The CFTs are mostly used in mini and micro hydropower units less than 2
MW and with heads less than 200 m, since it has a low price and good regulation.
Particularly with small run-of-the-river schemes, the flat efficiency curve yields better
performance than other turbine systems, as flow in small streams varies seasonally.
The efficiency of a turbine is determined whether electricity is produced during the
periods when rivers have low heads. Due to its better performance even at partial
loads, the CFT is well-suited to stand-alone electricity generation. It is simple in
construction and that makes it easier to repair and maintain than other turbine types.
33
Another advantage is that the CFTs gets cleaned as the water leaves the runner
(small sand particles, grass, leaves, etc. get washed away), preventing losses. So
although the turbine's efficiency is somewhat lower, it is more reliable than other
types. Other turbine types get clogged easily, and consequently face power losses
despite higher nominal efficiencies.
35
not possible with Francis turbines. Kaplan turbines are widely used in high-flow, low-
head power production.
The Kaplan turbine is an inward flow reaction turbine, which means that the
working fluid changes pressure as it moves through the turbine and gives up its
energy. The design combines radial and axial features. The inlet is a scroll-shaped
tube that wraps around the turbine‟s wicket gate. Water is directed tangentially
through the wicket gate and spirals on to a propeller shaped runner, causing it to spin.
The outlet is a specially shaped draft tube that helps decelerate the water and recover
kinetic energy.
The turbine does not need to be at the lowest point of water flow, as long as the
draft tube remains full of water. A higher turbine location, however, increases the
suction that is imparted on the turbine blades by the draft tube that may lead to
cavitations due to the pressure drop. Typically the efficiencies achieved for Kaplan
turbine are over 90%, mainly due to the variable geometry of wicket gate and turbine
blades. This efficiency however may be lower for very low head applications. Since
the propeller blades are rotated by high-pressure hydraulic oil, a critical design
element of Kaplan turbine is to maintain a positive seal to prevent leakage of oil into
the waterway.
Kaplan turbines are widely used throughout the world for electrical power
production. They are especially suited for the low head hydro and high flow
conditions – mostly in canal based MHPP sites. Inexpensive micro turbines can be
manufactured for specific site conditions (e.g. for head as low one meter). Large
Kaplan turbines are individually designed for each site to operate at the highest
possible efficiency, typically over 90%. They are very expensive to design,
manufacture and install, but operate for decades.
36
3.4 PUMPS WORKING AS TURBINES
Centrifugal pumps can be used as turbines by passing water through them in
reverse. The potential advantages are the lower costs due to mass production (also
local production), the availability of spare parts and the wider dealer/support
networks. The disadvantages are that their performance characteristics have not been
studied extensively and these poor part-flow efficiencies. Pumps as turbines have
been used at several locations but the technology still remains unproven.
37
turbines. Once the gross head is known, the net head can be computed by simply
subtracting the losses along its path. The first criterion to take into account in the
turbines selection is the net head. Table 3.2 specifies for each turbine type its range of
operating heads. The table shows some overlapping, so that for a certain head several
types of turbines can be used.
38
As a turbine can only accept discharges between the nominal and the practical
minimum, it may be advantageous to install several smaller turbines instead of a one
large. The turbines would be sequentially started, so all of the turbines in operation
except one will operate at their nominal discharges and therefore will exhibit a higher
efficiency. Using two or three smaller turbines will mean a lower unit weight and
volume and will facilitate transport and assembly on the site. The rotational speed of a
turbine is inversely proportional to its diameter, so its torque will be lower and the
speed increaser smaller and more reliable. The use of several turbines instead of one
large one with the same total power will result in a lower ratio kilogram of
turbine/cubic meter of operating flow, although the ratio equipment cost / cubic meter
of operating flow will be larger. Increasing the number of turbines decreases the
diameter of their runners, and consequently the support components in the
powerhouse will be smaller and lighter. As the water conduits are identical the
formwork, usually rather sophisticated, can be reused several times decreasing its
influence in the concrete cost. Notwithstanding this, generally more turbines means
more generators, more controls, higher costs.
