Sie sind auf Seite 1von 26

ANG V FULTON FIRE INSURANCE CO.

the insurer, or if the claim is made and rejected


Labrador, J. | July 31, 1961 but no action is commenced within 12 months
after such rejection, all benefits under the policy
Art 1155, Prescription, Resolutory Clause
would be forfeited, and that since the claim of the
Art 1155
plaintiffs was denied and plaintiffs received notice
The prescription of actions is interrupted when
of denial on April 18, 1956, and they brought the
they are filed before the court, when there is a action only on May 5, 1958, all the benefits under
written extrajudicial demand by the creditors, the policy have been forfeited.
when there is any written acknowledgement of the
debt by the debtor. On February 12, 1959, plaintiffs filed a reply to the
above answer of the Fulton Fire Insurance, alleging
Facts: that on May 11, 1956, plaintiffs had instituted Civil
The present action was instituted by the spouses Case No. 2949 in the Court of First Instance of
Paulo Ang and Sally C. Ang against the Fulton Fire Manila, to assert the claim; that this case was
Insurance Company and the Paramount Surety and dismissed without prejudice on September 3, 1957,
Insurance Company, Inc. to recover from them the and that deducting the period within which said
face value of a fire insurance policy issued in action was pending, the present action was still
plaintiffs' favor covering a store owned and within the 12 months period from April 12, 1956.
operated by them in Laoag, Ilocos Norte. From a
judgment of the court ordering the defendant The court below held that the bringing of the
Fulton Fire Insurance Co. to pay the plaintiffs the action in the Court of First Instance of Manila on
sum of P10,000.00, with interest, and an additional May 11, 1956 tolled the running of the 12 months
sum of P2,000.00 as attorney's fees, and costs, the period within which the action must be filed. The
defendants have appealed directly to this Court. court rendered decision in favor of the plaintiffs.

