Work Planning Template Doc No: RF0737

Version: 3
Reference Material

Time Job/Task Location Person in Risk Tool


Charge Required

0800 Scaffolding transfer in E/R Deck Bosun TBT, Take 5

0800 Painting and stencils on deck Deck Bosun TBT, Take 5

0800 Bilge alarm test in void space forward Deck C/O PTW, TBT, Take 5

0800 BTHRM Anti skid & walkway BTHRM Bosun TBT, Take 5

0800 De rust and paint fire fighting isolation Deck 3/O TBT, Take 5
valve and associated area

0800 Vapor reducers chipping and painting Deck Pump man TBT, Take 5

0800 Stay wire greasing in PV breaker Deck Pump man TBT, Take 5

0800 Snap Back zone modification Deck Bosun TBT, Take 5

0800 A and D deck shelf measurement and Accommodation Bosun TBT, Take 5
planning

0800 Inspection of tails for Acu terminal Deck C/O TBT, Take 5
preparation

0800 Atmospheric condenser FW side ER 2AE TBT, Take 5


inspection

0800 Aux. vacuum condenser FW side ER 2AE TBT, Take 5


inspection

0800 Hypermist test run Steering rm 1AE TBT, Take 5

0800 AE Turbocharger inspection ER 2AE PTW,TBT, Take 5

0800 AE #3&4 Cooler fitting change ER 2AE TBT, Take 5

0800 BT-T1 change oil FWD 2AE TBT, Take 5

0800 ER Emc’y light installation ER ETO TBT, Take 5

0800 CPP plant alarm test/ Motor megger test ER ETO TBT, Take 5

0800 Rudder DP resetting ER ETO TBT, Take 5

Further Comments: