TABLE OF CONTENTS
1.0 PURPOSE ............................................................................................................................................. 3
2.0 QUALIFICATION................................................................................................................................... 3
3.0 DEFINITIONS AND ABBREVIATIONS ................................................................................................ 3
3.1 Definitions ........................................................................................................................................ 3
3.2 Abbreviations ................................................................................................................................... 3
4.0 REFERENCE DOCUMENTS ................................................................................................................ 4
5.0 PIPING MATERIAL MAINTENANCE REQUIREMENTS ..................................................................... 4
6.0 PIPING FABRICATION AND INSTALLATION QUALITY CONTROL ................................................ 4
6.1 Underground Piping ......................................................................................................................... 4
6.1.1 Responsibility ................................................................................................................ 4
6.1.2 General Inspection Content .......................................................................................... 4
6.1.3 Forms ............................................................................................................................ 5
6.2 Aboveground Piping ........................................................................................................................ 5
6.2.1 Responsibility ................................................................................................................ 5
6.2.2 General Inspection Content .......................................................................................... 5
6.2.3 Forms ............................................................................................................................ 6
6.3 Welding Inspection .......................................................................................................................... 6
6.3.1 Responsibility ................................................................................................................ 6
6.4 General Inspection Content ............................................................................................................. 7
6.4.1 Assign Numbers to Field Pipe Welds ............................................................................ 7
6.4.2 Visual Check and Acceptance (By Foreman) ............................................................... 8
6.4.3 Inspection by the Welding Inspector - (Certification Required) ..................................... 8
6.4.4 Surveillance ................................................................................................................... 9
6.4.5 Forms ............................................................................................................................ 9
6.5 Nondestructive Examination ............................................................................................................ 9
6.5.1 Responsibility ................................................................................................................ 9
6.5.2 General Inspection Content ........................................................................................ 10
6.5.3 Perform RT, UT, MT, PT, PMI, HT .............................................................................. 10
6.5.4 Technical Supervision of NDE .................................................................................... 11
6.5.5 Weld Selection and Status Maintenance .................................................................... 11
6.5.6 Selection of Welds under a random radiographic program ............................................... 11
6.5.7 Identify the welds to be radiographed............................................................................... 11
6.5.8 Coordination of Weld Repairs ............................................................................................ 12
6.5.9 Forms ................................................................................................................................. 12
6.6 Positive Material Identification Examination .................................................................................. 12
6.6.1 Responsibility .............................................................................................................. 12
6.6.2 General Inspection Content ........................................................................................ 13
6.6.3 Forms .......................................................................................................................... 14
6.7 Hardness testing (if required) ........................................................................................................ 14
6.7.1 Responsibility .............................................................................................................. 14
ATTACHMENTS
This procedure applies for quality control for excavation, backfill, pre-fabrication, installation, NDE
inspection, pressure testing, welding, positive material identification, etc.
2.0 QUALIFICATION
Pipes pre-fabrication and installation Inspector shall have 5 years experience working with applicable
industry codes and conducting inspections during construction and fabrication in the petrochemical
industry. Less experience may be considered with documented formal education or technical training.
3.1 Definitions
3.2 Abbreviations
RT Radiographic Testing
UT Ultrasonic Testing
VE Visual Examination
PT Penetration testing
All pipes, fittings, valves, instruments, and special items should be 100% VE when arrived. Valves,
instruments, and special items need to inform COMPANY, and fill in the relevant quality forms.
A uniform color-strip system must be applied to materials management for traceability. For example, the
same size pipe but different wall thickness shall be mark different color by marker.
6.1.1 Responsibility
Excavation release will be signed off prior to the excavation. The location that has been laid out for
excavation will be accepted by the Construction Engineer and the Superintendents. Inspect the pipe
trench, dimensions as per drawing. Compaction test should be done before laying pipe. inspecting the
bedding.
Verify that pipe fabrication and installation activities are performed in accordance with the requirements
documented in the applicable drawings and specifications.
