Sie sind auf Seite 1von 11

Efficiency multipliers for

construction productivity:
A Comparative Evaluation

Antonios Panas John-Paris Pantouvakis


Centre for Construction Innovation, Centre for Construction Innovation,
Department of Construction Engineering Department of Construction Engineering
and Management, Faculty of Civil and Management, Faculty of Civil
Engineering, National Technical University Engineering, National Technical University
of Athens, Athens, Greece of Athens, Athens, Greece
cvapanas@mail.ntua.gr jpp@central.ntua.gr

DOI 10.5592/otmcj.2015.1.3 Efficiency multipliers for construction productivity are


Research paper often estimated on an ad-hoc basis, depending on the project
characteristics. The purpose of the study is to define a struc-
tured approach allowing the determination of the appropriate
empirical productivity relations and efficiency multipliers along
with their respective values. The proposed method breaks
down a given construction activity into distinct operational
scenarios which represent unique combinations of key produc-
tivity variables, thus providing a perspective on construction
productivity for both labor-intensive and equipment-inten-
sive operations. In addition, this is the first study to explicitly
describe the process and the theoretical prerequisites for the
statistically valid derivation and comparative evaluation of new
efficiency multipliers for a given construction activity. A case
study of heavy-duty concrete paving activities over an eight
month period is utilized as a testbed for the derivation of new
efficiency multipliers. An excavation scenario with the use of
published estimation formulae is also presented to demon-
Keywords strate the approach’s capability to corroborate the values of
Concrete pavements, known efficiency multipliers. The results indicate that the pro-
Estimation, Excavation, posed approach improves the accuracy of estimated multipliers
Multipliers, Productivity. stemming from past productivity studies and increases the esti-
mation precision for the derivation of new multipliers related to
future construction operations.

1186 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5


INTRODUCTION available (Jang et al., 2011; Moselhi and Background
Construction productivity is one of Khan, 2012) and, furthermore, may lead
the main drivers for completing proj- to unrealistically optimistic results Literature review
ects within time and cost limitations (Lambropoulos et al., 1996). Also, the In spite of the extensive research on
(Moselhi and Khan, 2010) and as such estimators cannot verify the accuracy construction productivity, there is no
its appropriate estimation is quite of the efficient multipliers selected for standard definition for its estimation
important for preparing construction the particular operations under study. (Moselhi and Khan, 2012). Therefore,
schedules and budgets (Song and The above shortcomings are this research defines construction pro-
AbouRizk, 2008). To determine con- addressed in this paper. More specifi- ductivity as the ratio of work-hours
struction productivity one needs to cally, the research objectives may now per output (e.g. wh/m3), which is often
estimate an average production rate be stated as follows: called the “unit rate” (Thomas and
(Kiziltas and Akinci, 2009; Song and (i) To define a structured approach Yiakoumis, 1987). The scope of the
AbouRizk 2008) and then adjust it to allowing the determination of the appro- analysis is set at the crew level, so as to
the specific operational conditions of priate empirical productivity relations examine factors that pose short-term
the job, such as temperature, overall and efficiency multipliers along with variations on productivity on a daily
site organization, crew skill, on the job their respective values. basis (Moselhi and Khan, 2010). A mea-
learning for repetitive work (Panas and (ii) To validate the above approach sure of productivity which has been
Pantouvakis, 2014) etc by multiplying on selected operations of a real-world long used in the estimating process
it by a set of “efficiency coefficients” large-scale infrastructure project for is the performance ratio (PR), whose
or “efficieny multipliers” (AbouRizk et both labor-intensive and equipment- mathematical expression is given as
al., 2001). intensive operations. follows (Thomas and Yiakoumis, 1987)
The average productivity is esti- The structure of the paper is as fol- (see Equation 1):
mated using published formulae pro- lows: The following section presents PR = Effective Productivity /
posed either by manufacturers such background information on construc- Theoretical Productivity (1)
as Caterpillar (Caterpillar, 2014) and tion productivity. Then we proceed with Usually, the effective or actual pro-
Komatsu (Komatsu, 2009) or by widely reviewing basic information on the ductivity is worse than the theoretical
acknowledged and accepted institu- concrete paving process, which will be estimate, so in most cases the PR is
tions such as the BML (1983). It should later used as a testbed for the approach lower than 1.00. In the estimating pro-
be noted that in some cases and for proposed herein, from a labor-intensive cess, the expected productivity rates
certain construction operations there operations perspective. In addition, the are generally tabulated as average
are no published formulae in the litera- productivity estimation formulae for values reflecting average conditions for
ture (Panas and Pantouvakis, 2010). In excavation operations with the use of a given project (AbouRizk et al., 2001).
these situations, one should determine hydraulic excavator is presented, as an Thus, single-value estimates of produc-
the procedural framework allowing the exemplar of equipment-intensive opera- tivity are typically used in preparing a
incorporation of an initially unknown tions. The research methodology is dis- bid. Therefore, if the PR is known in
but defined later, during the process, cussed in the subsequent section. The advance, then the estimation’s accu-
set of operational factors (Pantouvakis next section exemplifies the approach racy will increase. The performance
and Panas, 2013). for the estimation of new multipliers by ratio may be regarded as an efficiency
The average productivity is then mul- analyzing heavy-duty concrete pave- multiplier, since it is an aggregate
tiplied by appropriate “efficiency multi- ment construction operations. The measure that incorporates the effect
pliers” whose determination, however, analysis’ results stemming from field of several factors (AbouRizk et al., 2001;
is not trivial as the relationship between measurements are reported along with Thomas and Yiakoumis, 1987).
the affecting factors and productivity is the main factors and efficiency multipli- However, a review of pertinent
not well understood (O’Connor and Huh ers that affect the achieved productivity. research reveals some key limitations
2006). Different methods may suggest Then, the approach is implemented for in the estimation of the efficiency mul-
different sets of efficiency multipliers the corroboration of known efficiency tipliers. First, the number of factors
for the same operation each of which multipliers, by examining an excavation affecting productivity and the magni-
may take values from a specific range scenario. The main inferences emerg- tude of their impact within a project
of expected values. The selection of ing from the study are discussed and, varies (Hasan et al., 2013). Hence,
values suggested by manufacturers is finally, the conclusions and future direc- there is a difficulty in properly consid-
somewhat vague, as explicit guidelines tions for research are delineated. ering all factors that impact productiv-
for the selection of these values are not ity for a given activity (AbouRizk et al.,