3.5.2 DISCHARGE
The rated flow and net head determine the set of turbine types applicable to
the site and the flow environment. Suitable turbines are those for which the given
rated flow and net head plot within the operational envelopes. A point defined as
above by the flow and the head will usually plot within several of these envelopes. All
of those turbines are appropriate for the job, and it will be necessary to compute
installed power and electricity output against costs before taking a decision. It should
be remembered that the envelopes vary from manufacturer to manufacturer and they
should be considered only as a guide.
39
Table 3.3 Turbine Application Chart
3.1
Where,
Ns: Specific speed [m-kW]
N: Rotation speed [min-1]
P: Turbine output [kW]
H: Effective head [m]
The proper range of the specific speed has already been known as shown in
Table 3.4.The rotation speed of the turbine is limited. Therefore, it should be checked
whether the specific speed is within the proper range. The larger the rotation speed is,
the smaller the equipment is. The small equipment shall reduce the equipment cost. In
addition, the rotation speed affects draft head.
40
Table 3.4 Range of Ns
Turbine type Range of Ns(m-kW)
Pelton 8-25
Francis 50-350
Diagonal flow 100-350
Propeller 200-900
Tubular More than 500
3.5.4 CAVITATION
When the hydrodynamic pressure in a liquid flow falls below the vapor
pressure of the liquid, there is a formation of the vapour phase. This phenomenon
induces the formation of small individual bubbles that are carried out of the low-
pressure region by the flow and collapse in regions of higher pressure. The formation
of these bubbles and their subsequent collapse gives rise to what is called cavitations.
Experience shows that these collapsing bubbles create very high impulse pressures
accompanied by substantial noise (in fact a turbine undergoing cavitations sounds as
though gravel is passing through it). The repetitive action of such pressure waves
close to the liquid-solid boundary results in pitting of the material. With time this
pitting degenerates into cracks formed between the pits and the metal is spilled from
the surface. In a relatively short time the turbine is severely damaged and will require
being shut-off and repaired If possible.
Experience shows that there is a coefficient, called Thomas sigma, which defines
precisely enough under which parameters cavitations takes place.
This coefficient is given by the equation
3.2
Where
Hsv is the net positive suction head and H the net head of the scheme
3.3
Where,
Hsv is the net positive suction head
Hatm is the atmospheric pressure head
41
Hatm is the water vapor pressure
Z is the elevation above the tail water surface of the critical location
Ve is the average velocity in the tailrace
Hl is the head loss in the draft tube
Neglecting the draft-tube losses and the exit velocity head loss,
Thomas sigma will be given by
3.4
To avoid cavitations the turbine should be installed at least at a height over the
tailrace water level Zp given by the equation
3.5
The Thomas sigma is usually obtained by a model test, and it is a value furnished by
the turbine manufacturer. Notwithstanding the above mentioned statistic studies also
relates Thomas sigma with the specific speed. There under are specified the equation
giving óT as a function of ns for the Francis and Kaplan turbines
It must be remarked that Hvap decreases with the altitude, from roughly 10.3 m at the
sea level to 6.6 m at 3000 m above sea level. So then a Francis turbine with a specific
speed of 150, working under a 100 m head (with a corresponding ó T = 0.088), that in
a plant at sea level, will require a setting:
z = 10.3 - 0.09 - 0.088 x 100 = 1.41 m
Installed in a plant at 2000 m above the sea level will require
z = 8.1-0.09 - 0.088 x 100 = -0.79 m
A setting requiring heavy excavation
3.5.5 ROTATIONAL SPEED
The rotational speed of a turbine is a function of its specific speed, and of the
scheme power and net head. In the small hydro schemes standard generators should
be installed when possible, so in the turbine selection it must be borne in mind that the
turbine, either coupled directly or through a speed increaser, should reach the
synchronous speed, as given in table 3.5
42
Table 3.5 Generator synchronization speed
43
shaft speed of the generator shaft and the speed of the turbine are compatible. The
advantages of this type of system are low maintenance, high efficiency and low cost.
