Beruflich Dokumente
Kultur Dokumente
C.F. Mateus Marin, A. Gil Chacon, Weatherford; M. Monroy Barrios, Weatherford; E. Martinez, Ecopetrol S.A;
A.E. Patino, Schlumberger
This paper was prepared for presentation at the SPE Artificial Lift Conference-Americas held in Cartagena, Colombia 21-22 May 2013.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
conditions still.
Abstract
Introduction
After numerous artificial lift failures with PC pumping
installed in a new development field with high future Casabe south field is one of the most recent developments
growth, the production increase and application reliability of the Colombian state company in the Magdalena medio
were achieved through implementation of reciprocating area. From its prognosis it was designed to be produced
rod lift systems including several optimization key using a PCP artificial lift system, taking into
factors. consideration space disponibility, solid handling and the
excellent expericience in the adjacent field, convencional
This new artificial lift application was determined Casabe. However, during the installation of the first
considering primarily: gas production, API, BSW, solid systems in the wells CBES-04, CBES-07 and CBES-13,
production, well survey and production flow rate, all the presence of a high failure rate (run life less than 30
oriented to get a system which is anticipated the main days) associated principally to system’s affectation due to
issues identified in Casabe South field as erosion, poor gas handling, generated the need for additional
abrasion, cavitation, elastomer swelling, rod failures and technical analysis to establish the use of an alternative
low volumetric efficiency. artificial lift system that would maintain the economic
equilibrium of the project
Variable speed hydra-pneumatic units were introduced to
solve critical gas and flow rate variations to have change During the evaluation stage, Reciprocating rod lift system
options regarding operational parameters, i.e., speed and and Electric submersible systems were considered as the
stroke length, in instantaneous way to optimize viable technological alternatives, considering the
production levels using surface pumping with those particularities of the wells and the fluids to handle. This
advantages. paper describes the analysis performed, equipment used
and the results obtained using reciprocating rod lift
Gas Separators, Two-Stages Rod Pumps, Double Valves, systems, which nowadays has permit run lifes higher than
back pressure valve and Continuous Rod are the other 700 days without failures and the recover of the
technical components used within the optimization economical balance of the proyect, having in today a total
process developed; besides, a strict bottom-hole of 21 producing wells in this field.
monitoring and surface follow-up for every well are
programmed and carried out, which means down-hole Variable Speed Hydra-pneumatic Pumping Unit
gauges and rod pump controllers.
Operating with a conventional sucker-rod system, the
Change of mind started in March 2011 with Casabe VSH2 pumping unit was specifically developed for fields
South-4 well as field trial, after 3 interventions in less with heavy crude oil and wells with rodfall problems.
than 1 months and different problems with PC pumping, Nitrogen-over-hydraulic technology makes this unique
the performance of reciprocating rod lift system has surface-pumping unit capable of lifting greater loads and,
shown 715 days run life, no failures and under operating in some cases, using less energy than conventional units.
2 SPE 165052
The VSH2 unit offers variable speed control in both working with, in order to minimize the wear between the
directions and can accommodate polished-rod loads up to rods and the tubing, because the well is deviated and the
40,000 lb (13,144 kg) and pump to depths of up to 10,000 pump was going to be installed at 4300ft with an
ft (3,048 m) Fig. 1. inclination of 55o. Fig.5.
The VSH2 pumping unit offers maximum flexibility for a
wide range of requirements. Applications, both permanent In order to give versatility required by production a VSH2
and temporary, include testing wells (new and re-entry), surface equipment was installed, this pumping unit can
short-term repairs, projects with lengthy delivery times change its velocity independently in each stroke by
and dewatering gas wells. The VSH2 unit creates a viable simply turning the knob of a potentiometer and change its
alternative for keeping a well on production and on stroke length by simply moving a sensor on its mast.
schedule, saving operators valuable time and resources. Also, it works with a monitoring system in real time (Rod
Pump Off Controler, RPOC Wellpilot. Fig.6), with which
the performance of the downhole pump can be reviewed
Gas-Pusher pumps and operating time of the equipment can be optimized in
cases when the well’s fluid level decreases in order to
Gas-pusher pumps are API-type RHB pumps Fig. 2, maintain a constant pump fillage Fig. 7. In these cases the
designed for use in wells having a high gas-to-liquid ratio operator establishes a minimum value for pump fillage
(GLR). These pumps help minimize gas interference, gas and when the dinagraph has a lower value than the
lock and fluid pound. established, the unit stops and stays in a “stand-by” mode
for a determined time, enough for the well to recover the
A gas-pusher pump’s action is similar to that of a double- fluid level, when this time ends the unit starts again
stage compression pump with both low- and high- automatically.
compression chambers. On the upstroke, gas-laden fluid
enters the larger, low-pressure chamber below the This pilot was approved and the reciprocating rod lift
plunger. On the downstroke, the gas-laden fluid is system with a VSH2-150 unit was installed in the well
displaced into the smaller, high-pressure chamber above CBS-04 the 8th of March of 2011. Nowadays the well has
the plunger. On the next upstroke, the fluid held in the not presented any failure and has 715 days of run life,
high-pressure chamber is displaced further and discharged with a final production of 100 BFPD and an effective
through the exhaust ports of the top cage. As the highly submergence of 100 ft.
pressurized fluid is being discharged, the low-pressure
chamber is being filled. Performance
Conclusion
Glosary
Fig. 4 – Rotor Failure due to high torque. Fig. 8- Donwhole dynamometer card Casabe South 13
5.0
2.5
0 145.6
Tables