On September 9, 1953, defendant Fulton Fire On the appeal before this Court, defendant-
Insurance Company issued a policy in favor of P. & appellant argues that the court below erred in
S. Department Store (Sally C. Ang) over stocks of holding that the filing of the previous suit tolled or
general merchandise, consisting principally of dry suspended the running of the prescriptive period.
goods, contained in a building occupied by the
plaintiffs at Laoag, Ilocos Norte. Counsel for appellees contends that the action of
the plaintiffs against the defendant had not yet
On December 27, 1954, the store containing the prescribed at the time of the bringing of the
goods insured was destroyed by fire. On December action, because the period of prescription was
30, following, plaintiffs executed the first claim interrupted by the filing of the first action
form. against the Paramount Surety & Insurance Co., in
accordance with Article 1155 of the Civil Code.
On April 6, 1956, the Fulton Fire Insurance
Company wrote the plaintiffs that their claim was Issue:
denied. This denial of the claim was received by W/N action of Ang Spouses had already prescribed
the plaintiffs on April 19, 1956. pursuant to the prescription stipulated in their
contract with Fulton Fire Insurance Co.
The present action was instituted on May 5, 1958.
The action was originally instituted against both Held:
the Fulton Fire Insurance Company and the
YES.
Paramount Surety and Insurance Company, Inc.,
but on June 16, 1958, upon motion of the
NOT MERELY A PROCEDURAL ERROR
Paramount Surety, the latter was dropped from the
The basic error committed by the trial court is its
complaint.
view that the filing of the action against the agent
of the defendant company was "merely a
On May 26, 1958, the defendant Fulton Fire
procedural mistake of no significance or
Insurance Company filed an answer to the
consequence, which may be overlooked."
complaint, admitting the existence of the contract
of insurance, its renewal and the loss by fire of the
The condition contained in the insurance policy
department store and the merchandise contained
that claims must be presented within one year
therein, but denying that the loss by the fire was
after rejection is not merely a procedural
accidental, alleging that it was occasioned by the
requirement.
willful act of the plaintiff Paulo Ang himself. It
claims that under paragraph 13 of the policy, if the
loss or damage is occasioned by the willful act of
The condition is an important matter, essential to obtained by respondent from petitioner bank,
a prompt settlement of claims against insurance evidenced by: (1) promissory note; (2) loan
companies, as it demands that insurance suits be release sheet; (3) loan disclosure statement.
brought by the insured while the evidence as to  Petitioner bank, represented by its Deputy
the origin and cause of destruction have not yet Liquidator, sent a letter of demand on July 27,
disappeared. 1988, demanding full payment of the loan.
Another letter of demand was sent on February
It is in the nature of a condition precedent to the 22, 1994.
liability of the insurer, or in other terms, a  Respondent, through counsel, alleges that while
resolutory clause, the purpose of which is to the signature appearing at the back of the
terminate all liabilities in case the action is not promissory note “seems to be that of
filed by the insured within the period stipulated. defendant,” the receipt of the P1-M amount
shows that the amount was received by another
NO CONDITION IN POLICY RE: BRINGING SUIT person, not the defendant. This Answer was
AGAINST AGENT AND NOT THE PRINCIPAL contained in a Denial under Oath.
The bringing of the action against the Paramount  Both the trial court and Court of Appeals
Surety & Insurance Company, the agent of the dismissed petitioner’s complaint. The CA found
defendant company, cannot have any legal effect that petitioner failed to present any evidence to
except that of notifying the agent of the claim. prove the existence of respondent’s alleged
loan obligations, considering that respondent
There is no law giving any effect to such action denied petitioner’s allegations. It also found
upon the principal. Besides, there is no condition that petitioner bank’s cause of actions is
in the policy that the action must be filed against already barred by prescription.
the agent, and this Court cannot by interpretation
extend the clear scope of the agreement beyond ISSUE
what is agreed upon by the parties.  W/N respondent really denied the existence of
the loan
E. MACIAS & CO. VS. CHINA FIRE INSURANCE &  W/N petitioner’s cause of action is barred by
CO. prescription
The contractual limitation in an insurance policy
prevails over the statutory limitation, as well as HELD
over the exceptions to the statutory limitations;  Petition is GRANTED. Respondent is ordered to
that the contract necessarily supersedes the pay P1,000,000.00 plus 25% interest and 24%
statute (of limitations) and the limitation is in all penalty charge per annum beginning October
phases governed by the former. 13, 1983 until fully paid, and 25% of the amount
due as attorney’s fees.
RIDDLESBARGER VS. HARTFORD FIRE INSURANCE  A reading of Respondent’s Answer shows that
CO. respondent did not specifically deny that he
The rights of the parties flow from the contract of signed the loan documents. What he merely
insurance, hence they are not bound by the statute stated was that the signature seems to be his,
of limitations nor by exemptions thereto. and he that he also denied any liability on the
promissory note as he allegedly did not receive
the amount stated therein, and the loan
PERMANENT SAVINGS AND LOAN BANK V. documents do not express the true intention of
VELARDE the parties. Respondent’s denials do not
GR NO. 140608 | September 23, 2004 | AUSTRIA- constitute an effective specific denial as
MARTINEZ contemplated by law. This means that the
Prescription defendant must declare under oath that he did
Bank Loan; Letter of Demand; Prescription not sign the document or that it is otherwise
false or fabricated.
The SC ruled that the prescriptive period is  In fact, respondent’s allegations amount to an
interrupted upon receipt of written extrajudicial implied admission of the due execution and
demand, which commences anew the prescriptive genuineness of the promissory note.
period. Respondent is deemed to have admitted the
loan documents and acknowledged his
FACTS obligation with petitioner.
 Petitioner Permanent Savings and Loan Bank  Although respondent claims that he did not
sought to recover from respondent Mariano receive the amount as stated in the Loan
Velarde the sum of P1,000,000.00 plus accrued Release Sheet, the document bears his
interests and penalties, based on a loan signature. Res ipsa loquitur. The document
speaks for itself. A person cannot accept and
reject the same instrument.
 The Court also finds that petitioner’s claim is
not barred by prescription.
 Petitioner’s action for collection of a sum of
money was based on a written contract and
prescribes after 10 years from the time its right
of action arose (Art. 1144, Civil Code). The
prescriptive period is interrupted when there is
a written extrajudicial demand by creditors. The
interruption of the prescriptive period means
that the said period would commence anew
from the receipt of the demand.
 The Court categorically stated in Overseas
Bank of Manila v. Geraldez that the correct
meaning of interruption as distinguished from
mere suspension or tolling of the prescriptive
period is that said period would commence PABLO ANTONIO V ENGR. EMILIO MORALES
anew from the receipt of the demand. Justice Sandoval-Gutierrez; January 23, 2007
 Respondent’s obligation under the promissory -------------------------------------------------------------------------------
note became due and demandable on Oct. 13, Prescription, Snail Pace of Case, Withdraw from
1983. On July 27, 1988, petitioner’s counsel RTC
made a written demand for petitioner to settle
his obligation. From the time respondent’s Facts
obligation became due and demandable on Oct. 1. On December 18, 1995 E.M Morales and
13, 1983, up to the time the demand was made, Associates filed with the RTC of Makati a
only 4 years, 9 months, and 14 days had complaint for a sum of money against Pablo
elapsed. The prescriptive period then Antonio and Design Consultancy Inc.
commenced anew when respondent received 2. Petitioner Antonio filed a motion to dismiss the
the demand letter on August 5, 1988. Thus, complaint on two grounds— the failure to
when petitioner sent another demand letter on attach to the complaint a certificate of non-
February 22, 1994, the action still had not yet forum shopping, and the lack of legal capacity
prescribed as only 5 years, 6 months, and 17 to sue being a sole proprietorship.
days had elapsed. It was thus filed well before 3. On September 30, 1996 Engr. Emilio Morales
the lapse of the 10-year prescriptive period. filed an Amended Complaint attaching the
certificate of non-forum shopping. The RTC
issued an Order admitting the amended
complaint.
4. Morales, feeling that the case would remain
pending in an indefinite time, he filed a motion
to dismiss his complaint.
5. On August 1, 2001, the RTC dismissed Civil
Case No. 95-1796 without prejudice pursuant to
Section 2, Rule 17 of the 1997 Rules of Civil
Procedure, as amended.
6. On August 3, 2001, respondent filed with the
Court of Appeals a manifestation that the RTC
dismissed without prejudice Civil Case No. 95-
1796. However, it was only on August 27, 2002,
or after more than one year, that the Court of
Appeals issued a Resolution directing
petitioner to comment on respondent's
manifestation.
7. The Court of Appeals dismissed the petition.
8. Morales then filed a new complaint for the
collection of a sum of money, this time with the
RTC Quezon City.
9. Antonio now, filed a motion to dismiss the
complaint on the ground that the action has
prescribed considering that under Article 1145
of the Civil Code, action based on oral abandoning his claim but because of the
contracts prescribe in six years. From August intention to expedite the enforcement of his
14, 1995 when he received respondent’s last rights. He felt frustrated at the pace at which
letter of demand, to September 23, 2002 when his case was moving. (It remained in the CA for
respondent filed this case, more than 7 years 6 years). He acted swiftly after the dismissal of
had elapsed, and that the first case did not his case and immediately filed with the CA. But
interrupt the running period. the CA only acted on his manifestation only
10. RTC denied the motion to dismiss the after one year.
complaint by reason of prescription 15. This delay, beyond respondent's control, in turn
further caused delay in the filing of his new
Issue complaint with the Quezon City RTC. Clearly,
W/N the Court of Appeals erred in holding that the there was no inaction or lack of interest on his
trial court did not gravely abuse its discretion in part
denying petitioner’s motion to dismiss the 16. Statute of limitations was devised to operate
complaint by reason of prescription [NO] primarily against those who slept on their
rights and not against those desirous to act but
Decision could not do so for causes beyond their control
1. Court of Appeals did not err in holding that the
RTC of QC did not gravely abuse its discretion
when it denied petitioner’s motion to dismiss
respondent’s complaint and ruled that he is not
barred by prescription
11. Article 1139: Actions prescribe by the mere
lapse of time fixed by law; 1145: The following
actions must be commenced within 6 years—
upon an oral contract, upon a quasi-contract;
1155: Prescription of actions is interrupted
when they are filed before the court, when
there is written extra-judicial demand by the
creditors, when there is any written
acknowledgement of the debt by the debtor.
12. In US v Serapio, Court held that under the Civil
Code, the prescription of an action refers to the
time within which an action must be brought
after the right of action has accrued. The
prescriptive statutes serve to protect those
who are diligent and vigilant, not those who
sleep on their rights. The rationale behind the
prescription of actions is to prevent fraudulent
and stale claims from springing up at great
distances of time, thus surprising the parties or
their representatives when the facts have
become obscure from the lapse of time or the
defective memory or death or removal of the
witnesses
13. Prescription as understood and used in this
jurisdiction does not simply mean a mere lapse
of time. Rather, there must be a categorical
showing that due to plaintiff's negligence,
inaction, lack of interest, or intent to abandon a
lawful claim or cause of action, no action
whatsoever was taken, thus allowing the
statute of limitations to bar any subsequent
suit.
14. Petitioner's invocation of prescription is
misplaced. On December 18, 1995 Morales
initially filed with the RTC of Makati. While it
was later dismissed without prejudice to his
own motion, we note that the dismissal sought
was not for the purpose of voluntarily
ANTONIO P. TAMBUNTING, JR. v. SPOUSES EMILIO the highest bidder. Respondents failed to redeem
SUMABAT the property during the redemption period. Hence,
Justice Corona; September 16, 2005 title to the property was consolidated in favor of
Mortgage CHFI and a new certificate of title (TCT No.
310191) was issued in its name. In view of these
Facts: developments, respondents amended their
On May 3, 1973, respondents spouses Emilio complaint to an action for nullification of
Sumabat and Esperanza Baello mortgaged a parcel foreclosure, sheriffs sale and consolidation of title,
of land situated in Caloocan City to petitioner reconveyance and damages.
Antonio Tambunting, Jr. and his assignee,
Commercial House of Finance, Inc. (CHFI) to On February 11, 2000, the RTC issued the assailed
secure the payment of a P7,727.95 loan. decision. It ruled that the 1981 CFI decision in Civil
Case No. C-7496 had long attained finality. The
In August 1976, respondents were informed that mortgage was extinguished when respondents
their indebtedness had ballooned to P15,000 for paid their indebtedness by consigning the amount
their failure to pay the monthly amortizations. By in court. Moreover, the ten-year period within
May 1977, because respondents defaulted in their which petitioners should have foreclosed the
obligation, CHFI, as assignee of the mortgage, property was already barred by prescription. They
initiated foreclosure proceedings on the abused their right to foreclose the property and
mortgaged property but the same did not push exercised it in bad faith. As a consequence, the
through. It was restrained by the then Court of trial court nullified the foreclosure and
First Instance (CFI) of Caloocan City, Branch 33 extrajudicial sale of the property, as well as the
(now RTC Branch 123) in Civil Case No. C-6329, a consolidation of title in CHFIs name in 1995. It
complaint for injunction filed by respondents then ordered the register of deeds of Caloocan
against petitioners. However, the case was City to cancel TCT No. 310191 and to reconvey the
subsequently dismissed for failure of the parties to property to respondents. It also held petitioners
appear at the hearing on November 9, 1977. liable for moral damages, exemplary damages and
attorneys fees.
On March 16, 1979, respondents filed an action for
declaratory relief with the CFI, seeking a Issue:
declaration of the extent of their actual Whether or not the trial court erred when it
indebtedness. It was docketed as Civil Case No. C- affirmed the validity of the consignation
7496. Petitioners were declared in default for
failure to file an answer within the reglementary Held:
period. On January 8, 1981, the CFI rendered its Yes. The trial court erred when it ruled that the
decision. It fixed respondents liability 1981 CFI decision in Civil Case No. C-7496 was
at P15,743.83 and authorized them to consign the already final and executory. Where the law or
amount to the court for proper disposition. In contract has already been contravened prior to the
compliance with the decision, respondents filing of an action for declaratory relief, the court
consigned the required amount on January 9, 1981. can no longer assume jurisdiction over the action.
Here, an infraction of the mortgage terms had
In March 1995, respondents received a notice of already taken place before the filing of Civil Case
sheriffs sale indicating that the mortgage had No. C-7496. Thus, the CFI lacked jurisdiction when
been foreclosed by CHFI on February 8, 1995 and it took cognizance of the case in 1979. And in the
that an extrajudicial sale of the property would be absence of jurisdiction, its decision was void and
held on March 27, 1995. without legal effect.

