Beruflich Dokumente
Kultur Dokumente
3. Principle of Flow:
Muther said that, other things being equal, the best layout is one which arranges the work area
for each operation or process in the same order or sequence that forms, treats or assembles the
materials.
6. Principle of Flexibility:
It means the best layout is one which can be adopted and re-arranged at a minimum cost with
least inconvenience.
Keeping in view the type of industry and volume of production, there can be
following methods of layout:
(a) Line or Product Layout.
(d) Combination.
The raw material is supplied at one end of the line and goes from one operation to the next quite
rapidly with a minimum work in process, storage and material handling. Fig. 8.3 shows product
layout for two types of products A and B.
Suitability:
This is suitable for continuous process industries such as automobile manufacturing or chemical
industries.
Advantages:
1. It lowers the overall manufacturing time as product proceeds rapidly from operation to
operation without any handling.
2. Less space is needed for placing machines.
3. There is minimum of handling and transportation.
4. There is less work-in-process.
5. Better utilisation of machines and labour.
6. It minimises counting, inspecting, clerical work etc.
7. There is smooth flow of materials.
8. Promises for supply of products to customers are more reliable.
9. Use of gravity and power conveyors for material handling reduces the necessity of aisles.
10. Production control is simplified greatly.
Disadvantages:
1. When the model or type changes, the layout of machinery also requires a change.
2. All machines in the arrangement cannot be used to their maximum capacities.
3. The manufacturing cost rises with a fall in the volume of production.
4. If one or more lines are running light, there is great machine idleness.
5. Specialised and strict supervision is needed.
6. If any of the machines in the line breaks down the other machines have to remain idle till that
machine becomes again ready to commence operation.
7. For expansion purpose, it is not possible to add more machines.
8. Each worker performs job on a particular machine, so he is not skilled for other machines or
operations.
(b) Functional or Process Layout (Group Technology):
Under this arrangement each department or section is responsible for carrying out a particular
process and not a particular product as under line type layout. There are similar operations in
each department or section.
The process layout is particularly useful where low volume of production is needed. If the
products are not standardized, the process layout is more low desirable, because it has creator
process flexibility than other. In this type of layout, the machines and not arranged according to
the sequence of operations but are arranged according to the nature or type of the operations.
This layout is commonly suitable for non repetitive jobs.
Same type of operation facilities are grouped together such as lathes will be placed at one place,
all the drill machines are at another place and so on. See Fig. 8.4 for process layout. Therefore,
the process carried out in that area is according to the machine available in that area.
Suitability:
In this, similar equipment and similar machines are grouped together. This is very useful where
low volume of production is required.
Advantages:
1. Similar jobs are manufactured on similar machines, hence supervision is simple.
2. Less machines are required.
3. This offers great incentive for each worker to raise the level of performance.
4. There will be better control on precision or complicated process.
5. The layout is flexible, hence it can easily be managed to change in the rate of production, in
the design of products, in the methods of production or in the raw materials used.
6. Breakdown of any one machine does not affect production as its work can be done on a
standby machine.
7. Capital layout for machines is minimum.
8. New workers have better training facilities on the job. Workers know how to run various
machines in the group and also to set-up work.
9. Foremen become specialised in the performance of the job and know all about the
equipment’s and their operations.
Disadvantages:
1. Handling and back-tracking of materials is too much.
2. It makes necessary to plan and supervise the work of each department, each worker and
machine. This makes production control more difficult and more costly.
3. Generally more floor area is required.
4. Specialization creates monotony and there will be difficulty for the workers to find job in
other industries.
5. Total production cycle time is more due to long distances and waiting.
6. Routing and scheduling is more difficult, as the work does not flow through any definite
mechanical channels.
7. There are no cheaper and automatic devices for internal transportation.
8. Inspection of work for each operation is necessary as the material passes to the next
department. This results in more inspections and causes delay.
9. More training will be required to prepare the workers for the jobs.
(c) Fixed Position Layout:
This type of layout is the least important for today’s manufacturing industries. In this type of
layout the major component remain in a fixed location, other materials, parts, tools, machinery,
man power and other supporting equipment’s are brought to this location.
The major component or body of the product remain in a fixed position because it is too heavy
or too big and as such it is economical and convenient to bring the necessary tools and
equipment’s to work place along with the man power. This type of layout is used in the
manufacture of boilers, hydraulic and steam turbines and ships etc.
Advantages:
1. Capital investment is minimum.
2. Continuity of operations is ensured.
3. Less total production cost.
4. Less material movement.
Disadvantages:
1. Machines and tools etc. take more time to reach to the work place.
2. Highly skilled workers are required.
3. Complicated jigs and fixtures may be required in fixing jobs, tools etc.
(d) Combination Layout:
Now-a-days any one form of layout in pure state is rarely found. Therefore, a combination of any
of the three methods is formed according to the requirement of an industry. In factories, where
products are first manufactured and then assembled this method is mostly used.
Various managerial policies relate to future volume of production and expansion, size of the
plant, integration of production processes; facilities to employees, sales and marketing policies
and purchasing policies etc. These policies and plans have positive impact in deciding plant
layout.
