Details Plan for Certification of EN 15085-2 CL-1

1) Welding start on 22/01/2018 & maximum finish on 27/01/2018 for PQR Test Coupon.

2) Ones PQR Test Coupon is ready material will dispatch for Lab Testing (DT & NDT Test) on 27/01/2018.

3) Lab Testing will be start on 29/01/2018 and maximum finish on 03/02/2018.

4) All Lab testing will be Complete & if all test are success fully pass documentation prepare for WPS, WPQR & WQT
finish on 06/02/2018.

5) All Certification related documentation will be ready from my end on 08/02/2018.

6) Consultant for IWE Engineer will be visit Start on 09/02/2018 and Finish on 15/02/2018 for training & review of
documents & development.

7) Gap analysis for preparation of certification by TUV on 16/02/2018.

8) Finial Date conform to TUV for Audit.