On March 27, 1995, respondents instituted Civil Article 1142 of the Civil Code is clear. A mortgage
Case No. C-16822, a petition for preliminary action prescribes after ten years. An action to
injunction, damages and cancellation of enforce a right arising from a mortgage should be
annotation of encumbrance with prayer for the enforced within ten years from the time the right
issuance of a temporary restraining order, with the of action accrues. Otherwise, it will be barred by
RTC of Caloocan City, Branch 120. However, the prescription and the mortgage creditor will lose
public auction scheduled on that same day his rights under the mortgage.
proceeded and the property was sold to CHFI as
Here, petitioners right of action accrued in May All the checks were thereafter encashed and
1977 when respondents defaulted in their debited from private respondent's account, except
obligation to pay their loan amortizations. It was for the check representing the payment for August
from that time that the ten-year period to enforce 1991 which was unsigned and because of which
the right under the mortgage started to run. The the amount representing it was recalled and re-
credited to private respondent's account.
period was interrupted when respondents filed
Civil Case No. C-6329 sometime after May 1977
and the CFI restrained the intended foreclosure of Because of the recall, the last two checks dated
the property. However, the period commenced to February 10, 1993 and March 10, 1993 were no
run again on November 9, 1977 when the case was longer presented for payment, purportedly in
dismissed. conformity with petitioner bank's procedure. It
demanded payment of the balance including
The respondents institution of Civil Case No. C- liquidated damages, but private respondent
7496 in the CFI on March 16, 1979 did not interrupt refused to pay, prompting petitioner to file an
the running of the ten-year prescriptive period action for replevin1 and damages before the RTC.
because, as discussed above, the court lacked
The RTC decided against RCBC and granted the
jurisdiction over the action for declaratory relief.
counterclaim of Atty. Lustre for damages. The CA
All proceedings therein were without legal effect.
affirmed the RTC decision; hence this petition
Thus, petitioners could have enforced their right before the SC.
under the mortgage, including its foreclosure, only
until November 7, 1987, the tenth year from the
dismissal of Civil Case No. C-6329. Thereafter, ISSUE
their right to do so was already barred by
W/N Atty. Lustre defaulted on the payment on the
prescription.
last check? [NO]

The foreclosure held on February 8, 1995 was


therefore some seven years too late. The same
thing can be said about the public auction held on DECISION
March 27, 1995, the consolidation of title in CHFIs
Petitioner claims that private respondent's check
favor and the issuance of TCT No. 310191 in its representing the fifth installment was "not
name. They were all void and did not exist in the encashed," such that the installment for August
eyes of the law. 1991 was not paid. Using as basis the Chattel
Mortgage, petitioner submits that it "was justified
WHEREFORE, the petition is hereby DENIED. in treating the entire balance of the obligation as
due and demandable." Despite demand by
petitioner, however, private respondent refused to
pay the balance of the debt. Petitioner, in sum,
imputes delay on the part of private respondent.

Article 1170 of the Civil Code states that those


who in the performance of their obligations are
guilty of delay are liable for damages.2 The delay in
RCBC v. COURT OF APPEALS and FELIPE LUSTRE the performance of the obligation, however, must
Justice Kapunan; March 25, 1999 be either malicious or negligent.

Damages; Good Faith Compliance Thus, assuming that private respondent was guilty
of delay in the payment of the value of the
FACTS unsigned check, private respondent cannot be held
liable for damages. There is no imputation, much
In March 1991, private respondent Atty. Felipe less evidence, that private respondent acted with
Lustre purchased a Toyota Corolla. He made a malice or negligence in failing to sign the check.
down payment of P164,620.00, the balance of
which was to be paid in 24 equal monthly
installments thru RCBC as the financing agent. He 1 A procedure whereby seized goods may be
issued 24 postdated checks in the amount of provisionally restored to their owner pending the
P14,976.00 each. outcome of an action to determine the rights of the
parties concerned
2 Civil Code, art. 1170.
Indeed, we agree with the Court of Appeals' finding
that such omission was mere "inadvertence" on
the part of private respondent.

Toyota salesperson Jorge Geronimo testified that


he even verified whether private respondent had
signed all the checks and in fact returned three or
four unsigned checks to him for signing.

On the other hand, Petitioner's conduct, in the light


of the circumstances of this case, can only be DEIPARINE, JR. V. COURT OF APPEALS
described as mercenary. Petitioner had already G.R. No. 96643. APRIL 23, 1993 CRUZ, J.
debited the value of the unsigned check from (Unsafe building; rescission of contract)
private respondent's account only to re-credit it [Article 1191- power to rescind obligations implied
much later to him. Thereafter, petitioner encashed in reciprocal obligations]
checks subsequently dated, then abruptly refused
to encash the last two. More than a year after the FACTS:
date of the unsigned check, petitioner, claiming 1. On August 13, 1982, spouses Cesario and
delay. Teresita Carungay entered into an agreement with
contractor Ernesto Deiparine, Jr. for the
Good faith not only in compliance with its construction of a three-story dormitory in Cebu, for
contractual obligations3, but also in observance of which the Carungays agreed to pay P970,000.00.
the standard in human relations, for every person Deiparine bound to erect the building in strict
"to act with justice, give everyone his due, and accordance to plans and specifications. Nicanor
observe honesty and good faith," behooved the Trinidad, a civil engineer, was designated as
bank to do so. representative of the Carungay spouses with
power to inspect and coordinate with the
Failing thus, petitioner is liable for damages contractor.
caused to private respondent. These include moral
damages for the mental anguish, serious anxiety, 2. Upon the start of construction, Trinidad sent
besmirched reputation, wounded feelings and Deiparine the General Conditions and
social humiliation suffered by the latter. Specifications which prescribed 3,000 psi as
minimum compressive strength of the building. In
the course of the construction, Trinidad reported
to Cesario Carungay that Deiparine had been
deviating from the plans and specifications, thus
impairing the strength and safety of the building.

3. Carungay ordered Deiparine to first seek his


approval before pouring cement. The latter did not
heed the former so Carungay sent Deiparine a
memorandum complaining that the construction
works are faulty and done haphazardly mainly due
to lax supervision coupled with inexperienced and
unqualified staff. This memorandum was also
ignored.

4. After several conferences, the parties agreed to


conduct cylinder tests to test the structure’s
safety. Carungay suggested core-testing which is a
more reliable test. Deiparine was first reluctant
but eventually agreed and even promised that if
the tests should show total failure, or even above
10%, he would shoulder all expenses; otherwise,
the tests should be for the account of Carungay.

