Demolition & Dismantling Works (Non-Heritage Block)

Bracing of Heritage Block (Peripheral Wall)


Al Shafi Enterprises Commencement Date: December 15, 2017
Daily Construction Report
Site Info:
Site Name Silk Bank Tower
Owner JCL Reporting Date DATE: 08-01-2018

Subcontractor No. Contractor Al-Shafi Enterprises


Daily Job Report # 25 Day of Week Monday

Weather
Weather type (Sunny/Cloudy/Rainy) Time Temperature C
Sunny 1200PM Max. 28`

Site Visitor
Name Organization Time In Time Out

ASE Site Staff:


Designation No. Work Hours Designation No. Work Hours
Project Manager 01

Project Engineer 01
Site Supervisor 01
Guard 02

Total 05
Demolition & Dismantling Works (Non-Heritage Block)
Bracing of Heritage Block (Peripheral Wall)
Al Shafi Enterprises Commencement Date: December 15, 2017

Daily Construction Report

Description of Works:
Current Week Targets:
Target Work Done Labor Details
Activity Job Today

Skilled Un-Skilled

Fencing (General Labors from ASE) Folder 04


1. State Bank (Office + Mech. room) Side
Fencing is in progress (85% completed) Labor 05

Dismantling Contractor Labor 00

Support Bracing work for Heritage Building Welders 06


Bracing work in progress
Total 10 05
(Skilled + Unskilled)
Total Manpower 15 NOS.

Back Log Activities


Back Log:
Activity Target Work Done Total Achieved Labor Details
Quantum Today

-
-
-