Backfill Release Form F75001, will be signed off prior to backfilling. At this time, all work will be verified as
complete, including punch list items and holiday tests before filling over piping. Before filling over welded
joints the pressure test must be complete
6.1.3 Forms
6.2.1 Responsibility
Pressure Test Subcontractor / WQ1 P01R, P04R Per 000 509 7520
Surveillances Site Quality Manager F02201, F02209, F02221 During life of activity
Verify that pipe fabrication and installation activities are performed in accordance with the requirements
documented in the applicable drawings and specifications.
Reference Procedure 000 509 7560 for the cleaning of pipe inspection and testing requirements.
Verify that required pressure testing has been performed and documented in accordance with Procedure
000 509 7520. Document completed test on Form F75201 and ExxonMobil Mechanical Check Record
P01R and P02R.
6.2.3 Forms
6.3.1 Responsibility
Develop a weld map by assigning identity numbers to all pipe field welds on the isometric drawings,
including site pipe shop fabrication welds, prior to the start of work. Number the welds consecutively in the
direction of flow, starting with the first weld on each isometric sheet as No. 1, continuing through the last
weld on that sheet. If the drawings break at a weld, and the weld appears on both drawings, assign the
number on the upstream drawing. If additional welds must be added later to facilitate actual fabrication,
the weld locations shall be identified with the next available consecutive number until all additional welds
between design welds are identified. A log may be used to identify the weld numbers already assigned to
insure that no duplication of weld numbers occur. The inside weld of a slip on flange will carry the suffix
"S".
Attachment welds, such as shoes or other supports shall be numbered with the next available number
using the prefix "X". In the case of a reinforcing pad, all welds will refer to the field weld number joining
the branch to header pipe. Use the prefix "PB" and "PH" for pad to branch and pad to header
respectively.
When straight run pipe is being double jointed on the ground, and it is not certain to which line it belongs,
then use the prefix "DJ' before these field welds. Maintain a separate log of °"DJ" welds and assign
unique numbers starting with DJ-1. "DJ" welds are marked at 180 intervals. Weld maps shall accurately
show the final location of all "DJ" welds.
Note: Welder, NDE, PMI, PWHT information/results need not appear on the weld map but must be readily
traceable to the weld map and placed with the weld map at system completion.
Certain things need to be emphasized: Remember that it is of primary importance to assign a unique weld
number to all field welding. Once this number is assigned, do not change it for any reason. Do not
renumber isometrics to keep the weld numbers consecutive in the direction of flow. Use the next available
number for any alterations or additional welds. If a portion of piping containing assigned welds is cut out
of a system and discarded do not reuse these weld numbers but note on the isometric that these welds
are void and show the new welds on the current isometric revision. Cut shop welds will be assigned field
weld numbers.
In-process checking and surveillance of fabrication/erection welding is considered part of the foreman's
normal supervisory duties, and includes: welder qualification verification, materials verification, control of
welding consumables, joint preparation, fit-up, preheat, interpass heat, weld procedure variables, weld
condition between passes, and the appearance of all finished welds. Acceptance criteria is provided by
the applicable attachment to this procedure.
For all welds in piping systems and for all other welds requiring post weld heat treatment or NDE, the
foreman will prepare a "Daily Welding Report" (F79001) for completed welds to indicate his daily
production and to document his visual check and acceptance of each weld. The foreman's signature on
this form indicates his acceptance.
The foreman provides these reports daily to the Certified Welding Inspector. If a weld is repaired because
of rejected radiography, the identity of the repaired weld will maintain the identification number previously
assigned except the designation "R1" shall be added after the joint number. A suffix shall designate
subsequent repairs of the same welds, such as R2 and R3, until the weld is determined to be acceptable
by radiographic examination. If welds are completely cut out the suffix shall be C1, C2, etc.
The foreman should identify the first two welds made by a new welder, welding on a system requiring
random RT, by noting in the "Remarks" section "1st weld" or "2nd weld" so that these welds can be
examined by radiography to confirm welding proficiency in production.
