Sie sind auf Seite 1von 7

Demolition & Dismantling Works (Non-Heritage Block)

Bracing of Heritage Block (Peripheral Wall)


Al Shafi Enterprises Commencement Date: December 15, 2017
Daily Construction Report
Site Info:
Site Name Silk Bank Tower
Owner JCL Reporting Date DATE: 12-01-2018

Subcontractor No. Contractor Al-Shafi Enterprises


Daily Job Report # 29 Day of Week Friday

Weather
Weather type (Sunny/Cloudy/Rainy) Time Temperature C
Sunny 1200PM Max. 28`

Site Visitor
Name Organization Time In Time Out

ASE Site Staff:


Designation No. Work Hours Designation No. Work Hours
Project Manager 01

Project Engineer 01
Site Supervisor 01
Guard 02

Total 05
Demolition & Dismantling Works (Non-Heritage Block)
Bracing of Heritage Block (Peripheral Wall)
Al Shafi Enterprises Commencement Date: December 15, 2017

Daily Construction Report

Description of Works:
Current Week Targets:
Target Work Done Labor Details
Activity Job Today

Skilled Un-Skilled

Fencing (General Labors from ASE) Folder 02


1. Folding started at PSX Access side
Labor 03

Dismantling Contractor Labor 08


Dismantling work started at 1st floor of
NHB
Support Bracing work for Heritage Building Welders 06
Bracing work in progress
Pipes erected = 40 /1080 = 3.7% of total
Props of GF =360,
For three floor = 1080
Prop frame in process = 20

Total 08 11
(Skilled + Unskilled)
Total Manpower 20 NOS.

Back Log Activities


Back Log:
Activity Target Work Done Total Achieved Labor Details
Quantum Today

-
-
-