PREPARATION MAN POWER, TOOLS &EQUIPMENT FOR PROJECT EXECUTION

OF MODIFICATION SPOOL PIPE OF ASVLINE & REPLACE CHIMNEY HAT AT CPP


KEPODANG PETRONAS
Man Power
No Description QTY Remark
REPLACE CHIMNEY HAT
1 Supervisor 2 Pax Day Shift & Night Shift
2 Authorized Entrand / 3 Pax Day shift & Night shift
Technician
3 Watcher / Stand by Man 2Pax Day shift & Night shift
4 Flange Management Team 3 Pax Day Shift & Night shift
TOTAL CHIMNEY HAT 10 PAX

MODIFICATION ASV LINE


5 Construction Supervisor 1Pax Day Shift & Night Shift
6 Field Engineer 1 Pax Day Shift
7 Welder 4Pax Day Shift & Night Shift
8 Fitter 2pax Day Shift & Night Shift
9 Rigger Scaffolder 6pax Day Shift & Night Shift
10 QC Inspector 1 Pax Day Shift & Night Shift
11 Flange Management Team 2 Pax Day Shift & Night Shift
12 NDT Team Petronas to confirm Day Shift & Night Shift
13 Mechanic Compressor & 1 Pax Day Shift
Welding Machine
14 Stand By Fire Water 1 pax Day Shift & Night Shift
15 Elctrical Instrument 2 pax Day Shift & Night Shift
TOTAL ASV LINE 21 PAX

Summary:
Estimated man power needed:
 Chimney Hat Replacement : 10 pax
 Asv line Modification : 21 pax