ID Task Task Name Duration Start

5 Nov '17 12 Nov '17 19 Nov '17 26 Nov '17 3 Dec '17 10 Dec '17 17 Dec '17 24 Dec '17
Mode T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 S2995 SUN Lucban-Poblacion RELOC (42MD) 87 days Fri 10 11 17

2 PO/NTP Issued 1 day Fri 10 11 17


3 IWO/ACP Request 13 days Mon 13 11 17
4 Site Survey/TSSR/CD/DDD preparation 3 days Fri 1 12 17
5 TSSR/CD/DDD Submission and Approval 8 days Wed 6 12 17

6 SCAF/BOQ Submission and Approval 7 days Sat 16 12 17

7 Permitting: Pre-Con 22 days Fri 1 12 17


8 Tower Parts (Supply, Fab, PDI and Shipment) 29 days Sun 24 12 17

9 SKOM/Mobilization 2 days Fri 5 01 18


10 Manual Hauling of FDN Materials/Tower Parts 17 days Tue 9 01 18

11 Foundation Works 17 days Tue 9 01 18


12 Tower Delivery and Installation incl accessories 18 days Thu 1 02 18

13 RFI 1 day Mon 26 02 18


14 Completion Including Demobilization 5 days Tue 27 02 18
15 Permitting Post-con 10 days Tue 27 02 18
16 6243 Highlands-Midlands (36MD) 87 days Fri 10 11 17
17 PO/NTP Issued 1 day Fri 10 11 17
18 IWO/ACP Request 13 days Mon 13 11 17
19 Site Survey/TSSR/CD/DDD preparation 3 days Fri 1 12 17
20 TSSR/CD/DDD Submission and Approval 8 days Wed 6 12 17
21 SCAF/BOQ Submission and Approval 7 days Sat 16 12 17
22 Permitting: Pre-Con 22 days Fri 1 12 17
23 Tower Parts (Supply, Fab, PDI and Shipment) 29 days Sun 24 12 17

24 SKOM/Mobilization 2 days Fri 5 01 18


25 Manual Hauling of FDN Materials/Tower Parts 17 days Tue 9 01 18

26 Foundation Works 17 days Tue 9 01 18


27 Tower Delivery and Installation incl accessories 18 days Thu 1 02 18

28 RFI 1 day Mon 26 02 18


29 Completion Including Demobilization 5 days Tue 27 02 18
30 Permitting Post-con 10 days Tue 27 02 18
31 661 Highlands-Pinecrest Village (36MD) 87 days Fri 10 11 17
32 PO/NTP Issued 1 day Fri 10 11 17
33 IWO/ACP Request 13 days Mon 13 11 17

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017
ID Task Task Name Duration Start
5 Nov '17 12 Nov '17 19 Nov '17 26 Nov '17 3 Dec '17 10 Dec '17 17 Dec '17 24 Dec '17
Mode T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
34 Site Survey/TSSR/CD/DDD preparation 3 days Fri 1 12 17
35 TSSR/CD/DDD Submission and Approval 8 days Wed 6 12 17
36 SCAF/BOQ Submission and Approval 7 days Sat 16 12 17
37 Permitting: Pre-Con 22 days Fri 1 12 17
38 Tower Parts (Supply, Fab, PDI and Shipment) 29 days Sun 24 12 17

39 SKOM/Mobilization 2 days Fri 5 01 18


40 Manual Hauling of FDN Materials/Tower Parts 17 days Tue 9 01 18

41 Foundation Works 17 days Tue 9 01 18


42 Tower Delivery and Installation incl accessories 18 days Thu 1 02 18

43 RFI 1 day Mon 26 02 18


44 Completion Including Demobilization 5 days Tue 27 02 18
45 Permitting Post-con 10 days Tue 27 02 18
46 G9060 SUN BCDA (36MD) 87 days Fri 10 11 17
47 PO/NTP Issued 1 day Fri 10 11 17
48 IWO/ACP Request 13 days Mon 13 11 17
49 Site Survey/TSSR/CD/DDD preparation 3 days Fri 1 12 17
50 TSSR/CD/DDD Submission and Approval 8 days Wed 6 12 17
51 SCAF/BOQ Submission and Approval 7 days Sat 16 12 17
52 Permitting: Pre-Con 22 days Fri 1 12 17
53 Tower Parts (Supply, Fab, PDI and Shipment) 29 days Sun 24 12 17

54 SKOM/Mobilization 2 days Fri 5 01 18


55 Manual Hauling of FDN Materials/Tower Parts 17 days Tue 9 01 18

56 Foundation Works 17 days Tue 9 01 18


57 Tower Delivery and Installation incl accessories 18 days Thu 1 02 18

58 RFI 1 day Mon 26 02 18


59 Completion Including Demobilization 5 days Tue 27 02 18
60 Permitting Post-con 10 days Tue 27 02 18
61 S06 Lemery TP (6M RD) 87 days Fri 10 11 17
62 PO/NTP Issued 1 day Fri 10 11 17
63 IWO/ACP Request 13 days Mon 13 11 17
64 Site Survey/TSSR/CD/DDD preparation 3 days Fri 1 12 17
65 TSSR/CD/DDD Submission and Approval 8 days Wed 6 12 17
66 SCAF/BOQ Submission and Approval 7 days Sat 16 12 17
67 Permitting: Pre-Con 22 days Fri 1 12 17
68 Tower Parts (Supply, Fab, PDI and Shipment) 29 days Sun 24 12 17

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017
ID Task Task Name Duration Start
5 Nov '17 12 Nov '17 19 Nov '17 26 Nov '17 3 Dec '17 10 Dec '17 17 Dec '17 24 Dec '17
Mode T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
69 SKOM/Mobilization 2 days Fri 5 01 18
70 Manual Hauling of FDN Materials/Tower Parts 17 days Tue 9 01 18

71 Foundation Works 17 days Tue 9 01 18


72 Tower Delivery and Installation incl accessories 18 days Thu 1 02 18

73 RFI 1 day Mon 26 02 18


74 Completion Including Demobilization 5 days Tue 27 02 18
75 Permitting Post-con 10 days Tue 27 02 18

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017
24 Dec '17 31 Dec '17 7 Jan '18 14 Jan '18 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 4 Mar '18 11 Mar '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017
24 Dec '17 31 Dec '17 7 Jan '18 14 Jan '18 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 4 Mar '18 11 Mar '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017
24 Dec '17 31 Dec '17 7 Jan '18 14 Jan '18 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 4 Mar '18 11 Mar '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: SPILL OVER DP3
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

INTERLUX CORPORATION
Date: Dec 7, 2017