a. panas, j-p. pantouvakis · efficiency multipliers for construction productivity: a comparative evaluation · pp 1186-1196 1187
2001). Therefore, the efficiency multi- weather) on productivity. Factors not performed by large cranes, will be exam-
pliers must be directly associated with affecting productivity assume a value ined herein (Figure 1). See Panas and
a specific productivity factor, so as to equal to 1.00. Similarly, if all factors Pantouvakis (2011) for further informa-
explicitly determine both the scope are considered equal to 1.00, then the tion on the construction process.
of the analysis, as well as the limita- theoretical and effective productivities
tions in generalizing the applicability coincide.
of the estimated outputs. Secondly, How do we determine the set of mul-
the use of an aggregate measure of PR tipliers required and their respective
quantifies the combined impact of all values in each case? Clearly, we need
considered factors on the production a methodology, which we will present
rate, but limits the ability to isolate the and discuss in some detail in section 3
impact of any single factor from others of this paper. We also need at least two
(O’Connor and Huh, 2006). construction operations to exemplify
Consequently, it would be useful the approach; one with a known and
for the PR to be further analyzed in its one with unknown average productiv- Figure 1. Layering of ready-mixed
constituent factors, in order to gain a ity formulae. We review briefly these concrete for the construction of heavy
more detailed insight on the drivers construction operations in the following duty surfaces.
that shape the effective productivity. paragraphs.
Thirdly, a proper projection of Common excavating operations
the condition that each factor will Selection of construction operations One of the most well-known construc-
assume when the job commences and The approach proposed in this study to tion operations is excavation using a
the extent of their impact on produc- estimate and compare the pi coefficients hydraulic excavator. For this operation,
tivity have still not been adequately for a given construction activity will be there are many published methods for
addressed in literature (AbouRizk et exemplified through the test application productivity estimation. Here we adopt
al., 2001). In that sense, the correct in two construction activities; a labour one of the most widely accepted by
determination of each factor’s state intensive one where the average pro- construction practitioners, namely
in a multi-factor productivity analysis ductivity formulae is not known and an the one defined in BML (1983). Based
is of major significance. equipment intensive one with a known on Panas and Pantouvakis (2010), we
In view of the aforementioned, it average productivity formulae. For the may calculate Qeff for this operation by
is clear that the PR is a dynamically former, we have selected the complex Equations 3a, b and c:
changing measure of productivity that concrete paving operation, whereas for Qeff = Qth × pswing × pdepth
depends on the type and size of the pro- the latter we have opted for the common (3a)
ductivity factors involved in the esti- excavation operation using a hydraulic pswing = 4×10-6 × sa2 – 0.0024 × sa
mating process. As such, in this paper excavator. + 1.1824
we suggest a modification to Equation (3b)
1 to provide for the multifaceted effect Concrete paving operations pdepth = 0.0043 × d2 – 0.0622 × d +
of the varying productivity factors as Concrete paving operations require the 1.0618
shown combination of both equipment- and (3c)
i n labor-intensive resources, with a par- where: d = excavation depth [m];
Equation 2 below. ticular focus on the latter. Published pswing/depth = the dedicated efficiency
(2)
productivity data are scarce and based multiplier representing the quantita-
where: Qeff/th = effective/theoreti- mainly on road construction. For the pur- tive impact of the swing angle and
cal productivity for a given activity; poses of this paper, we consider the excavation depth for the adjustment
PR = performance ratio; pi = efficiency concrete pavement construction pro- of theoretical to effective productivity;
multiplier corresponding to productiv- cess to encompass area marking and and sa = swing angle [˚].
ity factor i for the adjustment of theo- preparation, concrete pouring, concrete Equipped with the basic theoretical
retical to effective productivity; and f = layering, concrete finishing and joints background and a selection of appro-
number of productivity factors. cutting operation. More specifically, the priate construction operations, we can
In essence, as shown in Equation 2, layering of ready-mixed concrete for the now present the research methodology
PR decomposes into a set of multipli- construction of heavy-duty surfaces in and demonstrate its application on the
ers each of which represents the effect external areas, such as those required selected processes.
of a specific productivity factor (e.g. for the loading operations in harbours