Production of heavy and bulky items need different layout as compared to small and light items.
Similarly products with complex and dangerous operations would require isolation instead of
integration of processes.
Job production involves intermittent process as the work is carried as and when the order is
received. Ship building is an appropriate example of this kind. This method of plant layout viz.,
Stationery Material Layout is suitable for job production.
Instead of making one single product as in case of job production a batch or group of products is
produced at one time, It should be remembered here that one batch of products has no
resemblance with the next batch. This method is generally adopted in case of biscuit and
confectionary manufacturing, medicines, tinned food and hardware’s like nuts and bolts etc.
Suitability of climate
Availability of raw materials Government policies
Nearness to the market Availability of finance
Availability of labor Competition between states
Transport facilities Availability of basic facilities(such as
Availability of fuel and power schools, hospitals, housing and
Availability of water recreation clubs, etc)
Disposal of waste
Break-even analysis entails the calculation and examination of the margin of safety for an entity
based on the revenues collected and associated costs.
Analyzing different price levels relating to various levels of demand, an entity uses break-even
analysis to determine what level of sales are needed to cover total fixed costs.
A demand-side analysis would give a seller greater insight regarding selling capabilities.
Advantages
PERT chart explicitly defines and makes visible dependencies (precedence relationships)
between the work breakdown structure (commonly WBS) elements.
PERT facilitates identification of the critical path and makes this visible.
PERT facilitates identification of early start, late start, and slack for each activity.
PERT provides for potentially reduced project duration due to better understanding of
dependencies leading to improved overlapping of activities and tasks where feasible.
The large amount of project data can be organized and presented in diagram for use in
decision making.
PERT can provide a probability of completing before a given time.
Disadvantages
The PERT chart is sometimes preferred over the Gantt chart, another popular project
management charting method, because it clearly illustrates task dependencies. On the other
hand, the PERT chart can be much more difficult to interpret, especially on complex projects.
Frequently, project managers use both techniques.
PERT chart for a project with five milestones (10 through 50) and six activities (A through F). The project has
two critical paths: activities B and C, or A, D, and F – giving a minimum project time of 7 months with fast
tracking. Activity E is sub-critical, and has a floatof 1 month.
Help you identify the activities that must be completed on time in order to complete the whole
project on time.
Show you which tasks can be delayed and for how long without impacting the overall project
schedule.
Calculate the minimum amount of time it will take to complete the project.
Tell you the earliest and latest dates each activity can start on in order to maintain the schedule.
The critical path is the sequence of activities with the longest duration. A delay in any of these activities
will result in a delay for the whole project. Below are some critical path examples to help you understand
the key elements...
The duration of each activity is listed above each node in the diagram. For each path, add the duration of
each node to determine it's total duration. The critical path is the one with the longest duration.
Float Determination
Once you've identified the critical path for the project, you can determine the float for each activity. Float
is the amount of time an activity can slip before it causes your project to be delayed. Float is sometimes
referred to as slack.
Figuring out the float using the Critical Path Method is fairly easy. You will start with the activities on the
critical path. Each of those activities has a float of zero. If any of those activities slips, the project will be
delayed.
Then you take the next longest path. Subtract it's duration from the duration of the critical path. That's the
float for each of the activities on that path.
You will continue doing the same for each subsequent longest path until each activities float has been
determined. If an activity is on two paths, it's float will be based on the longer path that it belongs to.
Determining Float
Using the critical path diagram from the previous section, Activities 2, 3, and 4 are on the critical path so
they have a float of zero.
The next longest path is Activities 1, 3, and 4. Since Activities 3 and 4 are also on the critical path, their
float will remain as zero. For any remaining activities, in this case Activity 1, the float will be the duration
of the critical path minus the duration of this path. 14 - 12 = 2. So Activity 1 has a float of 2.
The next longest path is Activities 2 and 5. Activity 2 is on the critical path so it will have a float of zero.
Activity 5 has a float of 14 - 9, which is 5. So as long as Activity 5 doesn't slip more than 5 days, it won't
cause a delay to the project.
The Critical Path Method includes a technique called the Forward Pass which is used to determine the
earliest date an activity can start and the earliest date it can finish. These dates are valid as long as all
prior activities in that path started on their earliest start date and didn't slip.
Starting with the critical path, the Early Start (ES) of the first activity is one. The Early Finish (EF) of an
activity is its ES plus its duration minus one. Using our earlier example, Activity 2 is the first activity on the
critical path: ES = 1, EF = 1 + 5 -1 = 5.
If an activity has more than one predecessor, to calculate its ES you will use the activity with the latest
EF.
The Backward Pass is a Critical Path Method techique you can use to determine the latest date an
activity can start and the latest date it can finish before it delays the project.
You'll start once again with the critical path, but this time you'l begin from the last activity in the path.
The Late Finish (LF) for the last activity in every path is the same as the last activity's EF in the critical
path. The Late Start (LS) is the LF - duration + 1.
In our example, Activity 4 is the last activity on the critical path. Its LF is the same as its EF, which is 14.
