Overview
This document shows prerequisites for output message type AUFB and explains in which cases it is possible to send an order confirmation to the vendor.
Prerequisites
In case we create an our own message type by copying it from message type AUFB, in Customizing we have to
Set the “Indicator: Print operation” to 7 for the message type in OLME> Messages> Output Control > Messages Types > define Messages Type for
In PO TAB Confirmation a confirmation control key is maintained and the flag ”Order Acknowledgment requirement” is set on.
(PO date plus monitoring time) the system computes the following operation “PO date + 10 days”, it means that the vendor has to send me a confirmation within
the date X= PO date + 10 days. If the field Reference date is 2 (Delivery date minus monitoring time) the system computes the following operation “Delivery date in
PO - 10 days”, it means that the vendor has to send me a confirmation within the date X= Delivery date in PO - 10 days.
Steps to be followed:
0001.
A reminder can be generated, if the vendor doesn’t send a confirmation within the 30.09.2012 (= 10.10.2012 – 10 days).
2. The PO is printed via ME9F and output message type NEU is successfully
processed.
3. In order to see the reminder’ list that could be generated, we run transaction ME2A. If we run ME2A before the 30.09.2012 system doesn’t find reminders and
error message ME260 comes up. If we run ME2A after 30.09.2012, for example on 01.10.2012, we get the following
information:
It means that we can generate a reminder i.e. an output message AUFB. Remark: With ME2A it is possible to see a list of reminders, it is not possible to create
reminders.
save.
Via push button Messages, system jumps in the message screen on the PO
header.
5.Now it is possible to send the reminder AUFB to the vendor via ME9F.
6. Print preview for the message type NEU appears as