1188 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5


Research methodology sub-tasks can be completed at a cer- The next step is the elicitation of work
The research methodology comprises tain theoretical productivity level. study data on a daily basis through
of three main phases; data elicitation, However, it is evident that each project the utilization of direct observation
productivity model generation and effi- is different and, thus, deviations from techniques, enhanced by the study
ciency multipliers determination, as theoretical values are expected, lead- of ancillary data, such as contractual
summarized in Figure 2 and presented ing to the actually effective productiv- documents, project reports, work-
in the following paragraphs. ity achieved on site. In that sense, the hours logs, interviews with key proj-
term “operational” denotes specific ect staff etc. One daily measurement
Data elicitation micro-level factors that can directly corresponds to one data point (DP) and
The first step of the data elicitation influence the effective productivity of the m elements or collected DP’s for a
process is the definition of the activity any construction operation. The fac- specific sub-task constitutes one data-
that is going to be studied. Flowcharts tors are conceptualised by measur- set (D) (see Equation 4):
are drawn, so as to decompose each ing specific physical parameters (i.e. (4)
activity in its “n” constituent sub-tasks excavation depth, concrete pouring
(si) and reveal the interactions between volume etc.) or by using a categorical
them. The scope of the experimen- variable, in case of qualitative fac- Regarding the sample size, as the
tal framework should be defined for tors (e.g. crew skill). Their influence is number of data points in each dataset
every sub-task, including contextual quantified by the use of the respective increases, the validity of the analysis
information, such as location of the productivity efficiency multipliers (pi), is potentially improved.
site, project characteristics, deployed whose mathematical formalisation is
resources etc. Following the definition provided by Equation 2. As such, the Productivity model generation
of the context within which the study study will be focused on scrutinising Productivity models can be generated
will be conducted, the operational fac- the impact of key factors to produc- by adopting data-oriented techniques
tors affecting productivity should be tivity by measuring parameters that (e.g. statistical regression, artificial
specified. As mentioned in the previ- are believed to shape the values of the neural networks), where the collected
ous section, each one of the identified productivity efficiency multipliers (pi). data are directly associated with each

1. Data elicitation
A
Define Register measured
Define scope of Specify datasets (D1) and
Define operational Elicit work
Start i=0 i=i+1 experimental respective data point
activity subtask (si) factors study data
framework (DP1...m)

NO
s1 s2 ... sn-1 sn i=n? A
YES
2. Productivity model generation

YES NO
Develop Statistical Productivity
Select model Build analytical models
productivity checks Model valid?
variables models checked by
models valid?
validation set YES
NO
3. Efficiency multipliers determination

Specify data Specify Baseline Determine Baseline


Select factors for Create dataset Reference Reference Metrics
clusters for each analysis allocation matrix
operational factor Conditions (BRC) (BRM)

Conduct Develop empirical Validation of


Estimate efficiency Estimate seperate comparative models for derived Finish
multipliers efficiency evaluation of productivity estimation estimation models
matrix multipliers results

Figure 2: Research methodology.