• “V” or wedge belts and pulleys: This is the most common choice for micro-
hydropower systems. Belts for this type of system are widely available because they
are used extensively in all kinds of small industrial machinery.
• Timing belt and sprocket pulley: These drives are common on vehicle camshaft
drives and use toothed belts and pulleys. They are efficient and clean-running and are
especially worth considering for use in very small system drives (less than 3 kW)
where efficiency is critical.
• Gearbox: Gearboxes are suitable for use with larger machines when belt drives
would be too cumbersome and inefficient. Gearboxes have problems regarding
specification, alignment, maintenance and cost, and this rules them out for micro-
hydropower systems except where they are specified as part of a turbine-generator set.
3.7 GENRATOR
Generators transform mechanical energy into electrical energy. Although most
early hydroelectric systems were of the direct current variety to match early
commercial electrical systems, nowadays only three-phase alternating current
generators are used in normal practice. Two types of current are produced by
electrical generators, either alternating current (AC) or direct current (DC). In the case
of AC the voltage cycles sinusoidally with time, from positive peak value to negative.
Because the voltage changes its sign the resulting current also continually reverses
direction in a cyclic pattern. DC current flows in a single direction as the result of a
steady voltage. DC is not usually used in modern power installations except for very
low-powered systems of a few hundred watts or less.
Alternating voltage can be produced in a stationery coil or armature by a
rotating magnetic field, but more usually a coil is rotated in a stationary magnetic
field. The magnetic field can be produced either by a permanent magnet or by another
coil (i.e., an electro-magnet) know as a field coil which is fed by direct current known
as the excitation current. A generator supplying alternative current is described as an
alternator to distinguish it from a machine designed to supply DC current which is
known as a DC generator or dynamo. Current flows when a voltage difference is
place across a conducting body. In AC circuits the magnitude and timing of the
44
current cycle relative to the voltage cycle will depend on whether the conductivity
body is resistance, inductive, capacitive or some combination of these elements.
45
its reactive power from a separate source such as a bank of capacitors. The mains
supply defines the frequency of the stator rotating flux and hence the synchronous
speed above which the rotor shaft must be driven. On start-up, the turbine is
accelerated up to 90-95% of the synchronous speed of the generator, when a velocity
relay closes the main line switch. The generator passes immediately to hyper-
synchronism and the driving and resisting torque are balanced in the area of stable
operation.
3.7.3 EXCITERS
The exciting current for the synchronous generator can be supplied by a small
DC generator, known as the exciter, to be driven from the main shaft. The power
absorbed by this dc generator amounts to 0.5% - 1.0% of the total generator power.
Nowadays a static exciter usually replaces the DC generator, but there are still many
rotating exciters in operation.
Rotating exciters: The field coils of both the main generator and the exciter
generator are usually mounted on the main shaft. In larger generators a pilot
exciter is also used. The pilot exciter can be started from its residual magnetic
field and it then supplies the exciting current to the main exciter, which in turn
supplies the exciting current for the rotor of the generator. In such way the
current regulation takes place in the smaller machine.
Brushless exciters: A small generator has its field coils on the stator and
generates AC current in the rotor windings. A solid state rectifier rotates with
the shaft, converting the AC output from the small generator into the DC
which is the supplied to the rotating field coils of the main generator without
the need of brushes. The voltage regulation is achieved by controlling the
current in the field coils of the small generator.
Static exciters: The exciting current is taken out, via a transformer, from the
output terminals of the main generator. This AC current is then rectified in a
solid state rectifier and injected in the generator field coils. When the
generator is started there is no current flowing through the generator field
coils. The residual magnetic field, aided if needed by a battery, permits
generation to start to be then stabilized when the voltage at the generator
terminals reaches a preset value. This equipment is easy to maintain has a
46
good efficiency and the response to the generator voltage oscillations is very
good.