Except as noted below, a minimum of 5% of groove welds shall have fit-up inspection by the inspector.
Each welder's work is to be represented. This percentage is to be increased, if necessary, to satisfy the
inspector that acceptable workmanship is being achieved. The inspector should normally be able to
achieve adequate fit-up inspections without establishing hold points, but he may request hold points for
fit-up inspection of specific joints.
The "visually inspected" block on the form is initialed by the inspector to indicate joints on which he
performed fit-up/final inspection. The inspector's signature on the Daily Welding Report indicates his
acceptance of the completed weld(s). Acceptance criteria is specified by the applicable attachment to this
procedure.
The inspector should also verify that the Daily Welding Report has been accurately completed and the
listed weld joints have been identified with the welder's stamp. The inspector provides these reports daily
to the NDE Coordinator for scheduling of NDE.
If the inspector considers any of the reported welds to be unacceptable, he will inform the foreman. If it is
not repaired prior to turning in the Daily Welding Report, the unacceptable welds are lined out and
recorded on a Surveillance Report (F02201) for tracking to closure.
6.4.4 Surveillance
Surveillance as described by procedure 000 509 0220 is to be performed for all welding activities
including post weld heat treatment using the applicable attachments to this procedure and the approved
PWHT procedure. Surveillance Reports (F02201) will be prepared for all deficiencies found during
surveillance or inspection. Surveillance reports will also be prepared for welds that were not subjected to
the inspection described above by the Certified Welding Inspector (i.e., category D piping).
Completion of Post Weld Heat Treatment will be documented on "Post- weld Heat Treatment Log"
(F79002). The log is to be provided to the NDE Coordinator for scheduling hardness test if required .
Welds requiring Code Stamping shall be examined and documented in accordance with "Fluor Quality
Control System Manual, Boiler and Pressure Vessel Code Work," or the applicable Subcontractors quality
program for boiler and pressure vessel code work.
Certification of Welding Inspectors shall be performed in accordance with Fluor Procedure 000 511 0101
"Certification of Nondestructive Examination Personnel."
For welded branch connections, perform final Weld Examination of the branch connection pressure weld
prior to the addition of any reinforcing pad or saddle. For welds that will be inaccessible for inspection due
to the fabrication process (E.g.: jacketed pipe, etc.) perform a visual inspection before fabrication renders
these welds inaccessible.
6.4.5 Forms
Methods within the scope of this procedure include radiographic testing (RT), ultrasonic testing (UT),
magnetic particle test (MT), liquid penetrant test (PT), positive material identification test (PMI) and
hardness test (HT).
6.5.1 Responsibility
Fluor personnel performing RT, UT, MT, PT, and PMI are to be qualified and certified to the requirements
of NDE Practice 000 511 0101 "Certification of Nondestructive Examination Personnel". Personnel
performing hardness tests must be trained in the use of the equipment and procedure but do not require
certification.
Fluor self-performed NDE will be performed in accordance with the referenced NDE procedures.
Volumetric Nondestructive Tests should be completed and results reported within 24 hours after the
welds are reported as complete. For special circumstances, such as the start of the welding program, or
when the NDE Contractor does not have a jobsite laboratory, welds requiring radiography may be
accumulated, but in these cases there should not be a backlog of more than ten (10) welds.
Other NDE methods should be completed as soon after the NDE request as practical.
The activities listed under Technical Supervision of procedure 000 509 0090 and activities listed under
the NDE Coordinator responsibilities of 000 509 0040.
Log the radiographic examination results for random radiography on Form F79201 "Welder B31.3
Random Radiography Control Log". Post the completed welds reported by the foreman, the date reported,
and the results of radiography on the Weld Map. Notify the Foreman and Welding Specialist of the results.
For random radiography, when a weld is rejected, select two previous similar welds by the same welder,
from a specified sample lot, for additional radiography, in compliance with ANSI B31.3. The selection shall
be made from the welder's history on Form F79201 "Welder B-31.3 Random Radiography Control Log.
The welds are to be selected from the sample lot used to select the initial weld.