a. panas, j-p. pantouvakis · efficiency multipliers for construction productivity: a comparative evaluation · pp 1186-1196 1189
other, without considering the process Factor 1 Factor 2
behind this data. Irrespective of the Cluster 2.1 ... Cluster 2.r
selected technique, the model’s vari-
Cluster 1.1 D1,1 ⊆ Di ... D1,r ⊆ Di
ables should be determined in the fol-
... ... ... ...
lowing manner: productivity should
Cluster 1.v Dv,1 ⊆ Di ... Dv,r ⊆ Di
be regarded as the response variable,
whereas the individual productivity
Table 1: Dataset allocation table
factors (i.e. efficiency multipliers) are
the model’s independent variables.
Upon the performance of the required D1,D1U...UD1,rU... UDv,1U...UDv,r=Di, it will then represent the operational
statistical checks that ensure the ∀v, r∈N scenario most frequently met on site
model’s robustness, the validation The essence of the dataset allo- (see Equation 6).
process initiates. The validation pro- cation table is that it “divides” each Upon the establishment of the BRC,
cess is performed by comparing the productivity dataset in specific opera- the “Baseline Reference Metrics”
outputs of the developed models to tional scenarios, i.e. pairwise combi- (BRM) are defined, namely the pro-
the actual collected data. Hence, the nations of operational factors. Hence, ductivity values which correspond to
validation process includes the sub- each table cell represents a unique the baseline reference scenario. In the
stitution of validation data inputs to operational setting within the desig- absence of actual data, BRM can be
the designed models, so as to compare nated clusters, thus highlighting the extracted from estimation handbooks
predicted results of the productivity contextual meaning of each data point. or from a company’s historical record.
models to the collected data. The sta- There is no standard rule as to how When field measurement data is avail-
tistical regression approach is adopted many data points there should be in able, then the BRM is directly associ-
in this study and the reader is referred each cluster. It is evident, however, that ated with the dataset allocation table,
to Panas and Pantouvakis (2011) for as the sample size increases, the infer- since it is equal to the average of the
more details. ences derived from each cluster will be BRC cell’s values (see Equation 7).
more valid. For indicative reasons, the
Efficiency multipliers determination table presented before has two dimen- BRC =max{D1,1,…,D1,r,…,Dv,1,…,Dv,r}
This section serves the main objectives sions. However, the analysis could be (6)
of the study, in terms of the research easily extended to incorporate three or BRM =<max{D1,1,…,D1,r,…,Dv,1,…,Dv,r}>
contribution. The key issue is the estab- more parameters, where each cluster (7)
lishment of a valid experimental frame- would be illustrated in a tree-structure.
work which will consequently help The next step is the definition of For example, if it is assumed that in
the categorization and the in-depth the “Baseline Reference Conditions” Table 1 the majority of the data points
analysis of the data within the regres- (BRC), namely the operational condi- are found in w-th row and z-th column,
sion models. First, every operational tions under which every operational then the cell containing the Dw,z dataset
factor is divided in specific categories, coefficient can be neglected, as it is is considered as representing the base-
or clusters, whose range is decided by supposed that it does not affect pro- line reference conditions, as shown in
the analyst. The limits of all clusters are ductivity. On a theoretical basis, this Table 2, below.
denoted by the minimum and maximum means that when certain conditions are In this manner, the BRM is estimated
values or the ordinal values for every met, then pi= 1.00,∀i∈N (see Equation as the average value of all data points
quantitative (e.g. min and max value of 2), and, consequently, theoretical and contained in the D w,z dataset (see
working length) and qualitative factor effective productivity coincide (Panas Equation 8):
(e.g. fiber-reinforced or plain concrete) and Pantouvakis 2010). In essence, the BRM = <Dw,z> (8)
respectively. A sub-set of the measured baseline reference conditions repre- The analysis concludes with the cal-
factors is chosen in pairs for further sent a specific operational scenario, culation of the efficiency multipliers,
elaboration. A dataset allocation table or, if seen in relation to Table 1, the as dictated by Equation 2. The coeffi-
is created, including all datapoints of BRC are associated with a certain table cients are calculated for every cluster
a given sub-task’s dataset, as follows cell. The choice of the BRC scenario in a v-by-r matrix as shown below (see
(see Table 1). depends on the analyst’s preference. Equation 9):
For validity reasons, all subsets con- A practical rule though would be for
tained in each table cell should sum up the BRC scenario to be specified as the
to the initial dataset (see Equation 5): table cell with most data points, since (9)

1190 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5


Factor1 Factor 2

Cluster 2.1 ... Cluster 2.z ... Cluster 2.r

Cluster 1.1 D1,1 ⊆ Di ... D1,z⊆ Di ... D1,r ⊆ Di


... ... ... ... ... ...
Cluster 1.w Dw,1 ⊆ Di ... Dw,z⊆ Di ... Dw,r ⊆ Di
... ... ... ... ... ...
Cluster 1.v Dv,1 ⊆ Di ... Dv,z⊆ Di ... Dv,r ⊆ Di

Table 2: Baseline Reference Metrics (BRM) specification table

New multipliers estimation:


Case Study of concrete
pavement construction
D1,1 D1,z D1,r
p1,1 p1,z p1,r A practical implementation of the
BRM BRM BRM
developed concepts is presented in
P= =
= Dw,1 BRM Dw,r the following sections, so as to dem-
pw,1 pw,z pw,r
BRM BRM BRM onstrate the applicability of the analy-
sis methodology. Data were collected
pv,1 pv,z pv,r Dv,1 Dv,z Dv,r
through work studies of actual paving
BRM BRM BRM
operations for the construction of a
container terminal infrastructure over
eight months, taking place in two dif-
ferent periods (2011 and 2013). Direct
It is evident that the BRM efficiency thus giving a notion of the sample’s observation and video recording were
multipliers are always equal to 1.00. sensitivity to changes in the opera- used as primary data elicitation instru-
In addition, the efficiency multipliers tional setting. The variation of the theo- ments. Secondary data were gathered
of the BRM row (pw,1,…,pw,z,…pw,r) and retical BRM to the actual data is visu- by open interviews with senior project
column (p1,z,…,pw,z,…pv,z) vectors indi- alised by the creation of charts which management staff, construction man-
cate the variation in productivity under facilitate the comparative analysis of agers and site personnel, as well as
the separate influence of either factor 2 the studied operations and, ultimately, by studying project documentation
or factor 1 respectively. This is particu- enable the formulation of new estima- (drawings, quantity take-offs, progress
larly important for the establishment tion formulae (see Equation 10): payment orders, labour hours logs).
of a valid experimental framework, in Qeff =Qth xP (10) All data points have been grouped in
case the analysis should be conducted The aforementioned relations are not specific datasets, while the scope of
under the prism of a sole operational computationally complicated, but rather measurements for each variable is
factor. In other words, if the effect of simple and useful estimation tools, denoted by the minimum and maximum
operational factor 1 on productivity against which actual measurements can values described before. In total, 46
were to be examined independently be benchmarked. Finally, after having data points have been collected rep-
of the influence of any other opera- ensured that the produced estimation resenting on-site workday measure-
tional factor, then the analyst should models are validated statistically and ments of concrete paving productiv-
conduct field measurements for differ- in practice, they can be directly applied ity, expressed in work-hours per cubic
ent clusters of factor 1, provided that in the estimation process. It should be meter of placed concrete (wh/m3).
the values of factor 2 would be strictly highlighted though that the implemen-
confined within cluster 2.z. The rest of tation of the calculated efficiency mul- Phase 1: Activity definition and data
the matrix elements indicate the varia- tipliers should not be extended beyond elicitation
tion in productivity under the combined the scope of the experimental framework Although measurements have been
effect of both factors. as defined in the beginning. collected for all subtasks of the con-
When all pi coefficients have been crete pavement process (see Concrete
estimated, comparative analyses can paving operations), the analysis will
be conducted to evaluate the intra-row be focused on the concrete layering
or intra-column variation of the BRM, subtask (n=1), for brevity reasons. The