47
3.8.1 SPEED GOVERNORS
A governor is a combination of devices and mechanisms, which detect speed
deviation and convert it into a change in servomotor position. A speed-sensing
element detects the deviation from the set point; this deviation signal is converted and
amplified to excite an actuator, hydraulic or electric, that controls the water flow to
the turbine. In a Francis turbine, where to reduce the water flow you need to rotate the
wicket-gates a powerful governor is required to overcome the hydraulic and frictional
forces and to maintain the wicket-gates in a partially closed position or to close them
completely. Several types of governors are available varying from purely mechanical
to mechanical hydraulic to electro hydraulic. The purely mechanical governor is used
with fairly small turbines, because its control valve is easy to operate and does not
require a big effort. These governors use a fly ball mass mechanism driven by the
turbine shaft. The output from this device .the fly ball axis descends or ascends
according to the turbine speed- directly drive the valve located at the entrance to the
turbine.
48
The most commonly-used type is the oil-pressure governor (Fig 3.7) that also
uses a fly ball mechanism lighter and more precise than that used in a purely
mechanical governor. When the turbine is overloaded, the fly balls slowdown, the
balls drop, and the sleeve of the pilot valve rise to open access to the upper chamber
of the servomotor. The oil under pressure enters the upper chamber of the servomotor
to rotate the wicket-gates mechanism and increase the flow, and consequently the
rotational speed and the frequency.
In an electro hydraulic governor a sensor located on the generator shaft
continuously senses the turbine speed. The input is fed into a summing junction,
where it is compared to a speed reference. If the speed sensor signal differs from the
reference signal, it emits an error signal (positive or negative) that, once amplified, is
sent to the servomotor so this can act in the required sense. In general the actuator is
powered by a hydraulic power unit consisting of a sump for oil storage, an electric
motor operated pump to supply high pressure oil to the system, an accumulator where
the oil under pressure is stored, oil control valves and a hydraulic cylinder. All these
regulation systems, as have been described, operate by continuously adjusting back
and forth the wicket-gates position. To provide quick and stable adjustment of the
wicket-gates, and/or of the runner blades, with the least amount of over or under
speed deviations during system changes a further device is needed. In oil pressure
governors, as may be seen in figure 3.7, this is achieved by interposing a .dash pot.
that delays the opening of the pilot valve. In electro hydraulic governors the degree of
sophistication is much greater, so that the adjustment can be proportional, integral and
derivative (PID) giving a minimum variation in the controlling process.
An asynchronous generator connected to a large net, from which it takes its
reactive power to generate its own magnetism, does not need any controller, because
its frequency is controlled by the mains. Notwithstanding this, when the generator is
disconnected from the mains the turbine accelerates up to runaway speed with
inherent danger for the generator and the speed increaser, if one is used. In such a case
it is necessary to interrupt the water flow, rapidly enough to prevent the turbine
accelerating, but at the same time minimizing any water hammer effect in the
penstock.
To ensure the control of the turbine speed by regulating the water flow,
certain inertia of the rotating components is required. Additional inertia can be
provided by a flywheel on the turbine or generator shaft. When the main switch
49
disconnects the generator the power excess accelerates the flywheel; later, when the
switch reconnects the load, the deceleration of this inertia flywheel supplies additional
power that helps to minimize speed variation. The basic equation of the rotating
system is the following:
3.6
Where,
J = moment of inertia of the rotating components
W = angular velocity
Tt = torque of turbine
TL= torque due to load
When Tt is equal to TL, dW/dt = 0 and W = constant, so the operation is steady.
When Tt is greater or smaller than TL, W is not constant and the governor must
intervene so that the turbine output matches the generator load. But it should not be
forgotten that the control of the water flow introduces a new factor: the speed
variations on the water column formed by the waterways.
