D.M. CONSUNJI, INC.

THE MAVEN AT CAPITOL COMMONS


Capitol Commons, Brgy. Oranbo, Pasig City

METHOD STATEMENT FOR THE ASSEMBLY OF TEMPORARY ACCESS STAIR


FROM BASEMENT 7 TO LEVEL 1

I. OBJECTIVE

The objective of this Method Statement is to detail the procedure for the assembly of
temporary access stair from basement 7 to level 1.

II. SCOPE

The work includes supply of labor, materials, tools, equipment and services necessary to
carry out the proper erection of scaffoldings and strong hold for safety features of
temporary access stair.

III. TOOLS

1. Chipper/ Combi Hammer


2. Welding Machine
3. Cutting Outfit
4. Level Bar
5. Cut-off Saw
6. Circular Saw
7. Plumb bob
8. Nylon Strings
9. Nylon Rope

IV. MATERIALS

1. A-Frame 1.9m x 1.2m


2. A-Frame 1.7 x 1.2m
3. Jack Base
4. Steel Catwalk/ Walking Galvanized Board
5. Scaffold Steel Hot Dipped Galvanized Stair
6. Cross Braces
7. Scaffold pipe & Swivel/ Fixed Clamps
8. Safety Nets
9. Welding rods
10. Phenolic Board
11. ɸ20mm steel bars
12. Tie Wires
13. 50mm x 50mm wire mesh
14. Oxy-Ace Tank

V. PROCEDURE

1. Identify strategic location of the temporary access stair from basement 7 to Ground
floor level.

2. Lay out the location of temporary access stair on basement 7.


3. Ensure the soil is fully compacted, prior assembly of scaffolding

4. Construct pulley at ground level alongside the location of the temporary access stair for
an easy access of materials to be haul.

5. Install all pulley accessories and start hauling of scaffolding from ground down to
basement 7

6. Ensure hauled materials are enough to form first layer, then start the assembly of
scaffolding.

7. Once finish check and align the levelness of the first layer of scaffolding.

8. Assemble scaffold pipe at every two layer interconnected to A-Frame as shown on shop
drawing.

9. Always check the vertical alignment for every additional fitting of scaffold.

10. Fix and weld ɸ20mm rebar to dowel drilled on excavated wall trench and to scaffold
pipe at the other side.

11. While assembly of scaffolding is on progress, installation of steel ladder and landing
platform will follow until completed and reached to the ground level.

12. Construct temporary access way connecting to landing platform at ground level. Provide
handrail at the access way using scaffold pipes.

13. Provide Toeboard at the perimeter of landing platform.

14. Provide safety net around the perimeter of the temporary access way and stair.

Prepared by:

Rodelio B. Gonzales
CQC Staff

Checked by:

Fernando O. Temario
CQC Head

Noted by:

Aris A. Cuevas
Sr. Project Manager