5. The core tests revealed that the building was


structurally unsafe so the Carungays filed with the
RTC of Cebu for the rescission of the construction
contract and for damages. Deiparine moved to
3 Civil Code, art. 1159.
dismiss, alleging that the court had no jurisdiction Code (providing that owner may withdraw at will
over construction contracts, which were now from construction contract although s/he must
cognizable by the Philippine Construction indemnify contractor for expenses, work, damages,
Development Board. etc.) is erroneous since the said provisions do not
apply to the construction agreement at hand.
6. The RTC rendered judgment: a) declaring the
construction agreement rescinded; b) condemning The trial court was correct in applying Article 1191
Deiparine to have forfeited his expenses in the because the latter relates to contracts involving
construction in the same of P244,253.70; c) reciprocal obligations like the subject construction
ordering Deiparine to reimburse to the spouses contract. The construction contract fails squarely
Carungay the sum of P15,104.33 for the core under the coverage of Article 1191 because it
testing; d) ordering Deiparine to demolish and imposes upon Deiparine the obligation to build the
remove all the existing structures and restore the structure and upon the Carungays the obligation to
premises to their former condition before the pay for the project upon its completion.
construction began, being allowed at the same
time to take back with him all the construction Article 1191, unlike Article 1385, is not predicated
materials belonging to him; and e) ordering on economic prejudice to one of the, parties but on
Deiparine to pay the Carungay spouses attorney's breach of faith by one of them that violates the
fees in the amount of P10,000.00 as well as the reciprocity between them. The violation of
costs of the suit. Judgment was affirmed by the reciprocity between Deiparine and the Carungay
Court of Appeals. spouses, to wit, the breach caused by Deiparine's
failure to follow the stipulated plans and
ISSUES: specifications, has given the Carungay spouses
1. Whether or not the trial court has jurisdiction the right to rescind or cancel the contract.
over the matter
2. Whether or not the trial and appellate court Article 1725 cannot support the petitioner's
erred in rescinding the contract position either, for this contemplates a voluntary
withdrawal by the owner without fault on the part
HELD: of the contractor, who is therefore entitled to
1. YES. indemnity, and even damages, for the work he has
Contrary to the malicious and misleading already commenced.There is no such voluntary
contention of the petitioners, the adjudicatory withdrawal in the case at bar. On the contrary, the
powers of the Philippine Domestic Construction Carungays have been constrained to ask for
Board are meant to apply only to public judicial rescission because of the petitioner's
construction contracts. Its power over private failure to comply with the terms and conditions of
construction contracts is limited to the their contract.
formulation and recommendation of rules and
procedures for the adjudication and settlement of The Court also held that while it is true that the
disputes involving such (private) contracts. It stress test was not required in any of the contract
therefore has no jurisdiction over cases like the documents, conducting the test was the only
one at bar which remain cognizable by the regular manner by which the owner could determine if the
courts of justice. contractor had been faithfully complying with his
presentations under their agreement. Furthermore,
2. NO. both parties later agreed in writing that the core
The Court sees no reason to disturb the factual test should be conducted. When the structure
finding of the courts below that Deiparine did not failed under this test the Carungay spouses were
deal with the Carungays in good faith. His breach left with no other recourse than to rescind their
of this duty constituted a substantial violation of contract.
the contract correctible by judicial rescission.
(Records show that Deiparine admitted that under Other applicable provisions according to the Court:
the General Conditions and Specifications sent by Articles 1714, 1715 and 1727.
Engr. Trinidad, a structural compressive strength
of 3,000 psi is required. Such belies Deiparine’s SPOUSES VASQUEZ V AYALA CORPORATION
contention that no compressive strength Tinga, J. | November 19, 2004
requirement was required.) Delay

The contention of the petitioner that Articles 1358 Art. 1169


(providing that rescission can only be carried out if Those obliged to deliver or to do something incur in delay
he who demands the same can return whatever he from the time the obligee judicially or extrajudicially
demands from them the fulfillment of their obligation.
may be obliged to restore) and 1725 of the Civil
However, the demand by the creditor shall not be Under the MOA, Ayala was to develop the entire
necessary in order that delay may exist: property, less what was defined as the "Retained
Area" consisting of 18,736 square meters. This
(1) When the obligation or the law expressly so declares;
"Retained Area" was to be retained by the Vazquez
or
(2) When from the nature and the circumstances of the
spouses. The area to be developed by Ayala was
obligation it appears that the designation of the time called the "Remaining Area". In this "Remaining
when the thing is to be delivered or the service is to Area" were 4 lots adjacent to the "Retained Area"
be rendered was a controlling motive for the and Ayala agreed to offer these lots for sale to the
establishment of the contract; or Vazquez spouses at the prevailing price at the time
(3) When demand would be useless, as when the obligor of purchase.
has rendered it beyond his power to perform.
"5.7. The BUYER hereby commits that it will develop
In reciprocal obligations, neither party incurs in delay if the 'Remaining Property' into a first class residential
the other does not comply or is not ready to comply in a subdivision of the same class as its New Alabang
proper manner with what is incumbent upon him. From Subdivision, and that it intends to complete the first
the moment one of the parties fulfills his obligation, phase under its amended development plan within
delay by the other begins. three (3) years from the date of this Agreement"

Article 1193
The parties are agreed that the development plan
Obligations for whose fulfillment a day certain has been
fixed, shall be demandable only when that day comes. referred to in paragraph 5.7 is not Conduit's
development plan, but Ayala's amended
Obligations with a resolutory period take effect at once, development plan which was still to be formulated
but terminate upon arrival of the day certain. as of the time of the MOA. While in the Conduit
plan, the 4 lots to be offered for sale to the
A day certain is understood to be that which must Vasquez Spouses were in the first phase thereof or
necessarily come, although it may not be known when.
Village 1, in the Ayala plan which was formulated a
year later, it was in the third phase, or Phase II-c.
If the uncertainty consists in whether the day will come
or not, the obligation is conditional, and it shall be
regulated by the rules of the preceding Section. After the execution of the MOA, Ayala caused the
suspension of work on Village 1 of the Don Vicente
Article 1197 Project. Ayala then received a letter from one
If the obligation does not fix a period, but from its nature Maximo Del Rosario of Lancer General Builder
and the circumstances it can be inferred that a period Corporation informing Ayala that he was claiming
was intended, the courts may fix the duration thereof.
the amount of P1,509,558.80 as the subcontractor
of G.P. Construction. The suit was terminated only
The courts shall also fix the duration of the period when
it depends upon the will of the debtor. on February 19, 1987, when it was dismissed with
prejudice after Ayala paid both Lancer and GP
In every case, the courts shall determine such period as Construction the total of P4,686,113.39.
may under the circumstances have been probably
contemplated by the parties. Once fixed by the courts, Taking the position that Ayala was obligated to sell
the period cannot be changed by them. the 4 lots adjacent to the "Retained Area" within 3
years from the date of the MOA, the Vasquez
Facts: spouses sent several "reminder" letters of the
On April 23, 1981, spouses Daniel Vasquez and Ma. approaching so-called deadline. However, no
Luisa M. Vasquez (hereafter, Vasquez spouses) demand after April 23, 1984, was ever made by the
entered into a Memorandum of Agreement (MOA) Vasquez spouses for Ayala to sell the 4 lots.
with Ayala Corporation (hereafter, AYALA) with
AYALA buying from the Vazquez spouses, all of the On the contrary, one of the letters signed by their
latter's shares of stock in Conduit Development, authorized agent, Engr. Eduardo Turla,
Inc. (hereafter, Conduit). categorically stated that they expected
"development of Phase 1 to be completed by
The main asset of Conduit was a 49.9 hectare February 19, 1990, three years from the settlement
property in Ayala Alabang, Muntinlupa, which was of the legal problems with the previous
then being developed by Conduit under a contractor."
development plan where the land was divided into
Villages 1, 2 and 3 of the "Don Vicente Village." The trial court rendered a decision in favor of
The development was then being undertaken for Spouses Vasquez but the Court of Appeals
Conduit by G.P. Construction and Development reversed.
Corp. (hereafter, GP Construction).
The Court of Appeals ruled that there was no delay
as petitioners never made a demand for Ayala
Corporation to sell the subject lots to them. NO DEMAND MADE BY PETITIONERS
According to the appellate court, what petitioners Accordingly, Ayala Corporation cannot likewise be
sent were mere reminder letters the last of which said to have delayed performance of the
was dated prior to April 23, 1984 when the obligation. Even assuming that the MOA imposes
obligation was not yet demandable. At any rate, an obligation on Ayala Corporation to develop the
the Court of Appeals found that petitioners in fact subject lots within three (3) years from date
waived the three (3)-year period when they sent a thereof, Ayala Corporation could still not be held to
letter through their agent, Engr. Eduardo Turla, have been in delay since no demand was made by
stating that they "expect that the development of petitioners for the performance of its obligation.
Phase I will be completed by 19 February 1990,
three years from the settlement of the legal As found by the appellate court, petitioners' letters
problems with the previous contractor." which dealt with the three (3)-year timetable were
all dated prior to April 23, 1984, the date when the
Issue: period was supposed to expire. In other words, the
W/N Ayala Corporation was in delay in selling the letters were sent before the obligation could
lots to the Spouses Valdez. become legally demandable. Moreover, the letters
were mere reminders and not categorical demands
Held: to perform. More importantly, petitioners waived
NO. the three (3)-year period as evidenced by their
agent, Engr. Eduardo Turla's letter to the effect
REQUISITES IN DECLARING DEFAULT that petitioners agreed that the three (3)-year
In order that the debtor may be in default it is period should be counted from the termination of
necessary that the following requisites be present: the case filed by Lancer.
(1) that the obligation be demandable and already
liquidated; (2) that the debtor delays performance; Excerpts from some of the letters:
and (3) that the creditor requires the performance In this regard, we would like to remind you
judicially or extrajudicially. of Articles 5.7 and 5.9 of our Memorandum
of Agreement which states respectively…
NO DAY CERTAIN FIXED IN CASE AT BAR
Under Article 1193 of the Civil Code, obligations for …and that we expect from your
whose fulfillment a day certain has been fixed goodselves compliance with our
shall be demandable only when that day comes. Memorandum of Agreement, and a definite
However, no such day certain was fixed in the date as to when the road to our property
MOA. and the development of Phase I will be
completed
In Par 5.7 of the MOA, it is unmistakable that it
merely expresses an intention (“that it intends to Manifestly, this letter expresses not only
complete the first phase under its amended petitioners' acknowledgement that the delay in the
development plan within three (3) years from the development of Phase I was due to the legal
date of this Agreement”) on Ayala Corporation's problems with GP Construction, but also their
part to complete the first phase under its amended acquiescence to the completion of the
development plan within three (3) years from the development of Phase I at the much later date of
execution of the MOA. February 19, 1990. More importantly, by no stretch
of semantic interpretation can it be construed as a
Petitioners, therefore, cannot demand categorical demand on Ayala Corporation to offer
performance after the three (3) year period fixed the subject lots for sale to petitioners as the letter
by the MOA for the development of the first phase merely articulates petitioners' desire to exercise
of the property since this is not the same period their option to purchase the subject lots and
contemplated for the development of the subject concern over the fact that they have not been
lots. provided with the specifications of these lots.