Selection of welds and maintenance of status can be performed using the computer program NEWS. In
this case, the forms for manual weld tracking (F79201 and F79204) do not need to be maintained. It is
recommended that the NEWS program be used for projects with 200 or more joints to be radiographed.
Issue periodic weld reject rate reports for welds examined by radiography using Form F79203,
"Radiographic Rejectable Defects Statistics". When statistical data indicates high or increasing reject
rates, the Site Manager, the Welding Specialist, and the Quality Manager shall be informed. A copy of the
weld reject rate reports should be sent to the Construction Technology Welding Engineer.
NOTE: Informative RT shall not be performed on welds that have been capped out.
6.5.9 Forms
6.6.1 Responsibility
NDE Coordinator/
Document Results F79301, F79302, F79304 Each test
Subcontractor
Resolve Accept and Site Quality Manager Project Specifications Per Rejects
Rejects
Contractor Quality
PMI of Welds Project Specifications Per Specification
Manager
PMI will be performed by trained personnel whose ability to successfully operate the PMI test equipment
has been documented by test
Non-destructive methods used for PMI testing shall be capable of identifying the material quantitatively.
All field installed alloy piping will be 100% PMI verified in the “as installed” position. Each spool and the
weld will be verified and results documented on the fabrication spool drawing/isometric, listed on the PMI
point sheet and marked with the appropriate verification color by the PMI Technician as each point is
analyzed.
If the PMI test results fall outside of the acceptable ranges, the item will be rejected.
All rejected materials shall be isolated in a "Quarantine" area, tagged "REJECTED", and a
Nonconformance Report initiated.
6.6.3 Forms
6.7.1 Responsibility
FREQUENCY OF
ACTIVITY RESPONSIBILITY DOCUMENTATION
ACTIVITY
Hardness Testing
Contractor Prior to start of work
Equipment
F79501 Yearly.
Personnel Training &
Contractor
Vision Test
F79502 Yearly
Preparation of Surface to
Contractor Each test location
be Tested
Obtain a copy of the Code/Job Specification requirements prior to the start of work.
Obtain the hardness testing equipment required or contract with a supplier of hardness testing services.
Assure that the personnel performing the hardness testing have been trained in the use of the equipment
or have used the equipment within one (1) year and have a current vision test (Jaeger 2 at 12 inches
minimum within one (1) year).
Assure that the surface to be tested is buffed/filed to a relatively flat smooth texture to avoid erroneous
measurements which may result from a coarse surface. Care must also be taken to assure that any
grinding or other mechanical working does not generate sufficient heat to affect the material hardness.
Perform the hardness testing in accordance with the equipment manufacturer's written procedure as
required by the code or job specification. For hardness testing in the weld heat affected zone (HAZ), the
test instrument indenter shall not be greater than three (3) millimeters across the tip.
Report hardness testing results. For local hardness testing on welded joints, three tests shall be
conducted at each location required by code or job specification. Each reading shall be reported and the
average for the three shall be computed and reported on Form F79503.
6.7.3 Forms
6.8.1 Responsibility
Responsibilities Subcontractor
Define Test Boundaries Subcontractor P01R, P02R, P04R Each Test Package
Provide Preparation / Test Pipe Const. Engr. P01R, P02R, P04R Each Test Package
Instructions
Perform Pre-Test
Quality Manager P01R, P02R Prior to Test
Inspections/Release
Complete ExxonMobil MC WQ1/ExxonMobil P01R, P02R, P03R, For each HYDRO Test
Check record P04R, P05R, P06R and Re-instatement
Boundaries and instructions in accordance with 000 250 3707 should be prepared and provided or made
available to those responsible for Preparing the System for Testing, Performing Pre-test Inspection
Release, Performing Test, and Verifying Satisfactory Test Results - Information should be included in
pressure test packages. These packages are, as much as possible, to be assembled so that they
comprise a portion or all of a piping system. This is required to facilitate system turnover at the end of the
job. Each pressure test package shall contain the following :
• Marked up P&IDs indicating extent of test; location and type of blinds; and equipment or
instrumentation to be included or excluded from test.
• Piping isometrics for lines included in the test. Isometrics are to indicate location of blinds, valves open
or closed, fill point, vent locations, equipment or instrumentation excluded from test and locations of
required temporary supports.
Make preparation for testing as required by test instructions, 000 250 3707 and 000 250 50050
Verify completion (by walk down) and acceptance of any required inspection, post weld heat treatment,
NDE, hardness testing, PMI, and any other required test/inspections. (Validate weld inspection and NDE
completion through NEWS NDE Clearance Reports.)
Verify piping system has been completely checked (punched out) and preparations for testing as required
by test instructions are complete.
Upon the attainment of the required hydrostatic test pressure, for at least the minimum specified time, an
inspection shall be made of all joints and connections. The inspection shall be made while the system is
at the required test pressure.
Following the application of the pneumatic test pressure and reduction to the design pressure the entire
line should be walked to determine if there is any audible evidence of leakage. Any leaks found at the
time shall be marked and repaired after first depressurizing the line. After this walkdown, all joints and
welds shall be covered with a soap solution in order to detect any leakage. Soap shall be commercial
preparation specifically for leak detection.
Complete the Pressure Test actual test conditions for Test Media/Metal temperature, Test Pressure Test
Gage Number and Calibration information.
Instructions to comply with reinstatement requirements of 000 250 50050 should be provided or made
available to those responsible for restoring the system after pressure testing and for verifying completion
of restoration. Information should include:
• Instructions for removal of temporary test material (blanks, blinds).
• Positioning of operating blinds.
• Draining instructions.
• Installation of equipment excluded from field test (valves, orifice plates, expansion joints, short pieces
of pipe, new gaskets, bolts, vessel internals, etc.).
• Instructions for removal of temporary supports.
• Resetting spring hangers.
• Drying of instruments.
• Treatment of vent and drain connections.
• Cleaning of strainers.
• Painting and insulation.
Verify that all reinstatement activities have been completed and the system(s) or partial system
represented by this pressure test report is complete.
6.8.3 Forms
6.9.1 Responsibility
Monitor chemical
QC Inspector ExxonMobil Form P07R Daily during activity
cleaning process
Verify that pressure testing and NDE are complete prior to release for cleaning.
Monitor chemical cleaning process verifying that it is performed in accordance with approved project
specifications and document on the pipe cleaning and verification checklist (P07R).
Retain water test report and certificate of conformance and attach to the pipe cleaning and verification
checklist (P07R).
6.9.3 Forms
Contractor shall ensure that the Company Representative is given sufficient time to witness tests and re-
inspect Work performed by Contractor. Unless otherwise specified in the Contract Specifications. The
times listed in Table 3 below are considered minimum notification periods.
Attachment A
Attachment B
Description Of Item/Work
Inspected/Observed:
Observations/Deficiency:
Name Title
Notes:
Name: Name:
Signature: re: Signature:
Date: Date:
Iso No.:
RT RT
Welder RT Report Welder RT Report
Weld No. Date Made PMI PWHT Weld No. Date Made PMI PWHT
Stencil No. Stencil No.
ACC REJ ACC REJ
Engineer: Date:
Inspector: Date:
Insulation Materials
01 Proper Materials
02 Verify insulation materials are free from damage
03 Verify insulation materials shelf-life has not expired
Remarks:
Contractor/Construction
Contractor/Quality Rep. Company Rep.
Rep.
SUBCONTRACTOR AREA
Foreman Date
Mark Completion
Log No. Line No. Line Class Sheet. Weld No. Weld Circuit. Initials
No. Date
Welding
Supervisor: Date:
Inspector: Date:
For Each
Selected
Two B31.3 Tracer
Date Welded
Reject
Welds
Date Examined
Rejected (R)
Accepted (A)
Defects And
Drawing Number
Weld No.
