Sie sind auf Seite 1von 8

Embedded generation

Voltage rise
the big issue when c nnecting
embedded generat on to long
11 kV overhead lines
There has recently been much interest in embedding small generators deep within
distribution systems. The steady-state voltage rise resultingfrom the connection of
these generators can be a major obstacle to their connection at the lower voltage
levels. This article summarises the results of some generic studies, explaining this
voltage rise issue and how it may be overcome.

by C. L. Masters

here has recently been much interest in should be maintained within +6% of the

T connecting small generators, between


200kW and lOMW, deep within distri-
bution systems. These networks are,
by tradition, passive networks. They were
designed to pass power from the national
nominal voltage. For systems above 50V and
below lOOOV, variations of between +lo%
and -6% of nominal voltage are permitted.
Prior to the 1994 amendments, variations of
+6% were permitted. This change was a result
grid system, down the voltage levels, to LV of proposals to harmonise the UK electricity
customers. They were generally not designed system with those in Europe.
for the connection of generators. There are The Electricity Supply Regulations are soon
many technical issues that must be considered to be replaced with the Electricity Safety,
when connecting a generating scheme to the Quality and Continuity Regulations.’ They
distribution system, such as: were due to come into force in October 2001,
but have been delayed due to the numerous
thermal rating of equipment comments made during the consultation
system fault levels process. The Electricity Safety, Quality and
stability Continuity Regulations do not propose to
reverse power flow capability of tap-changers make any immediate changes to the permitted
line-drop compensation voltage variations. However, it is proposed
steady-state voltage rise that, with effect from January 2003, the
losses permitted voltage variations for systems
power quality (such as flicker, harmonics) between 50V and lOOOV will change to +lo%.
protection. It is the Distribution Network Operator’s
(DNO’s) responsibility to ensure that its
This article concentrates on the steady-state systems are operated within the limits
voltage rise that occurs when connecting permitted by the Electricity Supply Regula-
small generators to l l k V networks and often tions. However, at the planning stage, the 1lkV
seriously impacts on the technical feasibility of system is often designed to maintain voltages
such schemes. within *3% of nominal, so that the voltage
variations seen by the LV connected customers
Allowable voltage variations remain within the permitted +lo% and -6%
The Electricity Supply Regulations’ stipulate limits.
that, unless otherwise agreed, the steady-state When a generator is to be connected to the
voltage of systems between lOOOV and 132kV distribution system, the DNO will consider

POWER ENGINEERING JOURNAL FEBRUARY 2002 5


Embedded generation

1 Voltage profile along


the heavily loaded 11kV
overhead line used in
the example

primary
substation

- nominal voltage at primary substation


- 103% of nominal voltage at primary substation
- 106% of nominal voltage at primary substation
IO8
106
r ___ +6% voltage limit

104

102

100

98

96

94

92 I I I I I
0 4 8 12 16 20
distance from the primary substation, km

the worst case operating scenarios and ensure line tends to be low, so neither of the terms RP
that their network and customers will not be or X Q can be neglected. This, coupled with the
adversely affected. Typically, these scenarios fact that the reactive power pushed down the
are: line is usually much lower in magnitude than
the power (assuming the customer imports
no generation and maximum system demand reactive power), leads to there being a voltage
maximum generation and maximum system drop along the line from the primary substation
demand to the point of connection of the customer.
maximum generation and minimum system To demonstrate this, consider the following
demand. example (Fig. 1): connected to a primary
substation is a 2Okm long, 1 l k V overhead line,
Some DNOs take into account the diversity of comprising 16mm2 copper conductors. Every
the local load and consider the system with the 4km along the line is a three-phase load of
minimum expected demand. Others do not, lOOkW and 20kvar. As the distance from the
and assume no load as the worst case scenario. primary substation increases the voltage falls.
With the primary substation at nominal voltage
Distribution systems with no embedded (IlkV), the far end of the line falls to 10.3kV
generation (6% below the nominal voltage). This is right
To transmit power from an l l k V primary on the permitted limit. If the line had been
substation to a typical LV connected customer longer or the load greater, the voltage would
some distance away will require the voltage have fallen even further.
at the primary substation to be higher than To maintain system voltages within permit-
the voltage at the point of connection ted limits, DNOs often maintain primary
of the customer to the 11 kV system. This is substations above nominal voltage using
explained using Panel 1. automatic voltage control (AVC), on-load
Generally the X/R ratio of an l l k V overhead tap-changers and line-drop compensation.

