土建工作周计划 (2017 年 11 月 22-30 日)

Construction Work Weekly Plan (Nov 22nd-30th 2017)

Responsbile
编 Construction works and technical Duration
工作内容及技术要求 Deadline person
号 requirements 时间
负责人
Road concrete work front of the
Administration building
From the front door to the water
办公室前路面水泥浇筑—从大门
pump near the Administration
1 到办公室水泵部分 30th Nov 7 Adana
building
地坪 25CM 不需要垫层
Technical Requirements: Thickness 25
cm , no low cement concrete

The fourth layer concrete work of


脱硫池第四层浇筑
2 de-sulf foundation 30th Nov 7 Adana

Track foundation of Refining kettle


精炼锅前轨道基础
steel bar, 20cm concrete
3 20cm 混泥土 30th Nov 7 Adana
And concrete work of south of
及南面地坪,30cm 混泥土
refining kettle

水沟及地坪 Ditch and concrete work


4 30th Nov 7 Adana
大炉、合金工段、水沟地面 Between Furnace and ditch

Heat exchanger foundation


换热器基础
5 Sand and stone as low cement 30th Nov 7 Adana
砂石垫层,混泥土基础
concrete, concrete foundation
Car Wash pool and concrete road
6 洗车池及地坪 towards to the gate 30th Nov 7 Adana
30cm concrete

Break room concrete and ditch work


7 破碎车间的地坪和水沟 30th Nov 7 Adana
30cm concrete

Road concreting by the generate


8 东边路到配电室地坪 room 30th Nov 7 Adana
30cm concrete
Unloading bay platform concreting
卸车池上口浇筑平整及卸料台面 and unloading bay wall concreting to
9 30th Nov 7 Adana
浇筑 same level.
30cm concrete