5-1CP

Ms. Finkel and her team had designed a production process so that 8% of al 16-ounce
boxes of Go Bananas! Fail to meet the standard weight of banana flavored marsh
mallows. They had decided that if at least five boxes in a weekly sample fail to meet the
standard weight of banana flavored marsh mallows, they would shut down the
production. The objective of the study is to analyze following aspects.

The production process will shut down if at least 5 boxes in a weekly sample fail to meet
the given standard weight. The probability that a weekly sample will result into a
shutdown process, if production process is working properly is 0.0451.

GGG management wants to shut down the production of Go Bananas! No more than 1%
of time when the production process is working properly. Therefore, the minimum
number of boxes that must fail to shut down the production process is 25 only.

Ms. Finkel wants to reduce the percentage of 16-ounce boxes of Go Bananas! That fail to
meet the standard weight of banana flavored marsh mallows when the process is working
properly. The probability that at least five of the sampled boxes fail to meet the standard
to 0.01 or less is 0.000004.