6 POWER ENGINEERING JOURNAL FEBRUARY 2002


Embedded generation

where

VPS is the primary substation voltage


VC is the voltage at the customer connection point
R, X are the resistance and reactance of the overhead line
P, Q are the power and reactive power transmitted from
the primary substation into the overhead line

Controlling the primary substation, in this able to absorb a significant amount of reactive
example, to 103%and 106%of nominal voltage power. This is explained using Panel 2.
(11.3 kV and 11.7 kV) maintains the end of the As the XIR ratio of the l l k V line is small,
l l k V line well within the permitted voltage neither RP nor X Q is negligible. The XQ term
limits. may be positive or negative, depending on
Although the Electricity Supply Regulations whether the generator is exporting or
allow voltage variations on the 11kV system of importing reactive power. However, as the
c6%, DNOs often impose limits of *3% at the magnitude of the reactive power will be small
planning stage. This is in order to maintain compared to that of the power (unless some
the LV connected customers within the form of compensation is used), the RP+XQ
permitted +lo% and -6% of nominal voltage. term will tend to be positive. Thus, the voltage
In this generic study the +3% planning limit is at the point of connection of the generator to
ignored. The l l k V system voltages are allowed the l l k V system will rise above that of the
to vary by +6% of nominal voltage, to more primary substation.
clearly demonstrate the effect of connecting a To demonstrate this, a 300kW generator
generator. (operating at unity power factor) is connected
l2km from the primary substation (controlled
Effect of connecting generation to at 103% of nominal voltage). The output of the
distribution systems generator is equal to the downstream demand,
Connecting a generator to the distribution so the direction of the power flow from the
system will affect the flow of power and the primary substation is not altered. The voltage
voltage profiles. To export its power, a genera- falls as the distance from the primary sub-
tor is likely to have to operate at a higher station increases, as before. But the magnitude
voltage than the primary substation, unless it is of the voltage drop is less profound (Fig. 2).
-- I_ ___ _I I-. -I I I ___

1
where
VPS is the primary substation voltage
VPS

I
tI
VGEN

I
VGEN IS the voltage at the generator connection point
R, X are the resistance and reactance of the overhead line
P, Q are the power and reactive power transmitted from
the generator into the overhead line
i
.
I .. .. " ....

POWER ENGINEERING JOURNAL FEBRUARY 2002 7


Embedded generation

the transformer's tap-changers are capable of


-no generation operating with a reverse power flow.
-300 kW generator
-1 MW generator /-- How can this voltage rise be counteracted?
g 109 If the connection of a generator to an 11 kV
<-
m
c
107 overhead line causes an excessive voltage
2
._ 105 rise, there are several techniques that can
E be employed to alleviate the situation, for
e
c
103
example:
8 101
reduce the primary substation voltage