Since the MOA does not specify a period for the At best, petitioners' letters can only be construed
development of the subject lots, petitioners should as mere reminders which cannot be considered
have petitioned the court to fix the period in demands for performance because it must appear
accordance with Article 1197 of the Civil Code. As that the tolerance or benevolence of the creditor
no such action was filed by petitioners, their must have ended.
complaint for specific performance was
premature, the obligation not being demandable at
that point.
Contract To Buy And Sell; Condominium Unit;
Delay; Financial Crisis; Laches

The SC ruled that Tanseco need not have sent an


extrajudicial demand for Megaworld to be in
default because such demand would be useless.
Also, the Asian financial crisis was not considered
a fortuitous event.

FACTS
 Petitioner Megaworld and respondent Mila S.
Tanseco entered into a Contract to Buy and Sell
a 224 square-meter condominium unit at a pre-
selling project, “The Salcedo Park,” located
along Senator Gil Puyat Avenue, Makati City.
 The purchase price was P16,802,037.32, t0 be
paid in installments. A remaining balance of
P2,520,305.63 was, according to the contract,
to be paid on October 31, 1998, the stipulated
delivery date of the unit.
 The construction schedule in §4 of the Contract
provided that the unit shall be completed and
delivered no later than Oct. 31, 1998, with
addition grace period of 6 months, barring
delays due to fire, earthquakes, the elements,
acts of God, war, civil disturbances, strikes, or
other labor disturbances, government controls,
etc.
 Tanseco paid all installments due up to January
1998, leaving unpaid the balance of
P2,520,305.63 pending delivery of the unit.
Megaworld, however, failed to deliver the unit
within the stipulated period on October 31,
1998, or April 30, 1999, the last day of the 6-
month grace period.
 Almost 3 years later, Megaworld, by notice of
turnover, informed Tanseco that the unit was
ready for inspection preparatory to delivery.
Tanseco replied through counsel that in view of
Megaworld’s failure to deliver the unit on time,
she was demanding the return of
P14,281,731.70, representing the total
installment payment she had made, with
interest. Tanseco pointed out that none of the
expected causes of delay existed.
 Megaworld attributed the delay to the 1997
Asian financial crisis which was beyond its
control, and argued that default had not set in,
Tanseco not having made any judicial or
extrajudicial demand for delivery.