The flywheel effect of the rotating components is stabilizing whereas the water
column effect is destabilizing. The start-up time of the rotating system, the time
required to accelerate the unit from zero rotational speed to operating speed is given
by
3.7
Where the rotating inertia of the unit is given by the weight of all rotating parts
multiplied by the square of the radius of gyration: WR2, P is the rated power in Kw
and n the turbine speed (rpm)
The water starting time, needed to accelerate the water column from zero velocity to
some other velocity V, at a constant head H is given by:
3.8
50
Where,
H = gross head across the turbine (m)
L = length of water column (m)
V = velocity of the water (m/s)
g = gravitational constant (9.81 m s-2)
To achieve good regulation is necessary that Tm/Tw > 4. Realistic water starting
times do not exceed 2.5 sec. If it is larger, modification of the water conduits must be
considered either by decreasing the velocity or the length of the conduits by installing
a surge tank. The possibility of adding a flywheel to the generator to increase the
inertia rotating parts can also considered. It should be noted that an increase of the
inertia of the rotating parts will improve the water hammer effect and decrease the
runaway speed.
51
CHAPTER 4
52
4.2 FEASIBILITY STUDY
A pre-feasibility study is carried out to determine whether the site is worth
further investigation. This study could involve visiting a site to measure head and
flow rate, or it could simply be a map study. If the site looks promising, the next step
is to carry out a full-scale, detailed feasibility study. Information collected by this
study should be of the highest quality and should be accurate enough to permit a full
technical design of the project without further visit. A feasibility study includes a site
survey and investigation, a hydrological assessment, an environmental assessment, the
project design, a detailed cost estimate and the final report. The depth of study will
depend largely on the size and complexity of the system. For a small system such as a
battery-based system, the feasibility study can be less rigorous than for a larger
system.
Carrying out a feasibility study is highly technical. Unless one has a strong
background and experience in the area, it is best left to professional consultants or
energy experts.
53
4.3 PRELIMINARY SITE SURVEY
The objective of preliminary site survey for micro-hydro is to investigate a
potential site and supply area in order to roughly evaluate the feasibility of projects
and get information on electrification planning around the site in the case of off-grid
project or existing transmission facilities (and/or planned transmission line) to be
interconnected in the case of on-grid project. One of the most important activities in
preliminary site survey is to measure water discharge and head that could be utilized
for micro/small-hydropower generation. Investigations of intake site, waterway route,
powerhouse site and transmission route etc. are also conducted to assess the feasibility
of project sites. In the case of off-grid project, power demand survey is also important
in the planning of the electrification system. Socio-economic data such as number of
households and public facilities in supply area, availability of local industries which
will use electricity, solvency of local people for electricity and the acceptability of
local people to the electrification scheme are gathered during the preliminary site
survey.
Basic items to be investigated in a preliminary site survey are:
Potential capacity of the project site
Measurement of river flow
Measurement of head
Topographical and geological condition of the sites for the structure layout
Accessibility to the site
In the case of off-grid project:
Power demand in the load center
Distance from the load center to the power house
Ability of the local people to pay for electricity
Willingness of the local people for electrification
In the case of on-grid project:
Distance from existing transmission facilities (and/or planned transmission
line) to the power house.
54
4.4 Survey to Outline the Project Site
During the reconnaissance at the proposed site of power generating facilities and
around the power demand area, a survey should be conducted on the following items:
55
4.4.3 STRUCTURE SITE INVESTIGATION
Taking into account the requirements for structure layout, an investigation at
each facility site is conducted as follows;
(1) Intake site
To determine the approximate location of the weir and intake
To draw sketches and to take photographs
(2) Headrace
To measure the head and length of waterway route
To investigate the surrounding conditions
To draw sketches and/or to take photographs
Photographs of the site
(3) Forebay/Head tank and Penstock
To investigate the forebay site
Suitable location for the forebay site
Adequate space for construction
To investigate the penstock route
Length of the penstock measured with distance meter or measuring tape
Geological and topographical conditions
(4) Power house
To investigate the slope condition. Unstable slopes, such as landslides or
collapses behind the powerhouse site
To measure the approximate location
Head between forebay and powerhouse measured with sight meter (hand-
level)and distance meter
To investigate the land use conditions, Location of artificial structures near the
powerhouse site, if any
To investigate tailrace route
Location of tailrace outlet
Length of tailrace measured with a measuring tape
To take photographs and draw sketches
56
(5) Transmission/Distribution Line
To survey the geological and topographical conditions from the powerhouse
site to the load center
To select a transmission line along existing road or foot path
To measure the length of the transmission route
To trace transmission line on maps
To take photographs and draw sketches of powerhouse site
Container method
Float method
Weir method
Current meter method
57
The rate that the container fills is the flow rate, which is calculated simply by dividing
the volume of the container by the filling time. Flows of up to20 LPs can be measured
using a 200-litre container such as an oil drum.