97
99 0 1 4 8 12 16 20
full demand on the line
0 4 8 12 16 20
no demand on the line
allow the generator to import reactive power
(reducing the RP+XQ term)
install auto transformers, or voltage regu-
distance from the primary substation, km lators as they are often called, along the line
(resetting the voltage along the line)
increase the conductor size (reducing the
2 Effect of connecting a Increasing- the -
generation to 1MW reverses resistance)
generator On thevoltage the flow of power along the line, from the constrain the generator at times of low
profile along the 11kV
generator towards the primary substation. demand (reducing the transmitted power)
line used in the
The voltage at the generator rises above that a combination of the above.
elsewhere, thus allowing the power to be
exported in both directions. In this example, Reduce the primary substation voltage
the voltage in some parts of the system rises It is common practice for DNOs to maintain
above the permitted +6% voltage limit. l l k V primary substations above nominal
The voltage rise is more onerous when voltage to ensure that system voltages remain
there is no demand on the system, as all within the permitted -6% voltage limit. In the
the generation is exported back to the previous example, the voltage at the 1MW
primary substation. With 1MW of generation generator is 109% of nominal (under full-
connected, the voltage rises to 112% of load conditions). Lowering the voltage at the
nominal. This suggests that it is the voltage rise primary substation from 103% to 100% of
during periods of no/minimum demand that nominal reduces the voltage rise to just below
limits how much generation can be connected. the permitted +6%voltage limit (Fig. 4). It also
When connecting a generator to the distri- reduces the voltage during periods of no
bution system, a DNO must consider whether system demand to around 110% of nominal,
3 rural3311 1kV the power may be exported back through the which is not sufficient.
primary substation primary substation and must ensure that Before lowering the voltage at a primary
substation, a DNO must ensure that it will not
k adversely impact on any of its customers. If
there are other feeders connected to the
primary substation or teed off the l l k V line,
the voltage profile along these circuits may be
depressed. This may reduce the voltage of the
LV customers connected to these feeders below
the permitted -6% limit.
Also, if the generator is not exporting power,
the system voltages will be depressed. In this
example, the primary substation is maintained
at 103%of nominal to ensure that the voltage
2Okm away is satisfactory. If the primary
substation voltage is reduced to l l k V in order
to connect the generator, the voltage at the end
of the line will drop to 94% of nominal
whenever the generator is not exporting power.
The DNO must consider how it will correct this
voltage depression. One solution may involve

8 POWER ENGI NEERlN G JOURNAL FEBRUARY 2002


Embedded generation

4 Effect of using various

- example system methods to reduce the


voltage rise on the 11kV
- effect of reducing primary substation to nominal voltage line used in the example
effect of the generator operating at 0 9 power factor leading
- effect of installing an auto transformer, 8 km from the
I

primary substation
- effect of upgradingthe line with 70 mm* copper conductor
110 - effect of constraining the generator
... --- +6% volta

I I I I I I I I I I
0 4 8 12 16 20 0 4 8 12 16 20
full demand on the line no demand on the line

I distance from the primary substation, km

customer minutes lost while the off-circuit lowered sufficiently.


tap-changers are reset on the 11/0-415kV If a generator is to import significant levels
distribution transformers. However, this may of reactive power, it may be necessary to agree
not be practical if there are long lines or many a charging mechanism with a supplier to cover
distribution transformers involved. the costs involved with purchasing and
transporting these extra kvars. The DNO must
Import reactive power also consider the effect that this additional
DNOs may stipulate that generators operate at reactive power flow will have on system losses
leading, lagging or even unity power factor, and the loading on circuits. The effect of the
depending on the X/R ratio of the system, generator tripping must also be considered, as
voltage regulation, local load etc. Generators this will cause a transient voltage rise. It may
are typically operated at a power factor such take the transformer tap-changers at the
that if they trip, when at rated generation, the primary substation several seconds to respond
disturbance to the system is minimised. and restore the voltages. Under such circum-
The amount of reactive power that can stances a DNO may be able to use a switched 5 Typical rural1 l k v
be imported is generally governed by the 'capacitor bank or some other form of reactive overhead line
parameters of the generator. Typically a
synchronous generator can import reactive
power at a 0.95 power factor. Wind turbines,
with uncompensated induction generators, can
import reactive power at around a 0.9 power
factor.
In the initial example the 1MW generator
operates at unity power factor. The voltage
rises to almost 109% of nominal (under full
load conditions) and 113% of nominal (under
no load conditions). Allowing the generator to
operate at a leading power factor of 0.9 limits
the voltage rise to 104%and 108%of nominal,
respectively (Fig. 4). With maximum demand
on the system, this brings the voltages within
the permitted +6% voltage limit. During
periods of no system demand, the voltage is not

'
POWER ENGINEERING JOURNAL FEBRUARY 2002 9
Embedded generation

6 Some guidance as to
the level of generation
that can be accepted
onto an 11kV overhead
line
- 16 mm2 conductor, 11 kV at primary substation
- 16 mm2conductor, 11.3 kV at primary substation
- 16 mm2 conductor, 11.6 kV at primary substation
- - - 70 mm2 conductor, 11 kV at primary substation
- - - 70 mm* conductor, 11.3 kV at primary substation
--- 70 mm2 conductor, 11.6 kV at primary substation

