Sie sind auf Seite 1von 4

Investigation Techniques and Remedial Works to Control Seepage

through an Earthfill Dam


Dan Stematiu, Radu Sarghiuta, Catalin Popescu
Technical University of Civil Engineering Bucharest, Romania, stematiu@utcb.ro

Daniel Gaftoi
ISPH Consulting Company, Romania

ABSTRACT:
Ostrovul Mic hydropower development creates a reservoir controlled by a gated dam and bordered by 2 km of earthfill lateral dams.
The lateral dams, with a maximum height of 20 m, are made of river ballast. The watertightening is provided on the upstream face by a
reinforced concrete slab and within the foundation by a cut-off wall at the upstream toe. During the first impoundment intensive
seepage were noted up to 1400 l/s. Large wetted area on the downstream face and local piping endangered the dam stability. Subsequent
the event the reservoir was lowered but in spite the operation at minimum levels the seepage phenomenon has developed and
remediation works are required. Three alternatives were proposed: an impervious wall drive from the dam crest in the central part of the
dam; a new cut-off wall in front of the existing one; a geomembrane covering the existing cut-off wall crest and the lower part of the
concrete slab. The final selection was based on simulation on a mathematical model. The model that was used for alternative selection
was calibrated based on in situ investigation by using infrared images of a thermacam. The paper presents the history of the events,
solution techniques and decision process.

Keywords: dam, seepage, remedial works, investigations, thermacam.

1. INTRODUCTION encountered at the Ostrovul Mic hydropower plant dikes.


The first part of the paper summarizes a series of seepage
Uncontrolled seepage can progressively erode soil from events that marked the functioning of the power plant
the embankment or its foundation in an upstream over the time. The second part presents the infrared
direction towards the reservoir and develop a flow thermal field investigation used to calibrate the
conduit (pipe) to the reservoir. If the seepage forces are mathematical model and the results of a comparative
large enough, soil will be eroded from the foundation and analysis in terms of seepage flow of the effectiveness of
be deposited in the shape of a cone around the outlet. If the sealing systems alternatives.
these "boils" appear, professional advice should be
sought immediately. Seepage flow which is muddy and
carrying soil particles may be evidence of "piping" and 2. OSTROVUL MIC DEVELOPMENT
complete failure of the dam could occur. If a seepage
problem has already been identified investigation is Ostrovul Mic development consists in a gated dam and a
required in order to determine the probable cause of the hydropower station closing the river bed area and dikes
seepage and the remedial action needed. The normal (lateral dams) that create the reservoir contour (Fig. 1).
approach is to define an adequate numerical model and to The power station has an installed discharge of 90 m3/s
examine the actual causes by defining several scenarios. and a head of 20 m the power being 15.9 MW.
The correctness of the investigation is dependent on the
accuracy of the model that in its turn depend on the The dikes are made of ballast (sand and gravel). The
model calibration (Guardo and Rohrer, 2000, CRWMS, watertightening system provides concrete slabs (4.0 x 5.0 m)
2001, Tayfur, 2005). The current field data available are on the upstream face and a cut-off wall 5 to 6 m deep in
the piezometric measurements. However, for long dikes the foundation (Fig. 2). The cut-off wall was performed
the extensive seepage may occur in zones not covered by in an open cut excavation of trapezoidal shape 4 m in the
readings. One of the most convenient methods in terms upper part and 1 m at the basis. To allow the closure of
of costs and duration that can furnish the needed the cut-off wall into the marne bedrock the upper layer of
information is seepage detection using infrared thermal the river alluvium (3 to 5 m) was removed in front of the
imaging (Stematiu, 2008; Shutko, 2009; Monique de dike upstream toe.
Moel, 2010).
The investigations conducted during the low level
The present paper deals with the seepage problems reservoir operation have revealed several faults in the
actual condition of foundation watertightening: the lower level in the reservoir (5 to 6 m) the wet area on the
cut-off wall is not fully closed into bedrock; there are downstream slope has extended, the number of springs
gaps between the concrete face support beam and the has raised and the level of emergence on the slope has also
cut-off wall; several windows were created in the cut-off raised.
wall by oversized blocks in the foundation ground.
The main cause of the very large seepage was considered
the deficiencies of the foundation watertightening.
Consequently, two alternatives of remedial works were
proposed:
- alternative I – performance of an impervious jet
grouting wall from the dike crest down to
bedrock, having at least 1 m rock penetration;
- alternative II – performance of an additional
cut-off wall in front of the existing one, this time
perfectly closed into the bedrock; a new
connection between the cut-off walls and the
concrete face was also provided.

