Jemal Musa
Project
: Building Electrical Installation Design & Drafting Flat Design 1
Supervisor :
Building Electrical Installation Design Project
Building Specification:
Number of floors : 6 Floors + Ground floor
Number of flats :
36 flats ( 6 flats per floor (3 large “3BHK”, and 3 small “2BHK”) )
All 2BHK flats are typical (same)
All 3BHK flats are typical (same)
Number of lifts : 2 Lifts
Generator to supply power for lift 1 (10 HP), lift 2 (10 HP), Water pump (50 HP), Fire-fighting water
pump (50HP), DB GF.
A chiller is a machine that removes heat from a liquid via a vapor-compression or absorption refrigeration cycle.
This liquid can then be circulated through a heat exchanger to cool equipment, or another process stream (such as
air or process water).
An air handler, or air handling unit (often abbreviated to AHU), is a device used to regulate and circulate air as
part of a heating, ventilating, and air-conditioning (HVAC) system.
CHWPP- Chilled Water Primary Pump
CHWSP- Chilled water secondary pump
ft2 Building Electrical Installation Design Project
Note :
W/H , W/M = 1500 w
FCU 1 Tonne = 1200 w
Calculation:
Total connected load = (6900+7200+6600) = 20700 W
T.C.L = 20.7 kW
= 33.61 A
Main feeder cable = 1 x 4C x 10mm², XLPE/SWA/PVC, Cu+ 1 x 1C x 10mm², PVC/PVC, Y/G Earth Cable
3 BHK Design
Note :
W/H , W/M = 1500 w
FCU 1 Tonne = 1200 w
Calculation:
Total connected load = (9000 + 9100 + 8900) = 27000 W
T.C.L = 27 kW
= 43.84 A
DB – GF Design
= 9.58 A
= 232.37 A
Plus 25 % as safety factor
Main feeder cable = 1 x 4C x 185 mm², XLPE/SWA/PVC, Cu+ 1 x 1C x 95 mm², PVC/PVC, Y/G Earth cable
NOTE
? SMDB-2F to SMDB-6F are Typical to SMDB-1F
P. 100kw 3phase
Current (I) = 100,000/(1.732×400×.8)= 180.42 A
Plus, 25% as safety factor 180.42× 1.25 = 225.525 A
Standard disconnect switch size = 250 A, 4P
Main feeder cable = 1 x4C×150mm²+ 1x1C×95mm² Y/G
2. Chiller (2)
P. 100kw 3phase
Current (I) = 100,000/ (1.732×400×.8)= 180.42 A
Plus, 25% as safety factor 180.42× 1.25 = 225.525 A
Standard disconnect switch size = 250 A, 4P
Main feeder cable AHU -1 (50HP)
3.
Current (I) = 37300/ (1.732×400×.8) =67.3 A
Plus, 25% as safety factor 67.3 × 1.25 = 84.125 A
Standard disconnect switch size = 100 A, 4P
Main feeder cable = 1 x4C×35mm²+ 1x1C×25mm² Y/G
4. AHU -2 (50HP)
P. 50×746 = 37.3kW
Current (I) = 37300/ (1.732×400×.8) =67.3 A
Plus, 25% as safety factor 67.3 × 1.25 = 84.125 A
P. 20×746 =14.92 kW
Current (I) = 14920/ (1.732×400×.8) =26.92 A
Plus, 25% as safety factor 26.92× 1.25 = 33.65 A
Standard disconnect switch size = 40 A, 4P
Main feeder cable = 1 x4C×10mm²+ 1x1C×10mm² Y/G
P. 20×746 =14.92 kW
Current (I) = 14920/ (1.732×400×.8) =26.92 A
Plus, 25% as safety factor 26.92× 1.25 = 33.65 A
Standard disconnect switch size = 40 A, 4P
Main feeder cable = 1 x4C×10mm²+ 1x1C×10mm² Y/G
P. 20×746 =14.92 kW
Current (I) = 14920/ (1.732×400×.8) =26.92 A
Plus, 25% as safety factor 26.92× 1.25 = 33.65 A
Standard disconnect switch size = 40 A, 4P