ISSUE
 W/N petitioner Megaworld is in default

HELD
MEGAWORLD GLOBUS ASIA, INC. V. TANSECO  Petition is GRANTED. Petitioner Megaworld is
GR NO. 181206| October 9, 2009 | CARPIO- declared in default and ordered to pay Tanseco
MORALES, the amount she had paid totaling P14,281,31.70,
Exceptions to Extrajudicial Demand; Default; Force with interest and damages.
Majeure/Caso Fortuito
 The Contract to Buy and Sell of the parties
contains reciprocal obligations, i.e., to complete
and deliver the condominium unit on October
31, 1998 or six months thereafter on the part of
Megaworld, and to pay the balance of the
purchase price at or about the time of delivery
on the part of Tanseco. Megaworld having failed
to comply with its obligation under the contract,
it is liable therefor.
 That Megaworld’s sending of a notice of
turnover preceded Tanseco’s demand for refund
does not abate her cause. For demand would
have been useless (Art. 1169, exception 3, Civil
Code), Megaworld admittedly having failed in its
obligation to deliver the unit on the agreed date.
 The Court cannot generalize the 1997 Asian
financial crisis to be unforeseeable and beyond
the control of a business corporation. A real
estate enterprise engaged in the pre-selling of
condominium units is concededly a master in
projections on commodities and currency
movements, as well as business risks. The
fluctuating movement of the Philippine peso in
the foreign exchange market is an everyday
occurrence, hence, not an instance of caso
fortuito. Megaworld’s excuse for its delay does
not lie.
 Tanseco’s claim is not barred by laches either.
Laches is a creation of equity and its
application is controlled by equitable
considerations. It bears noting that Tanseco
religiously paid all the installments due up to
January 1998, whereas Megaworld reneged on
its obligations to deliver within the stipulated
period. A circumspect weighing of equitable
considerations thus tilts the scale of justice in
favor of Tanesco. AEROSPACE CHEMICAL INDUSTRIES V CA, PHIL.
 Pursuant to §23 of PD 957, Tanseco is entitled to PHOSPHATE FERTILIZER CORP.
be reimbursed the total amount she paid Justice Quisumbing; September 23, 1999
Megaworld. ----------------------------------------------------------------------------
 Finally, since Art. 1191 of the Civil Code does Sulfuric Acid, Delay, Mora Solvendi
not apply to a contract to buy and sell, the Facts
suspensive condition of full payment of the 1. On June 27 1986, petitioner Aerospace
purchase price not having occurred to trigger Industries Inc. purchased f500 metric tons of
the obligation to convey title, cancellation, not sulfuric acid from private respondent Philippine
rescission, of the contract is thus the correct Phosphate Fertilizer Corporation (Philphos). The
remedy. contract was in letter-form stating that the
letter is to confirm of their agreement to supply
Sulfuric Acid under conditions agreed upon.
2. Petitioner agreed to secure the means of
transport to pick-up the sulfuric acid from
private respondents’ loadports— 100 MT in
Basay Negros Oriental and 400 MT from Sangi,
Cebu.
3. On August 6, 1986 Philphos sent Aerospace an
advisory letter to withdraw the sulfuric acid
purchased at Basay because they had been
incurring expenses of P2,000 each day of delay.
4. On October 3 1986, Aerospace paid P553,280
for the 500 MT sulfuric acid. On November 19
1986, Aerospace chartered M/T Sultan The storm, as the petitioner claims it, was not
Kayumanggi owned by Ace Bulk Head Services the proximate cause of the delay. According to
to carry the agreed volumes of freight from the a survey report submitted by a 3rd party
designated loading areas. surveyor, the vessel was unstable and
5. M/T Kayumanggi was able to withdraw only 70 incapable of carrying the full load of sulfuric
MT of sulfuric acid from Basay because the acid.
vessel was heavily tilted on its port side. 13. Note that there was a premature termination of
6. In a demand letter sent on December 12, 1986 loading in Basay, Negros Oriental. The vessel
Philphos asked Aerospace to retrieve the had to undergo several repairs before
remaining sulfuric acid in Basay so that the continuing its voyage to pick-up the balance of
tanks can be emptied on or before December cargo at Sangi, Cebu. Despite repairs, the
15, 1986. It said that Philphos will charge vessel still failed to carry the whole lot of 500
Aerospace the storage and conseqeuntial costs MT
for the Basay tanks. 14. It is not true that the defendant was not in a
7. On December 18, 1986, the vessel docked at position to deliver the 272.481 MT which was
Sangi, Cebu but withdrew only 157.51 MT of the balance of the original 500 MT purchased
acid. Again the vessel tilted. Later, the vessel by the plaintiff. The whole lot of 500 MT was
sank with a total of 227.51 MT of acid on board. ready for lifting as early as August 15, 1986.
8. Aerospace chartered another vessel M/T Don What the defendant could not sell to the
Victor with a capacity of 500 MT. On January 26 plaintiff was the additional 227.51 MT which
and March 20 1987, Aerospace addressed said plaintiff was ordering, for the reason that
letters to Philphos regarding additional orders the defendant was short of the supply needed.
of acid to replace its sunken purchases. The The defendant, however, had no obligation to
same letter was sent on May 15. agree to this additional order and may not be
9. On January 25 1988, Aerospace’s counsel, Atty. faulted for its inability to meet the said
Santos, sent a demand letter to Philphos for the additional requirements of the plaintiff. And the
delivery of the 272.49 MT of acid paid by his defendant's incapacity to agree to the delivery
client or the return of the purchase price of of another 227.51 MT is not a legal justification
P307,530. Philphos in reply on March 8, for the plaintiff's refusal to lift the remaining
instructed Aerospace to lift the remaining 30 272.481
MT of acid in Basay or pay the maintenance 15. Damages can be properly awarded to the
and storage expenses since August 1, 1986. But private respondent and not the petitioner.
Aerospace again, wrote a letter on July 6 Where there has been breach of contract by the
insisting on picking up the purchase of 272 MT buyer, the seller has a right of action for
because he had paid the full capacity of 500 damages. Following this rule, a cause of action
MT. of the seller for damages may arise where the
10. On May 4 1989, Aerospace filed a complaint for buyer refuses to remove the goods, such that
specific performance and/or damages before buyer has to remove them (Art. 1170) Delay
the RTC of Pasig. Philphos filed its answer begins from the time the obligee judicially or
stating that it was Aerospace who was remiss extrajudicially demands from the obligor the
in the performance of its obligation in performance of an obligation. In order that the
arranging the shipping requirements of its debtor may be in default, it is necessary that
purchases and thus should pay damages. the following requisites be present: (1) that the
11. RTC favored Aerospace finding that it was obligation be demandable and already
absolved in its obligation to pick up the liquidated; (2) that the debtor delays
remaining acid because its failure was due to performance; and (3) that the creditor requires
force majeure (unforeseeable circumstance). the performance judicially or extrajudicially. In
And that it was Philphos who committed the present case, private respondent required
breach when it failed to accommodate the petitioner to ship out or lift the sulfuric acid as
additional order. agreed, otherwise petitioner would be charged
12. CA reversed the decision and found Aerospace for the consequential damages owing to any
guilty of delay and negligence in the delay
performance of its obligation. 16. Philphos incurred expenses in its Basay ports
because of the partial lifting of Aerospace. It
Issue also extended its lease agreement for Sangi,
W/N Philphos commit a breach of contract when it Cebu because the petitioner was not able to
did not sell the additional orders of Aerospace [NO] get there. It stands to reason that petitioner
Decision should reimburse private respondent's rental
1. Court held that the claim that Aerospace’s expenses of P32,000 monthly, commencing
delay and failure to lift he cargo is untenable.
December 15, 1986, up to August 31, 1987, the suitable. The respondent then demanded the pre-
period of the extended lease. termination of the lease contract
17. As pointed out earlier, petitioner is guilty of effective November 4, 1997, and reimbursement of
delay, after private respondent made the the advance rentals and security deposit.
necessary extrajudicial demand by requiring
petitioner to lift the cargo at its designated
The petitioner rejected the respondents demand
loadports. When petitioner failed to comply
on the ground that the fire was caused by the
with its obligations under the contract it
gross negligence of the occupants. Instead, the
became liable for its shortcomings. Petitioner
is indubitably liable for proven damages. petitioner offered to refund the balance, if any, of
18. Considering, however, that petitioner made an the advance rentals and security deposit from the
advance payment for the unlifted sulfuric acid time it is able to find a new lessee until February
in the amount of three hundred three thousand, 22, 1999.
four hundred eighty three pesos and thirty
seven centavos (P303,483.37), it is proper to On May 29, 1998, petitioner informed the
set-off this amount against the rental expenses respondent of the completion of the repairs of the
initially paid by private respondent. It is worth premises and asked whether the latter will
noting that the adjustment and allowance of reoccupy the same. The respondent, however,
private respondent's counterclaim or set-off in replied that it was no longer interested in
the present action, rather than by another
reoccupying the subject property and reiterated its
independent action, is encouraged by the law.
request for the refund of the advance rentals paid.
Such practice serves to avoid circuitry of
Consequently, the petitioner informed the
action, multiplicity of suits, inconvenience,
expense, and unwarranted consumption of the respondent that it has advertised the property as
court's time available for lease and that it was willing to refund
the balance, if any, of the advance rentals and
FELSAN REALTY & DEV’T CORP. V security deposit from the time of the new lease up
COMMONWEALTH OFAUSTRALIA to and including February 22, 1999, less the
Justice Nachura; October 11, 2007 amount spent for the repairs of the damage
Contract of Lease caused to the property. The respondent did not
agree.
Facts:
Petitioner Felsan Realty & Development Respondent filed a complaint against the
Corporation is the owner of a three-storey duplex petitioner claiming that under Section 13 of the
residential house located at San Lorenzo Village, Contract of Lease, it is entitled to the
Makati City. Respondent Commonwealth of reimbursement ofP1,556,666.67 as balance of the
Australia entered into a contract of lease over the prepaid rental. (It also prayed for exemplary
said property with the petitioner. The lease was for damages, attorneys fees and the costs of suit.)
two years from February 22, 1997 until February
21, 1999. The respondent paid P200K as two In its Answer with Counterclaim, the petitioner
months deposit and P2.4M as advance rentals for averred that the respondent did not comply with
the entire duration of the lease. the mandatory requirement under Article 1358 of
the Civil Code of the Philippines that a pre-
On November 4, 1997, Fire broke out at the ground termination or rescission of a contract of lease
floor of the leased premises, which destroyed a over real property shall appear in a public
major portion of the house. According to the Fire document. It claimed that the respondent is not
Investigation Report, the cause of the fire was entitled to reimbursement because the subject
[a]ccidental due to overheated electric fan that property was damaged by fire due to its
produce[d] intense heat/sparks and subsequently negligence.
ignited the combustible materials thereat and
burst into flame During trial, Edgardo A. Nogales, who was the
Chief of the Investigation and Intelligence Unit of
Respondent, on November 21, 2007, informed the Fire Station 2- Fire District III, and Reynaldo D.
petitioner that the property has become Gonzales, the Fire and Arson Investigator assigned
uninhabitable. Its Facilities Manager indicated that to the case, had slightly conflicting testimonies on
it would take 3 months to complete restoration and the overheating of the electric fan. Nogales
that the alternate property offered was not testified that it was “off,” while Gonzales, who did
a personal, ocular inspection after the firemen
forcibly opened the maid’s room, testified that the On the matter of the conflicting testimonies, the
fan was in the “on” position. Both testified that the Court quoted with favor the respondent court’s
source of ignition could only be the burnt electric ruling:
fan that was still plugged in. x x x [T]he Court cannot reasonably conclude
therefrom that the accident was attended by
The trial court found for the respondent. Upon negligence or fault on the part of appellee. As
appeal, the CA rendered a Decision affirming the the trial court correctly pointed out, the
RTC decision upholding the right of the respondent cause of the fire could have been faulty
to pre-terminate the contract of lease. At the wiring either of the fan itself or the electrical
outset, the appellate court agreed with the socket but no evidence was presented to
petitioner that the terms accident and accidental establish the same. Thus, bereft of sufficient
do not exclude, without qualification, events evidence to establish that the fire was
resulting in damage or loss due to the fault, caused by the negligence of appellee, the
recklessness or negligence of third finding of the trial court that the cause of the
parties. However, in view of the conflicting fire was accidental in nature must be
testimonies of the fire investigators, it held that it sustained. Besides, appellants witness
cannot reasonably conclude that the accident was himself admitted that Felsan requested for
attended by negligence or fault. It, therefore, the certification of SPO4 Nogales and used
sustained the trial courts findings that the the same to establish that the fire was
respondent cannot be held liable since the caused by pure accident to recover indemnity
petitioner failed to establish by preponderance of in the amount of more than one million pesos
evidence of the respondent’s negligence. It agreed from the insurer and it is now estopped from
with the trial court that non-compliance with the disputing the said finding.”
requirement under Article 1358 of the Civil Code
does not affect the validity or enforceability of the Considering the foregoing, the petitioner cannot
rescission of the contract as between the parties use the respondent’s alleged fault or negligence as
[as it is “a mere formality for the convenience of an excuse to prevent the pre-termination of the
the parties”]. lease contract.