The simulations on the seepage numerical model that will


be presented in next section have pointed out that the most
significant contribution to seepage discharge and to the
high level of seepage line is localized on the lower part of
the concrete face, where the reinforced concrete slabs
provide sealing of the pervious layer of the foundation and
not to the dike body. Based on this finding a third
alternative was proposed:
- alternative III – placement of a PVC
geomembrane on the last 2/3 of the concrete face
and on the connection between the concrete face
and the cut-off wall

Figure 1. Plan and panoramic view of Ostrovul Mic HPP The validation of hypotheses concerning the seepage
1. Gated dam; 2. Stilling basin I; 3. Stilling basin II; 4. River bed; cause and the analysis of the efficiency of the proposed
5. Power station; 6. Outlet channel; 7. Tailrace; 8. Concrete face; alternatives were performed by using a finite element
9. Vegetated slope. model. The model includes the dike and its foundation up
to the impervious bedrock and all the features as cut-off
wall, concrete face, windows etc. The reservoir water
level was constant and equal to normal operation level -
the steady state case.

4. CALIBRATION OF THE MATHEMATICAL


MODEL

Finite element model calibration is usually based on the


Figure 2. Dike cross section seepage line position within the dike body. Since the
existing piezometric profiles were far from the seepage
affected zone it was decided to have as calibration data
3. SEEPAGE PHENOMENA AND PROPOSED the level of seepage emergence on the downstream face.
REMEDIAL WORKS A simple visual evaluation was considered very
inaccurate due to slope vegetation and the superficial soil
Large leakage through the dikes and especially through layer. Consequently, the infrared image technique was
the left bank one was noticed since the reservoir employed.
commissioning in 1986. This was the cause for restricted
water level operating mode as a prime measure. Over the Infrared light or thermography is the use of an infrared
time, various remedial works have been performed, but imaging and measurement camera to "see" and
they failed to effectively control the seepage flow. The "measure" thermal energy emitted from an object. FLIR
total seepage was up to 900 l/s. The largest defective seal camera (FLIR Systems, 2006) was used to obtain
behaviour was found between km 1 + 230 and 1 + 370 at infrared images of the downstream face of the dike. From
the left bank dike. In the last years, in spite of a significant the same location digital photos were taken (Fig. 3). The
images were taken in summer. The body of dike was significant contribution to seepage and to the high level
warmer than the water in the outer slope of dike; of seepage line is done by the deteriorated slabs on the
therefore it is shown with red tone in the picture in lower part of the concrete face and especially by the
compression with the yellow one above the saturated damaged joint between the concrete face and the cut-off
zone. By a simple calculation the elevation of the border wall. The excavations in front of the upstream toe,
between the saturated and unsaturated zones was required to implement the cut-off wall in an open trench,
determined as 455.90 mASL for a reservoir water level have exposed the most pervious layer above the bedrock
of 462.50 mASL. to direct infiltration.

a 5. ANALYSIS OF THE REHABILITATION


ALTERNATIVES
Seepage exit on the downstream face
The proposed dike rehabilitation alternatives were
evaluated based on the results of the numerical
simulations. The reference point was the actual state that
does not allow the reservoir operation at its normal level.
455.90
Without rehabilitation the full reservoir may cause
leakage up to 1 l/s per each meter of dike and a a
saturated area on the downstream face up to 10 m above
the foundation ground (see Table 2). The efficiency of
b the rehabilitation alternatives were judged by their effect
Reservoir level 462.50 Emergence level on the seepage flow and on the condition of the
downstream face. Fig. 4 presents the seepage spectrum
for each of the main three alternatives.
Alternative I. Impervious wall
NOL 465.00

Figure 3. Model calibration: a) infrared and digital images;


b) flow net after calibration.

Starting from the permeability values determined in


laboratory and having as calibration target the emergence
of the seepage line on the downstream face, the actual
permeability coefficients were defined by an iterative
process. The calibration was performed for two Alternative II. Additional cut-off wall
distinctive cases, one considering the cut-off wall closed NOL 465.00
into the bedrock, the other one considering a 0.5 m gap Emergence level
between the cut-off wall deep end and and the bedrock.
The values are listed in Table 1.

Table 1 Permeability
kx (m/s) ky (m/s)
horizontal vertical
Dike body 2 x 10-3 2 x 10-2 Alternative III. PVC geomembrane
Alluvium foundation 4 x 10-3 4 x 10-3
NOL 465.00
Bedrock 1 x 10-6 1 x 10-6
Deteriorated concrete face 2 x 10-4 2 x 10-4
Cut-off wall 1 x 10-6 1 x 10-6
Rehabilitated concrete face 1 x 10-5 1 x 10-5
New cut-off wall 1 x 10-6 1 x 10-6
Geomembrane 1 x 10-7 1 x 10-7

The emergence level on the downstream face shown by


the flow net in Fig. 3 corresponds to the measured one. Figure 4. Seepage analysis results for the main rehabilitation
Similar values were obtained in both cases – closed or alternatives
floating cut-off – thus revealing that the main cause of
the recorded seepage phenomena is not the deficiency of A synthesis of the results is presented in Table 2. The
the performed foundation sealing. As it was mentioned alternative II was divided into two sub alternatives
before, the simulations pointed out that the most assuming firstly that the new cut-off wall will be closed
into the bedrock and secondly that the new cut-off wall and especially the damaged joint between the concrete
execution will encounter the same difficulties as the face and the cut-off wall since the excavations in front of
existing one and some windows will be present. An the upstream toe, required to implement the cut-off wall
additional comparative term was added. The maximum in an open trench, have exposed the most pervious layer
seepage exit gradient was compared to the critical above the bedrock to direct infiltration.
gradient for the dike fill material.
Three rehabilitation alternatives were proposed: jet
The comparison shows that the jet grouting diaphragm is grouting diaphragm, additional cut-off wall and PVC
the most efficient alternative. The additional cut-off wall geomembrane on upstream face. In order to support the
will not solve the problem since a significant area of the final decision seepage analyses were performed having
downstream face remains saturated. If some deficiencies as comparison criteria the seepage flow, the condition of
of cut-off closure will appear the maximum gradient will the downstream face and the maximum seepage gradient.
overpass the critical one and piping may start. The
geomembrane alternative is also a convenient alternative The seepage analyses were done on a calibrated finite
in spite of the existence of some seepage flow. The final element model having as calibration target the emergence
decision has to consider the investment cost as well as of the seepage line on the downstream face. The actual
the maintenance costs for the technically accepted elevation of seepage emergence was determined by using
alternatives. the infrared image technique.

Table 2. Synthesis of the numerical simulations


Seepage Height of REFERENCES
l/s on emergen
Alternative i < icritic Allen, R. (2011) Safety Evaluations of Hidden Dam – Seepage
1 m of ce on the
Models Meet Reality. 2011 AEG Annual Meeting.
dike DS slope
CRWMS M&O (2001). Seepage Calibration Model and
0. Actual state 0.992 9.58 m No Seepage Testing Data. 153045MDL-NBS-HS-000004 REV
I. Impervious jet 01. Las Vegas, Nevada.
grouting wall from FLIR SYSTEMS.(2006). ThermaCAM TM B4. User manual.
0.037 0 Yes
the dike crest down to Guardo, M., Rohrer, K,P. (2000) Calibration of a steady-state
bedrock seepage model from transient recovery of field data†
IIa. Additional JAWRA Journal of the American Water Resources
cut-off wall in front Association. Volume 36, Issue 1, pages 87–94.
0.652 3.68 m Yes Moel, M. (2010). Seepage Detection within Embankment Dams
of the existing one
Using Infrared Thermal Imaging. Proceedings of the 2010
closed into bedrock ANCOLD Conference.
IIb. Additional Shutko I and col. (2009). New Technologies in Monitoring and
cut-off wall in front Emergency Mapping of Water Seepage and Dangerously
of the existing one 0.702 4.38 m No High Groundwaters. Research report.
not closed into Stematiu, D. (2008). Use of infrared images to revealed
bedrock infiltrations from tailings dams (in Romanian). Hidrotehnica,
III. PVC Vol. 53, Nr. 12.
Tayfur, G., Swiatek, D., Wita, A., and Singh V., P. (2005) Case
geomembrane on the
0.205 0 Yes Study: Finite Element Method and Artificial Neural Network
last 2/3 of the Models for Flow through Jeziorsko Earthfill Dam in Poland.
concrete face J. Hydraul. Eng. 131, 431.

6. CONCLUDING REMARKS

The dikes of the Ostrovul Mic HPP faced seepage


problems since their commissioning in 1986 and have
imposed a restricted water level operating mode. Over
the time, various remedial works failed to effectively
control the seepage flow and currently the largest
defective seal is found between km 1 + 230 and 1 + 370
at the left dike bank. In the last years the wet area has
extended, the number of springs has raised and the level
of emergence has also raised.

The main cause of the very large seepage was considered


the deficiencies of the foundation watertightening but the
present analysis has revealed that the main cause is the
deteriorated slabs on the lower part of the concrete face

Das könnte Ihnen auch gefallen