0 2 4 6 8 IO 12 14 16 18 20 22 24 26 28 30
distance, km

power compensation to restore the system transformers, the voltages may be maintained
voltages. within limits.
Auto transformers have not traditionally
Install auto transformers along the line been used by DNOs in this manner because
Auto transformers (voltage regulators or there has been little generation connected to
voltage boosters) are simply transformers with the distribution system. However, as the levels
a voltage ratio of 1:l and on-load tap-changers of embedded generation are set to increase
for voltage regulation. Essentially, inserting an their use may become more common.
auto transformer into a long circuit splits it into When installing an auto transformer into the
two sections. The voltage along one section distribution system the DNO must consider its
will be regulated by the AVC, tap-changers effect' on the system voltages under all the
and line-drop compensation at the primary worst case operating scenarios to ensure that
substation. The auto transformer will regulate no customers will be adversely affected. The
the voltage along the other section. effect of the auto transformer on the line
Inserting an auto transformer 8km from the loading must also be taken into account, as it
primary substation, in the initial example, has may increase the flow of reactive power along
little effect on the voltage profile between itself the line. The DNO must also consider how the
and the primary substation. Under full and presence of the auto transformer will affect
no load conditions the primary of the auto system security, as it will introduce another
transformer rises to 106% and 109% of factor of unreliability into the system.
nominal voltage, respectively (Fig. 4). The on-
load tap-changer, in this example, is set to Upgrade the conductor
control the voltage at the secondary of the auto Small overhead line conductors have higher
transformer to nominal voltage (using a tap impedance than large conductors. A 70mm2
range of ~ 5 in % five steps). Under both full and copper conductor has approximately one-third
no load conditions it operates to reduce the of the resistance and 90% of the reactance of
voltage to 101% of nominal, thus maintaining a 16mm2conductor. Thus, upgrading the con-
the voltage rise along the remainder of the ductor on an l l k V overhead line will signifi-
l l k V line below the permitted +6% voltage cantly reduce its resistance and will smooth the
limit. In this example, the auto transformer voltage profile along the line.
does not prevent this limit being exceeded In the initial example, the voltage at the
when there is no demand. However, by careful 1MW generator was 109% of nominal (under
positioning of either one or two auto full load conditions) and 113% of nominal

10 POWER ENGINEERING JOURNAL FEBRUARY 2002


Embedded generation

(under no load conditions). The voltage profile operating regime of the generation.
along the line is improved by replacing the
16mm2conductor with 70mm2copper (Fig. 4). Fig. 6 gives some indication as to the amount
It reduces the voltage at the generator to of generation that can be connected to an 11kV
less than 105% of nominal (under full load overhead line. It is clear that, as the distance
conditions). With no demand on the line, it is from the primary substation increases, the
marginally above the permitted +6% voltage amount of generation that can be accepted
limit. reduces.
This suggests that upgrading the conductors
is a very effective method of counteracting the Case studies
voltage rise problem. However, replacing the Three brief case studies are presented here to
conductors can be expensive and may make a show how Innogy plc has approached this
scheme uneconomic. voltage rise issue when developing small
generating schemes.
Constrain the generation
The sophisticated control systems available ChiRex.CHP scheme
these days will allow a generator to control its The ChiRex combined heat and power (CHP)
output in line with the system voltage. Thus if scheme in Northumberland (Fig. 7) comprises
the voltage is approaching the permitted +6% a 4.5MW gas turbine. It has been operational
voltage limit, a generator can reduce its output since June 1994, providing electricity and
in order to maintain the voltage below the steam to the ChiRex pharmaceutical plant.
threshold. This will allow the generator to Both are normally connected to the l l k V
continue operating, rather than being con- primary substation by a single l l k V cable. a
strained off during periods of low system During some periods, such as Christmas, the
demand. Conversely, should the system voltage demand at the pharmaceutical plant falls
fall below nominal, a generator may be able to dramatically, and the CHP scheme exports the
respond by increasing its output. majority of its power into the distribution
The initial example suggests that the 1MW system. This causes the voltage to rise and the
generator cannot be accepted onto the llkV generator was once tripped off by the
line, even when it is fully loaded. Its output has overvoltage protection.
to be constrained to 750kW to maintain the This problem was overcome by altering the
system voltages within the permitted +6% limit operating procedure of the CHP scheme. The
(Fig. 4). It will have to be constrained further output and power factor of the generator are 7 ChiRexCHPscheme
as the system loading is reduced. Under no load
conditions the generator has to be constrained
to 300kW to maintain the voltages below the
permitted +6% threshold.
Constraining an embedded generator will
obviously affect the economic benefit of the
scheme. It is usually only-aviable option when
the constraints are expected to be infrequent
and where significant system reinforcement
costs are avoided.