a. panas, j-p. pantouvakis · efficiency multipliers for construction productivity: a comparative evaluation · pp 1186-1196 1191
productivity factors which were initially step is the multiple regression model has been based on a limited number of
screened as candidate operational generation, with working width and collected datapoints. However, its face
factors were the working width and length being the predictor variables validity has been successfully tested
length, the concrete layer thickness, and layering productivity considered in a real construction setting and it is
the concrete type (fiber-reinforced or as the response variable. The provision currently extended with the inclusion
plain) and the gang size. Based on the of the source data is omitted due to of more data, in order to increase its
visualization of the pairwise correla- space limitation, however the results predictability and stability. Besides,
tions between these response vari- of the model fitting process showed the model’s main purpose is to serve
ables through a scatterplot matrix that the model has an R-square value as an instrument to exemplify the appli-
and the implementation of the back- 0.68432, which represents the coef- cability of the proposed methodology.
ward stepwise selection technique, it ficient of multiple determination that
was decided that the concrete paving measures the proportional reduction Phase 3: Estimation and comparative
operations should be better examined of total variation in producitivity using evaluation of efficiency multipliers
by taking into account the following working width and length as indepen-
operational factors: working width dent variables. In other words, it rep- Specification of aggregate
and length. It is evident that each one resents the total variability in produc- efficiency multipliers for all involved
of the aforementioned factors holds a tivity explained by working width and operational factors
certain set of attributes. The working length. R-squares values of >0.60 imply After the validation of the developed
width (w) holds a minimum value of that the data correlation is positive and model, the “efficiency multipliers
4m which represents the min working strong and, thus, acceptable (Kutner determination” phase initiates as
range of the laser screed and maximum et al., 2005). The analysis of variance depicted in Figure 1. The two basic
of 33m. The working length (l) ranges yielded an observed significance prob- operational factors are working width
between 15m-210m and represents the ability (Prob>F) of <0.0001 for width and and length and their data clusters are
lane length that is worked by a crew on length, which is significant at the 0.05 specified in such a way, so that the all
a given workday. On the basis of the level. The Prob>|t| metric is <0.0001 for data points within a single dataset are
operational factors described before, the working width and length, as well distributed accordingly. The dataset
the collected data will be divided as for the intercept, which means that allocation table is formed as follows
according to their attributes in specific b1 ≠ 0, b2 ≠ 0 and b0 ≠ 0 at 99% con- (see Table 3).
clusters, so as to enable their compu- fidence respectively. Ultimately, the Following the empirical rule expressed
tational processing, as will be shown following productivity model is used by Equation 6, the BRC scenario is rep-
in the next sections. (see Equation 11): resented by the D3,1 cell. In this case, the
Qeff = 0.4900881 – 0.007678 × [Width] BRC scenario is defined as the one cor-
Phase 2: Productivity model – 0.001332 × [Length], [wh/m3] responding to a working width of 21m-
generation 35m and working length of 0m-50m.
This section presents the results of Figure 3 illustrates the plotted Consequently, the BRM for concrete
the analysis for the productivity model regression model as a function of work- layering is established as the average
generation process, through the imple- ing length, for different width values, productivity value of the data points
mentation of the statistical regression whereas the respective validation chart contained in that cell, thus yielding
technique. The working width and is depicted in Figure 4. The mean abso- BRM = 0.22wh/m3. The matrix for the
length are the explanatory variables, lute percentage error is 10.98%, which calculation of the pi coefficients and the
whereas productivity is the dependent shows that the model values fit actual subsequent estimation of the effective
variable. The first step would be the productivity data adequately. productivity values is formulated as fol-
scanning of the data for outlying values It should be noted that, in prin- lows (see Equations 12 and 13):
and their examination to see if they are ciple, the determination of a quan- Since two operational factors are
valid observations. An outlier analysis titative relationship for estimating taken into account, then productivity
was conducted by the use of three sta- construction productivity with suffi- can be examined either under the com-
tistical metrics (Mahalanobis distance, cient statistical confidence requires bined influence of the working width
jackknife distances, T2 statistic) and the inclusion of a large database of and length, which is represented by
five data points were excluded from field measurements (AbouRizk et al., the aggregate efficiency multipliers of
the model. After the outliers’ identifi- 2001; Thomas and Yiakoumis, 1987). the matrix in Equation 12, or separately
cation and since all data lie within the As such, the developed model is at a for each factor. For the latter case, the
designated margins of Table 1, the next preliminary stage, since its derivation isolated effect of the working width

