EXPERIMENT NAME: Mixing of Concrete

INSTRUMENT NAME: Concrete Mixer

Stock Entry Page No.: Equipment Price:

POUR THE INGREDIENTS (CEMENT & FINE AGGREGATE)


OF CONCRETE TO MIXER

SWITCH ON THE MIXER

POUR COARSE AGGREGATE TO MIXER

ADD WATER TO MIX AS PER W/C RATIO


PROVIDED

SWITCH OFF THE MIXER AFTER 10


MINUTES OF MIXING TIME

TAKE THE CONCRETE OUT AND CLEAN


THE MIXER

Do’s and Don’ts


1. Don’t put hands inside machine during operation.
2. Don’t touch the switch with wet hands.
3. Make sure that the machine is cleaned after the use.
EXPERIMENT NAME: To determine workability by compaction factor
INSTRUMENT NAME : Compaction Factor Apparatus
Stock Entry Page No.: Equipment Price:

Close the door of all hopper

Pour the concrete in hopper A

Open the door of hopper A and


allow concrete to fall in hopper B

Open the door of hopper B and


allow the concrete to fall in cylinder
(C)

Weight the concrete in cylinder (C)

Clean the apparatus

Do’s and Don’ts

1. Keep the hoppers and cylinders cleaned and oiled.

2. Make sure that the machine is cleaned after the use.


EXPERIMENT NAME: To determine workability by Flow test.

INSTRUMENT NAME : Flow table Apparatus

Stock Entry Page No.: Equipment Price:

Place the slump cone on the table

Pour the concrete (added with


superplasticizers) into the slump
cone and lift the cone.

Allow the concrete to flow on the


table

Measure the diameter of the flow


of concrete in all direction.

Remove the concrete and clean the


apparatus

Do’s and Don’ts

1. Mix the concrete containing superplasticizers using gloves.

2. Make sure that the machine is cleaned after the use.


EXPERIMENT NAME : To determine workability by slump test

EQUIPMENT NAME : Slump Cone Apparatus

Stock Entry Page No.: Equipment Price:

Attach the slump cone to the base


plate and tighten it.

Pour the concrete in slump cone in


three layers while tamping

Remove the excess concrete from


the top surface using trimmer

Lift up the slump cone and allow


concrete to subsidize

Measure the subsidence

Clean the apparatus

Do’s and Don’ts

1. Keep the slump cone oiled before pouring the concrete.

2 Make sure that the machine is cleaned after the use.


EXPERIMENT NAME : To determine the fineness modulus

INSTRUMENT NAME : Sieve set

Stock Entry Page No.: Equipment Price:

Arrange the sieves in order

Put the material in top sieve.

Shake the sieve for 5 min. In mechanical sieve shaker

Take the weight of material in each sieve.

Clean the all sieve

Do’s and Don’ts

1. Arrange the sieve in correct order.

2. Make sure that the machine is cleaned after the use.


EXPERIMENT NAME : Sieve Analysis

INSTRUMENT NAME : Sieve Shaker


Stock Entry Page No.: Equipment Price:

Place the sieve on sieve shaker and


bolt it.

Set the timer as for 5 min. and than


start the machine

Switch off the machine and remove


the sieve

Clean the apparatus

Do’s and Don’ts

1. Don’t touch the switch with wet hands.

2. Don’ t touch the siever in working condition.

3. Place the sieve in correct order on siever machine.

4. Make sure that the machine is cleaned after the use