How much generation can be connected to


an 11kV overhead line?
The level of generation that can be absorbed
onto the distribution system is determined by
many factors, such as:

voltage level
voltage at the primary substation
distance from the primary substation
size of conductor
demand on the system
other generation on the system

POWER ENGINEERING JOURNAL FEBRUARY 2002 11


Embedded generation

The cost and feasibility of two methods of


overcoming the voltage rise problem are
currently being considered-installing reactive
power compensation at the generator, or an
auto transformer part way along the 11kV line.

1OMW mines gas generating scheme


Cogen, an Innogy subsidiary, is currently
developing a lOMW generating scheme to burn
methane gas from a disused coal mine. The
scheme will comprise two 5MW plants (Fig. 9)
connected separately to two existing l l k V
cables that run along the edge of the proposed
site. Studies have shown that the generation
cannot be accepted onto the existing system
8 Typical small hydro now manually adjusted by the operators who due to the excessive voltage rise.
generating scheme monitor the local demand and the system The local DNO currently operates the
(Blantyre, Scotland)
voltage. primary substation at 11.6kV. Following tests
on the system, the DNO has agreed to reduce
500kW hydro-generating scheme the primary substation voltage to 11.3kV so the
Innogy Hydro is in the early stages of generation can be connected. However, should
developing a 500kW hydro-generating scheme the generating scheme be out of service, the
in the north of Scotland (Fig. 8). The generator system voltages will be depressed and the
is to be connected to an l l k V overhead voltage of a few customers will fall below the
line, comprising 16"' copper conductors, permitted limit. As the generating scheme is
approximately 15km from the primary expected to operate at base load, this scenario
substation. Also connected to this 1lkV line will not occur frequently. It has been agreed
are numerous domestic customers fed by that, when this does occur, the DNO will
individual 1U0.415 kV distribution trans- dispatch an engineer to manually alter the
formers with off-circuit tap-changers. distribution transformers' tap-changers and
The DNO has stipulated that the voltage 'the DNO will be compensated appropriately by
along this l l k V line must not exceed 11.13 kV Innogy.
(1.2% above nominal voltage) as this will raise
customers' voltages above 253\3 the +lo% Conclusions
tolerance specified in the Electricity Supply In conclusion, there are many factors that
Regulations. determine the level of generation that can be
Provisional studies have shown that the connected to the distribution system at 1lkV
existing l l k V system cannot accept 500kW Thus every scheme will face different technical
9 Jenbacher gas of generation. Reducing the voltage at the and commercial issues and must be studied on
engine, produced by primary substation is not feasible, as there are a site-by-site basis. One of the major technical
Clarke, for small other l l k V circuits connected to the primary difficulties is the voltage rise resulting from the
embedded generation substation. Upgrading the line with 70"' reversed power flow. There are methods of
schemes (photo:
copper conductors increases the amount of counteracting this voltage rise; however, a
courtesy of Clarke
Energy, www.clarke- generation that can be connected, but not developer must consider whether the addi-
energy.co.uk) sufficiently. tional costs are justified.
I I

References
1 The Electricity Supply Regulationsl988: Regulation
30, paragraph 2, amended in 1994
2 The Electricity Safety, Quality and Continuity
Regulations. 2001: Draft copy-available for con-
sultation purposes on the DTI wehsite

0 IEE: 2002
Dr C. L. Masters is a Power Systems Engineer in
Operations and Engineering, lnnogy plc. She is a
Member of the IEE.

12 POWER ENGINEERING JOURNAL FEBRUARY 2002

Das könnte Ihnen auch gefallen