1192 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5


2.06 1.39 0.39
P= 1.49 1.26 1.07 (12)

= 1.00 0.88 0.74

2.06 1.39 0.39 0.45 0.31 0.20


Qeff = Qeff x P = 0.22 x P = 0.22 x 1.49 1.26 1.07 = 0.33 0.28 0.24 (13)

1.00 0.88 0.74 0.22 0.19 0.16

4.3.2. Specification of seperate efficiency multipliers for


specific operational factors

0,5

Width=4m Width=8m

0,4
Width=16m Width=24m
Productivity (wh/m3)

0,3

0,2

0,1

20 40 60 80 100 120 140 160 180 200

Lenght (m)
Figure 3: Concrete layering
productivity estimation chart.
0,4

0,3
Productivity (wh/m3)

0,2

Productivity (estimated)
0,1
Productivity (actual)

0
0 1 2 3 4 5 6 7 8 9 10 11 12 13

Figure 4. Concrete layering productivity validation chart.

a. panas, j-p. pantouvakis · efficiency multipliers for construction productivity: a comparative evaluation · pp 1186-1196 1193
Width [m] Length [m]

0-50 51-100 101-215

0-10 16, 32 1, 15 3, 8, 9, 10, 11, 12, 13

11-20 20, 21, 23, 24, 25, 29, 30, 35 4, 7, 14, 34, 37, 42, 46 19

21-5 22, 26, 27, 28, 31, 33, 38, 39, 40, 41, 43, 45 36 18

Table 3: Baseline Reference Metrics (BRM) specification table

on productivity is expressed by all pi (Qeff = 0.22×1.00=0.22wh/m3), to 51m- directly, if the aggregate efficiency mul-
coefficients in the first column of the 100m (Qeff = 0.22×0.88=0.19wh/m3) tiplier was used for width values within
matrix, whereas, in a similar fash- and ultimately to 101m-215m (Qeff = 0.22 0m-10m and length values within 51m-
ion, the effect of the working length × 0.74 = 0.16wh/m3), as shown by the 100m (see Equation 12):
is denoted by the equivalent values last row of the respective productivity Qeff = Q th × p1,2 =0.22 × 1.39 =
of the third row of the matrix. Let us estimation matrix (see Equation 13). 0.31wh/m3. If adequate data is avail-
assume that the objective is the study In the same fashion, the equivalent able, then the effect of plength and pwidth
of the impact that each factor (i.e. width efficiency multiplier for width (pwidth) can be generalised and aid estimators
and length) has on productivity. Then, would be estimated for a working in adjusting their estimates under dif-
Equation 2 would be modified into length less than 50m, so that Qeff = ferent operational scenarios. It should
Equation 14 as follows: Qth × 1.00 × pwidth = Qth × pwidth. In that be noted, though, that the computed
Qeff = Qth × plength × pwidth (14) sense, it is found that productivity efficiency multipliers have been
where: plength/width = the dedicated is decreased by ~50.00% for a work- derived from a rather small sample.
efficiency multiplier representing the ing width in the region of 11m-20m It is logical, that as more data points
quantitative impact of the working (Qeff = 0.22×1.49=0.33wh/m3) and, are being added to the sample, the
length and width for the adjustment subsequently, further diminishes by predictive capability of the efficiency
of theoretical to effective productivity. 36.36% for widths lower than 10m multipliers is going to be improved.
In other words, plength illustrates (Qeff = 0.22×2.06=0.45wh/m3). However, the validity of the estima-
productivity’s sensitivity solely to the In any other case, the comparative tion process per se is independent of
available length under no other influ- evaluation of the efficiency multipliers the sample size and should only abide
ence of any other operational factor. demands for their gradual variation to with the statistical inferences of the
Since the aggregate multiplier of be explicitly taken into account, since experimental framework, as described
Equation 12 for width values within the the analysis is shifting away from the in the research methodology.
21m-35m range and respective length BRC state into other cells, which denote
values within the 0m-50m range is different operational scenarios. Thus, if Known multipliers
1.00, this means that plength × pwidth = the length is supposed to be within 51m- corroboration: The case of the
1.00× 1.00 = 1.00. As such, both factors 100m, then the effective productivity is hydraulic excavator
are assumed at a baseline reference first adjusted by the efficiency multi- In view of the analysis presented in the
condition for that particular opera- plier plength, in order to shift from the previous section, it would be useful to
tional scenario. The statistically valid BRC state to the 51m-100m category: examine how known efficiency esti-
examination of the length’s effect on Qeff = Qth ×plength=0.22×0.88=0.19wh/ mators can be corroborated within a
productivity would require pwidth to be m3. The estimation of effective produc- specific operational setting. Equation
held constantly equal to 1.00, so that tivity values within that length range 3 as defined by BML (1983) for the esti-
Qeff = Qth × plength × 1.00 = Qth × plength. requires the calculation of the partial mation of the hourly productivity of
This means that plength should be exam- width multipliers as follows: For a width the hydraulic excavator will be used
ined along the third row of the multipli- ranging from 11m-20m, pwidth = 1.26 / in this section. More specifically, let
ers matrix (see Equation 12). Hence, for 0.88 = 1.43 and, hence, Qeff = Qth × plength us assume that the method statement
a constant working width in the region × pwidth = 0.22×0.88×1.43=0.28wh/ for an excavation operation dictates
of 21m-35m, the effective productivity m3. Finally, for widths lower than that the hydraulic excavator should
will incrementally improve by approx. 10m, pwidth = 1.39 / 0.88 = 1.58, so Qeff operate at a swing angle of 45˚ and
13.64% and 15.79% respectively, as the = 0.22×0.88×1.58=0.31wh/m3. Note, at the depth of 5m. First, the baseline
working length increases from 0m-50m that the last result could be reached reference conditions are represented