Disposition
(Line And Sheet)
NONDESTRUCTIVE EXAMINATION
F79202
REQUEST/RECORD
Type Examination
Liquid Hardness
Penetrant Testing Requested by:
Examination Data
Location:
P No./Material:
Pipe Size/Schedule:
Note: The Following Identification Shall Be Plainly And Permanently Included On The
Radiographic Film: Project No., Line No., Weld No., Welder Symbol, Date Of
Radiography.
Cracks Cracks
Undercut Undercut
Porosity Porosity
Remarks
al Notes:
1. This exhibit is to be used to track weld quality levels as determined by butt weld
radiography.
2. Keep separate records for each weld process, controlling code, random or 100%
radiography.
3. Report high or increasing defect rates or repetitive defect types to the Jobsite Welding
Specialist and the Construction Project Manager.
RT/UT PT/MT
Weld Welder Date PWHT BH
Accept Accept Remarks
No. Symbol Welded Date Date
Date Date
nal Information
PMI Supervisor:
Signature/Date
Analyzed Date:
Material Verified
Item Line Item Description Type, Material PMI
QTY Body Bonnet Stem Remarks
No. Size, Rating Type
Accept Reject
Subcontracto
Client Sub – System:
r
Subcontractor:
Exxonmobil Other Location:
Analyzed Date:
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
This is to verify that has been trained in the use of the Hardness
Testing Equipment described below or has successfully used this equipment within the past year.
Description of Equipment:
Passed
Failed
Corrected
Uncorrected
Remarks/Comments:
2.1
HARDNESS TESTING REPORT F79503
BM
HAZ
WM
HAZ
BM
BM
HAZ
WM
HAZ
BM
Remarks:
MC CHECK RECORD
P01R – Test Pack Isometric Index
REV.
PAINT TRACING INSUL.
ISOMETRIC NO. LINE NUMBER P & ID
SYSTEM Y / N CLASS PUNCH NO.
SIGNATURE
DATE
MC Check Record
P02R – Piping Pressure Test Certificate
FLUSHING □ □ □
PRESSURE TESTING □ □ □
REINSTATEMENT
ALL ITEMS (CONTROL VALVES, ETC.) REMOVED FOR CLEANING AND TESTING HAVE BEEN REINSTATED
AS PER P&ID
□ □ □
ALL TEMPORARY VENTS AND DRAINS HAVE BEEN REMOVED, AND OPENINGS CLOSED IN ACCORDANCE
WITH SPECIFICATION.
□ □ □
COMMENTS
TEST PRESSURE MEASUREMENT INSTRUMENT SHALL BE CALIBRATED AND ITS RECORDED TEST PRESSURE TRAVEL AND
TEMPERATURE CHART IS TO BE ATTACHED TO THIS CERTIFICATE.
SIGNATURE
DATE
MC Check Record
P03R – Piping Test Equipment Calibration Record
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
DATE PICKLING:
RANGE
ZERO
INPUT OUTPUT (R) BARG % ERROR INPUT OUTPUT (R) BARG % ERROR
RANGE
ZERO
INPUT OUTPUT (R) BARG % ERROR INPUT OUTPUT (R) BARG % ERROR
RANGE
ZERO
DEAD W EIGHT TESTER SERIAL NO. :
TEST CERTIFICATE NO. DATE OF ISSUE EXPIRY DATE
TEMPERATURE RECORDER DATA (CALIBRATION CHECK CYCLE)
Contractor/ Construction
VERIFIED BY Contractor/Quality Rep. Company Rep.
Rep.
SIGNATURE
NAME
DATE
MC Check Record
P04R - Piping System Flushing and Testing Record
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
REMARKS: PICKLING:
NOTES
1 ALL TEST AND CALIBRATION CHARTS TO BE SIGNED, VERIFIED AND IDENTIFIED WITH THE TEST NUMBER.
2 W HERE TEST IS NIT WITNESSED STATE NA.
Contractor/ Construction
VERIFIED BY Contractor/Quality Rep. Company Rep.
Rep.
