Sie sind auf Seite 1von 2

Company

Rep. No.
CORROSION COUPON INSTALLATION Proj, Int. ID.
INSPECTION CHECK LIST Form – IQ Form E037

Contractor Contract No.: Project


Location:

TAG N°: SYSTEM:


P&ID N°: SERVICE:
LINE N°: PIPE SIZE/THICKNESS:
END CONNECTION: FLARE WELD MAX.PRESSURE(PSI): MAX.TEMP:
MATERIAL
FLARE WELD ACCESS FITTING BODY ASTM A-182 F316L
SOLID PLUG ASSEMBLY: 316L DISC COUPEN HOLDER: 316L
DISC COUPON: 316SS

CHECK PERFORMED P N N/A


A. MATERIAL INSPECTION & STORAGE

1. MATERIALS ARE RECEIVED IN GOOD CONDITION, NO DAMAGE.


2. MATERIAL CONFORMS TO SPECIFICATION AND DRAWINGS.

3. CONFIRM MATERIAL TEST CERTIFICATES (MTC) ARE AS PER PROJECT SPECIFICATION.

4. MATERIAL PRESERVATION STATUS AS PER VENDOR RECOMMENDATION.


5. CORROSION COUPON INSPECTED FOR IDENTIFICATION, EXTERNAL DAMAGE CHECKED

B. WELDING OF ACCESS FITTING FLAREWELD

6. CHECK THE PIPE HOLE IS CORRECT SIZE WITH FITTING AND CLEAN FOR WELD

7. CHECK THE DISC COUPON & HOLDER REMOVED FROM THE FITTING DURING WELDING
larger sized holes.
8. CONFORM THE FITTING IS IN12” O” CLOCK POSITION PRIOR TO WELD
stress relieving operations.
9. ENSURE THAT THERE WILL BE ADEQUATE CLEARANCE ABOVE THE FITTING
TO OPERATE THE RETRIEVER.

10. CHECK THE WELDING RODS APPROPRIATE TO THE FITTING AND LINE MATERIAL.

11. CHECK FITTING MUST BE RAISED OFF THE SURFACE OF THE PIPE WALL TO
ESTABLISH A PROPER WELD GAP.
12. CHECK PENETRANT TEST TO BE COMPLETE AFTER COMPLETION OF WELD

B. RESTORATION OF DISC COUPON HOLDER & DISC COUPON

13. HYDROTEST CARRIEDOUT WITHOUT INSTALL DISC COUPON HOLDER & DISC
COUPON.
14. CONFIRM THE DISC, DISC COUPON ACCESSORIES ARE FIXED AS PER
VENDOR ASSEMBLY DRAWING
15. CHECK FOR PROPECTIVE COVER INSTALLED.
Note: P=POSITIVE N=NEGATIVE N/A = NOT APPLICABLE
FOREMAN - CONTRACTOR QC - CONTRACTOR QC - ENI QC - ZFOD

NAME NAME NAME NAME

SIGNATURE SIGNATURE SIGNATURE SIGNATURE

Date Date Date Date

Das könnte Ihnen auch gefallen