Issue: It must be noted that the various stipulations in a


Whether or not the CA committed a grave and contract must be interpreted together, attributing
reversible error in ruling that the respondent has to the doubtful ones that sense which may
the right to pre-terminate the Contract of Lease result from all of them taken jointly. Section 13 of
the Contract of Lease enumerates the grounds for
Held: pre-termination as fire, lightning, earthquake,
The Court finds no reversible error in the appellate typhoon, or by any cause in the nature of force
court’s ruling that the respondent has the right to majeure. The second and third sentences of
pre-terminate the Contract of Lease. The first Section 13 use accident or force majeure in
paragraph of Section 13 plainly states that, where referring to the grounds for the pre-termination of
the leased property is damaged by fire, the lessee the Contract. Except for fire, none of the other
has the right to automatically pre-terminate the causes can occur through accident because they
contract when it finds that the damage to the are all natural calamities. The only logical
property rendered it uninhabitable or unsuitable conclusion is that the word accident qualifies
for living. In this case, the respondent determined fire; the lessee does not have the right to pre-
that the leased property has become uninhabitable terminate only when fire is not accidental or is
after it was damaged by fire. Accordingly, it deliberate. No other qualification can be read into
immediately exercised its right to pre-terminate the Contract. Accident and negligence are
the contract. intrinsically contradictory; one cannot exist with
the other. Accident occurs when the person
When the terms of the contract are clear and leave concerned is exercising ordinary care, which is not
no room for interpretation, the literal meaning of caused by fault of any person and which could not
its stipulations shall, therefore, control. A court have been prevented by any means suggested by
has no alternative but to enforce the contractual common prudence. Hence, a statement that the
stipulations in the manner they have been agreed cause was accidental necessarily implies that it
upon and written. was not due to the fault or negligence of any party.
Clearly, the respondent had the right to pre-
terminate the Contract of Lease considering that it
was well established that the fire was accidental
in nature.

* As to the award of attorney’s fees in favor of the


respondent, the Court finds that this is not
warranted under the circumstances; hence, it
should be deleted. An adverse decision does
not ipso facto justify an award of attorneys fees to
the winning party. The power of the court to
award attorneys fees under Article 2208 demands
factual, legal, and equitable justification. Even
when a claimant is compelled to litigate with third
persons or to incur expenses to protect his rights,
still attorneys fees may not be awarded where no
sufficient showing of bad faith could be reflected
in a party’s persistence in a case other than an
erroneous conviction of the righteousness of his
cause

ANTONIO TAN v. COURT OF APPEALS and CCP


Justice De Leon, Jr.; October 19, 2001
Obligations with a Penal Clause; Interest when
Judicially Demanded