SIGNATURE
PRINT NAME
DATE
MC Check Record
P05R – Bolt Tensioning / Torque
SIGNATURE
PRINT NAME
DATE
MC Check Record
P06R – Piping Re-Instatement
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
1. NG, HYDROSTATIC TESTING AND DRYING HAS BEEN COMPLETED AND DOCUMENTED. □ □ □
YSTEM HAS BEEN REINSTATED IN ACCORDANCE WITH THE LATEST REVISION OF THE
2. □ □ □
P&ID’S, ISOMETRICS AND LAYOUT DRAWINGS.
CT BOLTS AND GASKETS ARE INSTALLED AT ALL RE-INSTATED JOINTS (ITEMS THAT
3. □ □ □
WERE REMOVED).
NTS/DRAINS ARE INSTALLED IN ACCORDANCE WITH THE DRAWINGS (ALL PLUGGED WITH
5. □ □ □
IN SPEC PLUGS AT COMPLETION).
LVES FUNCTION PROPERLY AND ALL HANDLES/HAND WHEELS ARE RE-INSTALLED AND
9. □ □ □
LUBRICATED.
AIN WHEELS AND EXTENDED HAND WHEELS REQUIRED FOR SPECIFIED VALVES HAVE
10. □ □ □
BEEN RE-INSTALLED.
E INTERNALS OF CHECK VALVES HAVE BEEN REMOVED OR LOCKED OPEN, CHECK THAT
12. □ □ □
INTERNALS HAVE BEEN REPLACED OR LOCKS HAVE BEEN REMOVED.
15. RM THAT ALL CHECKS PERFORMED FOR WDCL 02A REMAIN VALID. □ □ □
ANY “NEW” ITEMS ADDED AFTER TEST ARE CORRECT MATERIAL AND TRACEABILITY OF
16. □ □ □
ALL ITEMS IS DOCUMENTED (IF REQUIRED).
COMMENTS
OUTSTANDING PUNCH LIST ATTACHED? ( YES / NO.)
SIGNATURE
PRINT NAME
DATE
MC Check Record
P07R - Chemical Cleaning
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
NO
ACTIVITY DESCRIPTION OK N/A P/L
CHECK THAT EQUIPMENT LINES ARE CLEAN PRIOR TO START OF CLEANING (OR
1 □ □ □
INCLUDE IN CLEANING WITH ENGINEERING APPROVAL.)
COMMENTS
Contractor/
VERIFLED BY Contractor/Quality Rep. Company Rep.
Construction Rep.
SIGNATURE
PRINT NAME
DATE
MC Check Record
P08R – Hot Oil Flushing
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
2
CONFIRM SYSTEM / EQUIPMENT BLINDED OFF PRIOR TO START OF FLUSHING
(IF REQUIRED)
□ □ □
3
CHECK THAT PIPE / EQUIPMENT CHEMICALLY CLEANED AND/OR DE-SCALED (IF
REQUIRED)
□ □ □
Contractor/ Construction
VERIFIED BY Contractor/Quality Rep. Company Rep.
Rep.
SIGNATURE
PRINT NAME
DATE
MC Check Record
P14R - Flange Alignment Report
EQUIPMENT DESCRIPTION
SUB-SYSTEM DESCRIPTION
2 GASKET EXAMINED AND CONFIRMED CORRECT SIZE AND RATING, CLEAN AND DAMAGE FREE. □ □ □
3 NUTS AND STUD BOLTS EXAMINED AND CONFIRMED CORRECT SIZE, TYPE AND DAMAGE FREE. □ □ □
JOINT PULLED UP EVENLY WITH NO VISIBLE DAMAGE TO GASKET AND THREAD LENGTH
5
THROUGH NUTS ACCEPTABLE.
□ □ □
FLANGE ALIGNMENT
NO DESCRIPTION LINE NO. * GASKET TYPE PUNCH NO.
(OK / ADJUST)
Contractor/ Construction
VERIFIED BY Contractor/Quality Rep. Company Rep.
Rep.
SIGNATURE
PRINT NAME
DATE