To calculate the LS, subtract its duration from its LF and add one. LS = 14 - 2 + 1 = 13.
You then move on to the next activity in the path. Its LF is determined by subtracting one from the
previous activity's LS. In our example, the next Activity in the critical path is Activity 3. Its LF is equal to
Activity 4 LS - 1. Activity 3 LF = 13 -1 = 12. It's LS is calculated the same as before by subtracting its
duration from the LF and adding one. Activity 3 LS = 12 - 7 + 1 = 6.
You will continue in this manner moving along each path filling in LF and LS for activities that don't have it
already filled in.
In Conclusion...
The Critical Path Method is an important tool for managing your project's schedule. As you can see, it's
not very difficult to determine it's key elements. However, once your project has more than a few
activities, critical path scheduling can become tedious.
GANTT CHART
INVENTORY
I s a complete list of items such as property, goods in stock, or the contents of a
building.
1. Time - The time lags present in the supply chain, from supplier to user at every stage,
requires that you maintain certain amounts of inventory to use in this lead time. However, in
practice, inventory is to be maintained for consumption during 'variations in lead time'. Lead
time itself can be addressed by ordering that many days in advance.
2. Seasonal Demand: demands varies periodically, but producers capacity is fixed. This can
lead to stock accumulation, consider for example how goods consumed only in holidays can
lead to accumulation of large stocks on the anticipation of future consumption.
3. Uncertainty - Inventories are maintained as buffers to meet uncertainties in demand, supply
and movements of goods.
4. Economies of scale - Ideal condition of "one unit at a time at a place where a user needs it,
when he needs it" principle tends to incur lots of costs in terms of logistics. So bulk buying,
movement and storing brings in economies of scale, thus inventory.
5. Appreciation in Value - In some situations, some stock gains the required value when it is
kept for some time to allow it reach the desired standard for consumption, or for production.
For example; beer in the brewing industry
ABC analysis
The ABC analysis (or Selective Inventory Control) is an inventory categorization technique. ABC
analysis divides an inventory into three categories- "A items" with very tight control and accurate
records, "B items" with less tightly controlled and good records, and "C items" with the simplest
controls possible and minimal records.
The ABC analysis provides a mechanism for identifying items that will have a significant impact on
overall inventory cost,[1] while also providing a mechanism for identifying different categories of stock
that will require different management and controls.
The ABC analysis suggests that inventories of an organization are not of equal value. [2] Thus, the
inventory is grouped into three categories (A, B, and C) in order of their estimated importance.
'A' items are very important for an organization. Because of the high value of these 'A' items,
frequent value analysis is required. In addition to that, an organization needs to choose an
appropriate order pattern (e.g. ‘Just- in- time’) to avoid excess capacity. 'B' items are important, but
of course less important than 'A' items and more important than 'C' items. Therefore, 'B' items are
intergroup items. 'C' items are marginally important.
‘A’ items – 20% of the items accounts for 70% of the annual consumption value of the items.
‘B’ items - 30% of the items accounts for 25% of the annual consumption value of the items.
‘C’ items - 50% of the items accounts for 5% of the annual consumption value of the items.
Another recommended breakdown of ABC classes:
A 10% 70%
B 20% 20%
C 70% 10%
Inventory ABC Classification (as known as ABC Analysis) is a term used to define an inventory
categorization technique often used in materials management.
The ABC Classification provides a mechanism for identifying items that will have a significant impact on
overall inventory cost, while also providing a mechanism for identifying different categories of stock that
will require different policy settings and inventory control.
The ABC analysis is done to manage different stocked items (or SKU’s) that are not all equal in value or
order frequency. A best practice is for an organization to group their inventory into three categories (A, B,
and C).
‘A Classification’ items are very important for an organization. Because of the high demand of these
‘A’ items, frequent value analysis is required. These are your fast moving and typically lower value
items that drive the largest percentage of your target service levels and customer satisfaction rates.
‘B Classification’ items are important, but of course less important than ‘A’ items and more important
than ‘C’ items. These are typically mid range in inventory value and order frequency.
‘C Classification’ items are marginally important. Typically, very low order frequency and high
inventory value. These items are usually stocked with very low quantities or not at all due to the high
carrying costs associated with the stock levels.
When it comes to classifying your inventory it is usually safe to follow the Pareto Principle, also known as
the 80/20 rule. The Pareto Principle is the theory that most businesses see 80% of their sales come
from roughly 20% of customers, which should fall into your A classification category.
ABC Classification for inventory management is a very similar approach. Classifying your inventory items
into A, B, C, and D (80%, 15%, 5%, 0%) based on sales volume is an industry best practice when
managing inventory.
The most common metric to use is your Annual Sales Volume when doing ABC Classification to calculate
your inventory for each group. For example, if you run the calculation and your A items represent 50% of
your inventory, you may not have enough inventory for these items to meet customer demand.
Special consideration needs to be taken for new and critical items in your inventory. For new products, it’s
an option to use yearly demand forecasting estimates to support demand estimates. For critical inventory
items, you need special monitoring so you don’t run out of stock on the essential items that might result in
customer turn elsewhere.