9-DEC-Civil
Check the surface of after coating for 1.access platform near tank columns for
DS7;2.pipe support columns (PS-D7-001-002-012-016-017-075-082-096-097-0098-
9-Dec 7:30 DS7 CE-C1555-R1 099-100-101-102-103-104-151A-152A)3.EYE WASH foundation (slope) in DS7.
Final inspection for the rebar , formwork and anchor bolts(including survey work) of:
CE-C1556-R1 1:pipe support columns ((PS-D6-001-002-003-004-005-035-037-038-050-052-054-
9-Dec 8:30 DS6
040-041-042-043-044-045-046-047-048-049);2.access platform(F1) in DS6
9-Dec 8:30 DS6 CE-C1557 Check the surface of after coating for containment for pumps in DS6.
Witness conducting compaction degree test for pipe support area (sixth
9-Dec 9:00 ALFO D8 LAB CE-C1558 layer,elevation=1.95) EAST-NORTH the 2400m³tank in DS7 .
Witness to test concrete cubes (compressive strength at 7 days) of 1.access platform
near tank columns for DS7;2.pipe support columns (PS-D7-001-002-012-016-017-
9-Dec 9:00 ALFO D8 LAB CE-C1559 075-082-096-097-0098-099-100-101-102-103-104-151A-152A)3.EYE WASH
foundation (slope) in DS7.
Check the formwork of grout for pump shelter (IQD8-
9-Dec 9:30 DS8 CE-C1560 PBE681052A/B;PAX681051A/B) and platform near the tank in DS8
Witness pump shelter (IQD8-PBE681052A/B;PAX681051A/B) and platform near the
9-Dec 9:30 DS8 CE-C1561 tank grouting (including temperature and make specimen (cubes) in DS8.
Final inspection for the rebar , formwork and anchor bolts(including survey work) of
9-Dec 10:30 DS7 CE-C1562 cartridge filters skid in DS7.
Sampling backfill soil for 1.pipe support area east of 1200m³tank(first
layer,elevation=1.35);2. pipe support area west of 2400m³tanktank(first
9-Dec 11:30 DS7 CE-C1563
layer,elevation=1.35);3. pipe support area east-south of 2400m³tank (sixth layer,
elevation=1.95) in DS7.
ISSUED
edule RESPONSIBILITY Date: 8-12-2017
Time:
West Qurna I
Produced Water Treatment M109