58
Figure 4.4 flow measuring weir method
59
then be reduced by correction factor, which estimates the mean velocity as opposed to
the surface velocity. By multiplying averaged and corrected flow velocity, the volume
flow rate is estimated. This method provides only an approximate estimate of the
flow. Approximate correction factors to convert measured surface velocity to mean
velocity are as follows:
Cross-Sectional Area
Now we can measure and calculate the cross-sectional area of a „slice‟ of the
water. In the segment used above for determining water speed, select a spot that will
provide a representative water depth and width for the 50 ft. segment. Measure and
record the water depth at one foot increments along a cross section (water-edge to
water-edge) of the river or stream at this spot. Laying a log or plank across the river or
stream from which you can take these measurements is convenient. You can also
wade (or boat) across but take care that you are measuring the actual water depth and
not the depth of water affected by your presence in the water. Calculate the average
depth of the water (as explained above during water speed).Measure and record the
width of the river or stream (in feet and from water-edge to water edge).Multiply the
average depth X the width. You now have the cross-sectional area (in square feet) of
that „slice‟ of the river or stream.
60
Figure 4.5 flow measuring Float method
Calculating Flow
The following equation is used to calculate Flow.
Water Speed (ft/sec) X Cross Sectional Area (sq ft) =Flow (cubic feet per second) X
450 = Flow (gallons per minute)
Calculate the flow in cubic feet/second first by multiplying the average speed (in feet
per second) X the cross-sectional area (in square feet). Then convert the flow from
cubic feet per second to gallons per minute (GPM) by multiplying the cubic feet per
second X 450.
61
4.6.1 CLEAR HOSE METHOD
The figure below shows this method. The method is useful for low head sites,
since it is cheap and reasonably accurate. To get the head of two points, measure the
difference of water level of the water-filled clear hose at two points. Even a man who
does not have a skill of survey work can apply this method.
62
4.6.3 Sighting meter method
Hand-hold sighting meters measure angle of inclination of a slope (they are
often called clinometers or Abney levels). A head is calculated by the following
formula using a vertical angle that is measured by a hand-hold sighting meter, and a
hypotenuse distance measured by tape measure.
H=L× sinθ
H: Head L: Hypotenuse distance θ: Vertical angle
63
And for average Depth (Davr):
D1 = 7 inches D3 = 7 inches D5 = 6 inches
D2 = 6.5 inches D4 = 5 inches
Therefore
Davg = 6.3 inches (0.16002meter)
Now Area (A1):
A1 = Davg × Wavg
A1 = 0.6879 × 0.16002
A1 = 0.11007 m2
Next step is to find the average time (Tavg) of the float to covered the marked distance
L1
T1 =14.97 sec T3 = 14.47 sec
T2 = 15 sec T4 = 14.55sec
Therefore
Tavg= 14.74 sec
Speed of flowing water is given by
V1 = L1/Tavg
V 1= 14.6304/14.74
V1 = 0.9920 meter/sec
So Flow Rate (Q1) is
Q1 = A1 × V1
Q1 = 0.11007 × 0.9920
Q1 = 0.1091 m3/sec
Q1 = 0.11m3/sec
Flow Rate (Q2) at the start of HRC:
The same method is repeated for finding flow rate at start of HRC.