Main feeder cable = 1 x4C×10mm²+ 1x1C×10mm² Y/G
P. 15×746= 11.19 kW
Current (I) = 11190/ (1.732×400×.8)= 20.19 A
Plus, 25% as safety factor 20.19× 1.25 = 25.24 A
Standard Main Isolator size = 30 A, 4P
Main feeder cable = 1 x4C×6mm²+ 1x1C×6mm² Y/G
P. 15×746= 11.19 kW
Current (I) = 11190/(1.732×400×.8)= 20.19 A
Plus, 25% as safety factor 20.19× 1.25 = 25.24 A
Standard Main Isolator size = 30 A, 4P
Main feeder cable = 1 x4C×6mm²+ 1x1C×6mm² Y/G
P. 15×746= 11.19 kW
Current (I) = 11190/ (1.732×400×.8)= 20.19 A
Plus, 25% as safety factor 20.19× 1.25 = 25.24 A
Standard Main Isolator size = 30 A, 4P
Main feeder cable = 1 x4C×6mm²+ 1x1C×6mm² Y/G
= 326.76 x 1 =326.76 kW
= 589.56 A
Plus, 25% as safety factor
Main feeder cable for MCC = 2 x4C×300mm². XLPE/SWA/PVC, Cu+ 2x1C×150mm² Y/G
Designed by: Mohnad Ibrahim Abdalla Jobbara
Building Electrical Installation Design Project
P. 10×746= 7.46 kW
Current (I) = 7460/(1.732×400×.8) = 13.46A
Plus, + 25% as safety factor 13.46× 1.25 = 16.825 A
Standard disconnect switch size = 20 A, 4P
Main feeder cable = 1 x4C×4mm²+ 1x1C×4mm² Y/G
P. 10×746= 7.46 kW
Current (I) = 7460/(1.732×400×.8) = 13.46A Plus, +
25% as safety factor 13.46× 1.25 = 16.825 A
Standard disconnect switch size = 20 A, 4P
Main feeder cable = 1 x4C×4mm²+ 1x1C×4mm² Y/G
P. 50×746= 37.2 kW
Current (I) = 37200 / (1.732×400×.8) = 67.12 A
Plus, + 25% as safety factor 67.12× 1.25 = 83.9 A
Standard disconnect switch size = 100 A, 4P
Main feeder cable = 1 x4C×35mm²+ 1x1C×25mm² Y/G
P. 50×746= 37.2 kW
Current (I) = 37200 / (1.732×400×.8) = 67.12 A
Plus, + 25% as safety factor 67.12× 1.25 = 83.9 A
Standard disconnect switch size = 100 A, 4P
Main feeder cable = 1 x4C×35mm²+ 1x1C×25mm² Y/G
Main feeder cable for SMDB - Comm = 1 x4C×95mm². XLPE/SWA/PVC, Cu+ 1x1C×50mm² Y/G
Transformer Sizing
1. Max demand of MDB = 1152.608 kW
2. Total max demand of MDB in kVA = Power
(kW) / CosФ
= 1152.608 kW/ 0.8
= 1440.76 kVA
3. Add 10 % as future load
Max demand in kVA = 1440.76 x 1.10 = 1584.836 kVA
4. Transformer Size = (Total max demand with future load in kVA / Transformer load (90%))
Standard Transformer size = 2000kVA,
Voltage : 11kV/ (400-230V), Step-down, 3phase.
Frequency : 50 Hz,
Winding : Delta/Star,
Cooling : Air Cooled
Capacitor Bank Sizing
Generator Sizing
Cable Schedule
From To Size Length
MDB MCC 2x4C×300mm² 35 meters
MDB SMDB-Comm 1x4C×95mm² 10 meters
MDB SMDB-1F 1x4C x185mm² 15 meters
MDB SMDB-2F 1x4C x185mm² 20 meters
MDB SMDB-3F 1x4C x185mm² 30 meters
MDB SMDB-4F 1x4C x185mm² 40 meters
MDB SMDB-5F 1x4C x185mm² 50 meters
MDB SMDB-6F 1x4C x185mm² 60 meters
1 . % Vd (MDB to SMDB-6F)
Vd = I ×L (Meter) × VD / (R× 1000)
Cable size = 1x4C x185mm²
I = current of max demand of SMDB-6F = 232.37 A
L = 60 Meters, R = 1
VD = 0.26 (See page 34, cable data table)
Vd = (232.37 × 60× 0.26)/(1000×1) = 3.63 V
%Vd = (3.63/400) ×100 = % 0. 9075
1. %Vd(MDB-MCC) :
2. % Vd(MCC-Chiller1):
= 0.886 % (< 4 % “less than 4%) So, the sizes of all cables are in
Drawings: