PREPARATION MAN POWER, TOOLS &EQUIPMENT FOR PROJECT EXECUTION
OF MODIFICATION SPOOL PIPE OF ASVLINE & REPLACE CHIMNEY HAT AT CPP
KEPODANG PETRONAS Man Power No Description QTY Remark REPLACE CHIMNEY HAT 1 Supervisor 2 Pax Day Shift & Night Shift 2 Authorized Entrand / 3 Pax Day shift & Night shift Technician 3 Watcher / Stand by Man 2Pax Day shift & Night shift 4 Flange Management Team 3 Pax Day Shift & Night shift TOTAL CHIMNEY HAT 10 PAX
MODIFICATION ASV LINE
5 Construction Supervisor 1Pax Day Shift & Night Shift 6 Field Engineer 1 Pax Day Shift 7 Welder 4Pax Day Shift & Night Shift 8 Fitter 2pax Day Shift & Night Shift 9 Rigger Scaffolder 6pax Day Shift & Night Shift 10 QC Inspector 1 Pax Day Shift & Night Shift 11 Flange Management Team 2 Pax Day Shift & Night Shift 12 NDT Team Petronas to confirm Day Shift & Night Shift 13 Mechanic Compressor & 1 Pax Day Shift Welding Machine 14 Stand By Fire Water 1 pax Day Shift & Night Shift 15 Elctrical Instrument 2 pax Day Shift & Night Shift TOTAL ASV LINE 21 PAX
Summary: Estimated man power needed: Chimney Hat Replacement : 10 pax Asv line Modification : 21 pax