Total length (L2) = 31 ft (9.448 meter)
Width & Depth of the channel for the selected length is measured at different
position
W1 = 31 inches W3 = 28.8 inches
W2 = 30 inches W4 = 29 inches
Therefore
Wavg = 29.7 inches (0.754meter)
64
And for average Depth (Davg):
D1 = 7 inches D3 = 6.2 inches D5 = 6.9 inches
D2 = 6.5 inches D4 = 5 inches
Therefore
Davr = 6.32 inches (0.160meter)
Now Area (A2):
A2 = Davg × Wavg
A2 = 0.160 × 0.754
A2 = 0.121 m2
Now we find the average time (Tavg) of the float to covered the measured distance L2
T1 =7.5 sec T3 = 9 sec T5 = 8 sec
T2 = 7 sec T4 = 8.5sec
Therefore
Tavrg= 8 sec
Speed of flowing water is given by
V2 = L2/Tavg
V 2= 9.448 /8
V1 = 1.1811 meter/sec
And the Flow Rate (Q2) is
Q2 = A2 × V2
Q2 = 0.121 × 1.1811
Q2 = 0.1429 m3/sec (actual discharge)
Loss of Flow Rate in HRC:
Q = Q2 – Q1
Q = 0.1429 – 0.1091
Q = 0.0338 m3/sec
65
H = H1 + H2 + H3 + H4 + H5 + H6
H = 88 + 96 +120 +108 + 90 + 84
H = 586 inches (14.9 m)
Head loses: Due to wrong position of penstock with FBT
H1 = 88 inches (2.235m)
66
4.8.3 POWER LOSSES
Power loses in HRC:
Plos = ρQHg
Plos = 1000 × 0.0338 × 14.9 × 9.8
P los = 4935 watts
Plos = 4.9 kw
Power loss due to head:
Plos = ρQHg
Plos = 1000 × 0.1429 × 2.235 × 9.8
Plos = 3.16 kw
Total power loss:
Plos/total = 4.9 + 3.16
Plos/tota = 8.06 kw
67
CHAPTER 5
RECOMMENDATIONS FOR ENHANCING
EFFICIENCY AND COST ESTIMATE
The calculated efficiency is 21% which is far below the optimum range 60-
75%. The much lower efficiency depicts serious shortcomings in the installed plant.
Careful calculations and analysis portray limitations in the following areas.
68
5.2 WEIR
Weir is not properly designed and built since stones, wood logs and sands are
raw materials used. A medium level flow in rainy days could ruin the weir and it is
routine for the locals to built it again and again when flow in the stream increases.
To ensure stable flow even in rainy days, the weir must be made with concrete,
having steel fixers.
5.4 PENSTOCK
It is the part which counts for almost 30% of the overall cost of the turbine.
The sizing is awesome i.e. having 30 inches diameter but little bit leakage is there
from penstock which requires minimal maintenance.
5.5 TURBINE
Old version of cross flow turbine is installed. Major shortcomings are;
Excessive leakage due to large clearance volume between casing and rotor
blades.
Rough outer and interior periphery. Blades are not smoothly fabricated and
also the absence of well design trash rack and screens added more to this
misery.
69
Inaccurate balding.
Excessive leakage from the nozzle
Absence of Draft tube
Difficulty in maintenance and cleaning due to complex assembly.
The old version of CFT must be replaced with the latest design cross flow
turbine having minimal clearance volume, sealing and fine blades. In the international
market, comparatively low cost and easily available choice would be T15 turbine
made by ENTEC. This firm has given license to manufacturers in Pakistan. Salient
features of the turbine are:
High precision fabrication of runner cylinder, laser cut slide disks and
exceptionally fine blading drawn from bright steel.
70
Due to these salient features the organization claims efficiency of the turbine after
testing as:
To cope with the problem, one should either install mechanical governor or
ELC (Electronic load controller). Practical experience depicts that mechanical
governor in MHPPPs often fails. So a viable alternative is ELC.