1194 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5


by a swing angle of 90˚ (pswing = 1.00) of strict procedures in handling the of the selected factors’ impact on
and an excavation depth of 1.00m involved efficiency multipliers, in productivity. The applied approach
(pdepth = 1.00). In that view, the actual order for the analysis to yield valid can be easily extended to include
on-site measurement of the pswing and comparable results. The study more than two factors, depending on
efficiency multiplier should be con- might be criticized for its limited the estimator’s judgment. Secondly,
ducted for excavation depths in the data sample, since, indicatively, the this is the first study to evaluate the
area of 1.00m, whereas the respective efficiency multiplier in the second effect of the contextual framework
determination of the pdepth efficiency row and third column of the matrix on a productivity sensitivity analysis
multiplier should stem from measure- in Equation 12 has been derived against a specific factor. The term
ments at swing angles equal to 90˚. from a single data point, which is, “contextual framework” denotes
Hence, taking into account the exact obviously, not representative of the the state assumed by the rest of the
operating conditions, the sensitivity activity under study. Consequently, productivity factors not included in
analysis for the variation of the pswing for the cells that contain little data, the sensitivity analysis. Therefore,
cannot be undertaken at the baseline two possible remedial actions would it is evident that it would not suffice
reference conditions. In that case, first be either to merge clusters, so as to to vary a specific productivity fac-
the pdepth is estimated as pdepth = 0.0043 end up with more data points in all tor’s values and estimate its effect on
× 52 – 0.0622 × 5 + 1.0618 = 0.86 and, cells, or use the validated regression productivity, if the estimator has no
subsequently, productivity variation is model in order to “generate” data knowledge or control over the vary-
examined according to the mathemati- points within the selected clusters. ing state of the other productivity
cal formula Qeff = Qth × pswing × 0.86, for factors. It must be ensured that all
different values of pswing. In a similar 2. Estimation of new efficiency multi- other parameters are at a “base-
fashion, the examination of the sensi- pliers: The analytical determination line reference” state, so as for their
tivity for the pdepth multiplier demands of the efficiency multipliers enables impact to be neglected. This means
the estimation of the pswing for 45˚ as the dynamic parameterization of that pi would be equal to 1.00 for all
pswing = 4×10-6 × 45 2 – 0.0024 × 45 + the estimation process, since the productivity factors, except the one
1.1824 = 1.08. Then, the productivity analysis can be easily shifted from currently investigated. In any other
estimation formula is Qeff = Qth × pdepth the “baseline reference scenario” to case, the shift from the “baseline
× 1.08, for different values of pdepth. In any other operational settings. Thus, reference” state to other opera-
that sense, the values provided in the the change in the working conditions tional scenarios must be carefully
estimation handbooks can be critically is explicitly quantified from a pro- conducted, as was shown by the case
evaluated and their applicability can ductivity standpoint, because each study results.
be examined according to their ability efficiency multiplier is directly asso- An additional point is that the pro-
to reflect the actual on-site conditions. ciated with a specific operational posed framework may be implemented
factor: in our case, these were the for both labor- and equipment-inten-
Discussion working width and length for con- sive operations, as long as produc-
This section presents the main infer- crete layering in paving operations tivity estimation can be formalized
ences emerging from the study. and the swing angle and digging mathematically in an explicit, quan-
This study research contribution is depth for the excavation operations. tifiable way. The qualitative examina-
assessed along three pillars: On any case, it must be highlighted tion of productivity influencing factors
that the derived empirical models requires a different methodological
1. Methodological framework: The should be constrained to their fac- approach, which, however, falls out
study has demonstrated that the tors and respective attributes, as of the scope of this study.
establishment of a structured defined in the dataset allocation
approach for assessing construction table (e.g. see Table 3 for concrete Conclusions
productivity may be translated into layering operations) and not be gen- This study presented an investigation
specific and practical steps that pro- eralised beyond that scope. into the estimation and comparative
vide full control over the estimating evaluation of new efficiency multipli-
process. In addition, the importance 3. Comparative evaluation of efficiency ers and the corroboration of known
of the contextual framework has multipliers: The research contribu- efficiency multipliers for a given con-
been highlighted, since the exami- tion stemming from the performance struction activity. The research did not
nation of different operational sce- ratio (PR) decomposition was two- pursue the development of just another
narios suggests the implementation fold: first, it enabled the isolation productivity model. The main research