71
An ELC is a solid-state electronic device designed to regulate output power of
a micro-hydropower system. Maintaining a near-constant load on the turbine
generates stable voltage and frequency. ELCs can also be used as a load-management
system by assigning a predetermined prioritized secondary load, such as water
heating, space heating or other loads. In this way, one can use the available power
rather than dumping it into the ballast load. Without an ELC, the frequency will vary
as the load changes and, under no-load conditions, will be much higher than rated
frequency. ELCs react so fast to load changes that speed changes are not even
noticeable unless a very large load is applied. The major benefit of ELCs is that they
have no moving parts, are reliable and are virtually maintenance-free. The advent of
ELCs has allowed the introduction of simple and efficient multi-jet turbines for
micro-hydropower systems that are no longer burdened by expensive hydraulic
governors.
There are various types of ELCs in the market that can regulate systems from
as small as 1 kW to 100 kW. The choice of the controller depends on the type of
generator you have. ELCs are suitable for synchronous generators. If there is an
induction generator, it will need an induction generator controller (IGC). IGCs work
on a principle that is similar to that used by ELCs, but an IGC monitors the generated
voltage and diverts the surplus power to the ballast load.
72
5.7 LINE LOSSES
The line losses are due to the use of substandard cables and non-availability of
poles. Since the site is in mountainous territory, the cable is now and often passing
through large bulky trees. It is routine in raining that locals shut downs the plant since
the wooden pole or those wires which are passing through trees become short-
circuited. Poles with insulators for holding live wires are needed besides quality cable
for transmission
73
a. Cost plan-1
Penstock (Installed) 0
ELC 400000
Theoretical power output of the site is 21kw and installing 15KW T15 CFT, gives
5KW extra which was not harnessed previously. The efficiency of the plant could be
raised to its normal range which is 60-75%.
b. Plan-2:
In this plan, the aim is to minimize the overall expenditures as low as possible
in the optimum range of performance. The already installed old version of CFT could
be repaired. The nozzle at inlet to the turbine must be replaced because of excessive
leakage. The turbine blade angles must be checked and maintenance must be done to
smooth the periphery. The civil work is important and again a compromise is made on
ELC, since the price of ELC is very high in Pakistan. ELC could be installed in later
stage, if local manufacturers start producing ELC. It is of vital importance to
implement the recommended design of FBT and HRC, since both accounts for almost
50% power loss. The forecasted estimate is
74
Table 5.3 Cost estimate for Plan-2
The efficiency of the already installed CFT could be improved almost 15%.
75
References
Books
Fluid Mechanics, Hydraulics and Hydraulic Machines by Dr
K.R.ARORA
Manuals
How to Develop a small Hydro site by Layman
Micro-Hydro power: Reviewing an old concept by Butte, Montanna,
1979
A Guide to UK Mini Hydro Developments by British Hydro Power
Association
Micro hydro power systems, a buyer‟s Guide by Natural Resources
Canada
Research Papers
Best practices for sustainable development of Micro hydro power in
developing countries by Smail Khennas & Andrew Barnett
Understanding Micro hydro electric generation, Technical paper No 18
by weaver and Christopher s
Hydro power in the nineties (home power No 44) by Paul & Barbara
Small hydro power systems by NREL, U.S Department of Energy
Websites
www.microhydropower.net
www.minigrid.com
www.british-hydro.org
www.renewable-energy-sources.com
76
Abbreviations:
MHPP = micro hydro power plant
CFT = Cross flow turbine
HRC = Head Race Canal
FBT = Fore bay tank
AC = alternating current
cfm = cubic feet per minute
DC = direct current
e = efficiency
ELC = electronic load controller
ft. = foot; feet
gpm = gallons per minute
Hz = hertz
IGC = induction generator controller
kW = kilowatt
kWh = kilowatt hour
lps = litres per second
m = metre
P = power
Q = flow rate
rpm = revolutions per minute
V = voltage
W = watt
77
APPENDIX A
FBT Weir
78
Spill way CFT
79