a. panas, j-p. pantouvakis · efficiency multipliers for construction productivity: a comparative evaluation · pp 1186-1196 1195
contribution is the development of a Engineering and Management, Vol. 132, No.
structured estimation approach, whose References 4, pp. 408-415.
functional characteristics allow the AbouRizk, S., Knowles, P. and Hermann, U. R. Panas, A. and Pantouvakis, J.P. (2010),
quantitative assessment of the impact (2001). “Estimating labor production rates for “Comparative analysis of operational
that dynamically changing operational industrial construction activities”, Journal of coefficients’ impact on excavation

factors have on construction productiv- Construction Engineering and Management, operations”, Engineering Construction and

ity. In addition, this research adds to Vol. 127, No. 6, pp. 502-511. Architectural Management, Vol. 17, No. 5, pp.
461-475.
the existing body of knowledge since it BML (1983), Handbuch BML: Daten für die
(i) formulates the computational frame- Berechnung von Baumaschinen-Leistungen, Panas, A. and Pantouvakis, J.P. (2011), “Multi-

work that allows the specification of Zeittechnik Verlag , Neu-Isenburg. attribute regression analysis for concrete
pavement productivity estimation”,
statistically valid aggregate efficiency Caterpillar (2014), Caterpillar Performance
Organization, Technology and Management
multipliers that quantify the perfor- Handbook, 44th edition, Caterpillar Inc.,
in Construction: An International Journal, Vol.
mance ratio (PR) impact on productivity Illinois, USA.
3, No. 2, pp. 289-295.
and (ii) implements the concept of the Hasan, S., Bouferguene, A., Al-Hussein, M.,
Panas, A. and Pantouvakis, J.P. (2014),
“baseline reference conditions”, so as Gillis, P. and Telyas, A. (2013), “Productivity
“Simulation-Based and Statistical Analysis
to estimate separate efficiency multi- and CO2 emission analysis for tower crane
of the Learning Effect in Floating Caisson
utilization on high-rise building projects”,
pliers for each involved factor. The case
Construction Operations”, Journal of
Automation in Construction, Vol. 31, pp.
study results indicate that productivity Construction Engineering and Management,
255-264.
is affected more by width rather than Vol. 140, No. 1, 04013033.
Jang, H., Kim, K., Kim, J. and Kim, J. (2011),
length variations. In addition, a larger Pantouvakis, J.P. and Panas, A. (2013),
“Labour productivity model for reinforced
working area increases productivity for “Computer simulation and analysis
concrete construction projects”, Construction
a given working width or length. It is framework for floating caisson construction
Innovation, Vol. 11, No. 1, pp. 92-113.
believed that the proposed approach operations”, Automation in Construction,
Kiziltas, S. and Akinci, B. (2009), “Contextual
supports estimators in corroborating Vol. 36, pp. 196-207.
information requirements of cost estimators
or improving the results of past pro- Song, L. and AbouRizk, S.M. (2008), “Measuring
from past construction projects”, Journal of
ductivity studies and efficiency mul- and modeling labor productivity using
Construction Engineering and Management,
tipliers derived from historical data. Vol. 135, No. 9, pp. 841-852.
historical data.” Journal of Construction
Future research is suggested towards Engineering and Management, Vol. 134, No.
Komatsu (2009), Specifications and Application
the investigation of other activities, 10, pp. 786-794.
Handbook, 30th edition, Komatsu, Japan.
in order to further validate the pro- Thomas, H.R. and Yiakoumis, I. (1987), “Factor
Kutner, M.H., Nachtsheim, C.J., Neter, J. and Li,
posed approach, as well as automate model of construction productivity.”
W. (2005), Applied linear statistical models,
the proposed methodological frame- Journal of Construction Engineering and
Mc-Graw Hill, New York.
work, through the development of a Management, Vol. 113, No. 4, pp. 623-639.
Lambropoulos, S., Manolopoulos, N. and
computer-based estimation tool.
Pantouvakis, J.P. (1996), “SEMANTIC: Smart
EarthMoving ANalaysis and estimation
of Cost”, Construction Management and
Economics, Vol. 14, No. 2, pp. 79–92.

Moselhi, O. and Khan, Z. (2010), “Analysis of


labour productivity of formwork operations
in building construction”, Construction
Innovation, Vol. 10, No. 3, pp. 286-303.

Moselhi, O. and Khan, Z. (2012), “Significance


ranking of parameters impacting
construction labour productivity”,
Construction Innovation, Vol. 12, No. 3, pp.
272-296.

O’Connor, J.T. and Huh, Y. (2006), “Crew


production rates for contract time
estimation: Beam erection, deck, and rail of
highway bridges”, Journal of Construction

1196 o rganization, tech no logy a n d ma n agem e nt in construc ti on · a n i nte rn ati on a l j ou rn a l · 7(1 )2 01 5

Das könnte Ihnen auch gefallen