FACTS
On May 14, 1978 and July 6, 1978, petitioner
Antonio Tan obtained two (2) loans each in the
principal amount of P2,000,000 (totaling
P4,000,000)or in the total principal amount of Four
Million Pesos (P4,000,000.00), from respondent
CCP, evidenced by two (2) promissory notes with
maturity dates on May 14, 1979 and July 6, 1979,
respectively.
Petitioner defaulted but after a few partial
payments he had the loans restructured by In the case at bar, the promissory note (Exhibit
respondent CCP, and petitioner accordingly "A") expressly provides for the imposition of both
executed a promissory note on August 31, 1979 in interest and penalties in case of default on the
the amount of P3,411,421.32)payable in five (5) part of the petitioner in the payment of the subject
installments, which he failed to pay. restructured loan. The stipulated fourteen percent
(14%) per annum interest charge until full payment
In a letter dated January 26, 1982, petitioner of the loan constitutes the monetary interest on
requested and proposed to respondent CCP a the note and is allowed under Article 1956 of the
mode of paying the restructured loan: 20% upon New Civil Code.5 On the other hand, the stipulated
confirmation by CCP to the proposal, and the two percent (2%) per month penalty is in the form
remaining balance paid in 36 equal installments. of penalty charge which is separate and distinct
from the monetary interest on the principal of the
On October 20, 1983, petitioner again sent a letter loan.
to respondent CCP requesting for a moratorium on
his loan obligation until the following year Second, according to the petitioner, there is no
allegedly due to a substantial deduction in the legal basis for the imposition of interest on the
volume of his business and on account of the peso penalty charge for the reason that the law only
devaluation. No favorable response was made to allows imposition of interest on monetary interest
said letters. Instead, respondent CCP, through but not the charging of interest on penalty.
counsel, wrote a letter dated May 30, 1984 to the
petitioner demanding full payment of the loan, now However, the SC explained that penalty clauses
amounting to P6,088,735.03. can be in form of penalty or compensatory
interest. Thus, the 2% penalty is sanctioned and
On August 29, 1984, respondent CCP filed in the allowed by law. In addition, interest became due
RTC of Manila a complaint for collection of a sum from the time CCP filed a complaint in Court, as
of money against Tan. this constituted a judicial demand as required by
law.6
The RTC ruled in favor of CCP and ordered Tan to
pay the amount of more than seven million pesos Third, petitioner sought the elimination of the
representing his outstanding account with compounded interest imposed on the total amount
interest, surcharges, and attorney's fees. The CA based allegedly on the case of National Power
affirmed the RTC’s decision imposing interest, and Corporation v. National Merchandising Corporation,
surcharges but reduced the amount of attorney's wherein the SC ruled that the imposition of
fees and deleted the exemplary damages. interest on the damages from the filing of the
complaint is unjust where the litigation was
On appeal, Tan asked for the non-imposition of prolonged for twenty-five (25) years through no
interest on the surcharges inasmuch as the fault of the defendant.
compounding of interest on surcharges is not
provided in the promissory note marked Exhibit The SC explained that this ruling did not apply to
"A." the Tan case because there was an express
stipulation in the present case stating Tan’s
ISSUE agreement to the penalty of compound interest.
W/N the CA erred in affirming the RTC’s decision,
there is no stipulation to the contrary.
imposing interest and attorney’s fees. [NO]
Nevertheless, damages shall be paid if the obligor
refuses to pay the penalty or is guilty of fraud in
DECISION the fulfillment of the obligation.
First, the petitioner imputed error on the part of
the appellate court in not totally eliminating the The penalty may be enforced only when it is
award of attorney's fees and in not reducing the demandable in accordance with the provisions of
penalties considering that the petitioner, contrary this Code.
to the CA’s findings, has allegedly made partial
payments on the loan. The SC disagreed with this,
citing Art. 1226 of the Civil Code4 as basis. 5 Civil Code, art. 1956: No interest shall be due
unless it has been expressly stipulated in writing.
4 Civil Code, art. 1226: 6 Civil Code, art. 2212: Interest due shall earn legal
interest from the time it is judicially demanded,
In obligations with a penal clause, the penalty although the obligation may be silent upon this
shall substitute the indemnity for damages and the point.
payment of interests in case of non-compliance, if
However, the SC found the continued monthly specifications of the DPWH by using substandard-
accrual of the two percent (2%) penalty charge on size steel bars instead of standard-size steel bars.
the total amount due to be unconscionable RAM Builders was required to make additional
inasmuch as the same appeared to have been reinforcements to attain the strength required for
compounded monthly. the foundation and to pour additional mix
concrete.
Considering Tan’s several partial payments and the
fact that he was liable for the 2% penalty charge 3. In its claim for payment, RAM Builders reported
per month on the total amount due, the SC found it that petitioner Cruz certified that all work items
fair and equitable to reduce the penalty charge to have been accomplished in accordance with the
a straight 12% per annum on the total amount. approved plans, specification and program of work
and that petitioner Brucal signed the certificate of
Fourth, petitioner imputed error on the CA for not clearance for equipment rental and other
declaring the suspension of the running of the obligations which allowed RAM Builders to claim
interest during that period when the respondent payment. The latter also submitted and signed the
allegedly failed to assist the petitioner in applying Statement of Time Elapsed of Work Accomplished.
for relief from liability. The OMB Task Force however, concluded after its
investigation that there were major defects in the
The SC disagreed with this, saying that the said construction of the school building as a direct
letter did not contain any categorical agreement result of the contractors improper methods and its
on the part of respondent CCP that the payment of use of substandard materials and that the school
the interest and surcharge on the loan was building was far weaker in strength than that
deemed suspended while his appeal for envisioned by the planners. Said task force also
condonation of the interest and surcharge was found that the deviation from the plan had been
being processed. deliberate considering that RAM Builders is
already a regular supplier and dealer of
construction materials in Lucena City.
BRUCAL v. DESIERTO
G.R. No. 152188. JULY 8, 2005 4. The Administrative Adjudication Bureau of the
QUISIMBING, J. OMB found the petitioners administratively liable
(DPWH Officials convicted with Dishonesty and for dishonesty and gross neglect of duty and
Gross Neglect of Duty; Definition of dishonesty and recommended the dismissal of the petitioners with
gross negligence) forfeiture of leave credits and retirement benefits
[No mention of any article of the Civil Code] and disqualification for reemployment in the
government service. On appeal, the Court of
FACTS: Appeals affirmed the conviction of Cruz and
1. Petitioners Florentino Brucal and Cesar Cruz Brucal.
were members of the members of the Second
Engineering District Prequalification, Bids and ISSUES:
Awards Committee (PBAC) of the Department of Whether or not petitioners Brucal and Cruz could
Public Works and Highways (DPWH). Brucal was legally and validly be held liable for dishonesty and
the project engineer while Cruz was the chief of gross neglect of duty in signing the statement of
the construction section of the work accomplished and statement of time elapsed
Inaclagan Barangay High School Project. They
were charged by the Ombudsman Task Force on Their contentions:
Public Works and Highways with Dishonesty, a. For the charge of dishonesty, the petitioners
Falsification of Official Documents, Grave contend that the questioned decision is based on a
Misconduct, Violation of Office Rules and misapprehension of facts. They allege that they
Regulations, and Conduct Prejudicial to the Best signed the Statement of Work Accomplished as
Interest of the Service for irregularities in well as the Statement of Time Elapsed on April 4,
connection with the bidding, award, and 1990, after corrective measures were undertaken
implementation of contracts in the province of on the project.
Quezon. b. On the charge of gross neglect of duty,
petitioners submit that there could be no
2. Said OMB Task Force found out that petitioners administrative culpability as they acted in good
awarded the P281,475.30 construction of a three- faith. They both attended to other simultaneous
classroom building at Inaclagan Barangay High on-going projects and thus could not be physically
School, Gumaca, Quezon to contractor RAM present everyday during the construction of the
Builders which allegedly committed substantial Inaclagan project. They asked
deviations from the approved plans and the barangay officials to oversee the project.
professional nature and responsibilities of the task
HELD: but its impact as well on the efficiency of public
YES. service. As public servants, petitioners are
For petitioner Cruz, signing the Statement of Work expected to exhibit the highest degree of
Accomplished, despite the fact that the proper dedication in deference to their foremost duty of
methods of construction were not complied with, accountability to the people.
amounts to dishonesty. On Brucal’s part, signing
the Statement of Time Elapsed constitutes fraud
and dishonesty vis--vis the contractors obligation
relative to the plans and specifications as it
allowed payment to RAM Builders. Clearly, the
petitioners factual averment that the said RODZSSEN SUPPLY CO. INC. V FAR EAST BANK &
statements were signed after corrections were TRUST CO.
made need to be ascertained to determine their Panganiban, J. | May 9, 2001
liability on the charge for dishonesty. As Debtor and creditor both negligent
defined, dishonesty is intentionally making a false
statement in any material fact, or practicing or Facts:
attempting to practice any deception or fraud in TRIAL COURT
securing his examination, registration, Rodzssen Supply, Inc. opened with Far East Bank
appointment or promotion. Dishonesty is and Trust Co. a 30-day domestic letter of credit
understood to imply a disposition to lie, cheat, (LC) in the amount of P190,000.00 in favor of
deceive, or defraud; untrustworthiness; lack of Ekman and Company, Inc. (Ekman) for the
integrity. purchase from the latter of 5 units of hydraulic
loaders, to expire on February 15, 1979; that
Anent the charge of gross neglect, the Court is in subsequent amendments extended the validity of
accord with the findings of the OMB Adjudication said LC up to October 16, 1979.
Bureau, as affirmed by the Court of Appeals,
finding herein petitioners liable for gross neglect On March 16, 1979, 3 units of the hydraulic loaders
of duty. Gross negligence refers to negligence were delivered to Rodzssen for which Far East
characterized by the want of even slight care, Bank on March 26, 1979, paid Ekman the sum of
acting or omitting to act in a situation where there P114,000.00, which amount Rodzssen paid Far East
is a duty to act, not inadvertently but wilfully and Bank before the expiry date of the LC.
intentionally, with a conscious indifference to
consequences in so far as other persons may be The shipment of the remaining 2 units of hydraulic
affected. It is the omission of that care which even loaders valued at P76,000.00 sent by Ekman was
inattentive and thoughtless men never fail to take 'readily received by Rodzssen before the expiry
on their own property. In cases involving public date [of] subject LC.
officials, there is gross negligence when a breach
of duty is flagrant and palpable. Upon Ekman's presentation of the documents for
the P76,000.00 'representing final negotiation' on
The Court finds that petitioners were unable to the LC before the expiry date, and 'after a series of
satisfactorily explain their failure to oversee the negotiations', Far East Bank paid to Ekman the
project in its critical stages. Their defense that amount of P76,000.00; and that upon Far East
corrections were nevertheless employed and that Bank’s demand on Rodzssen to pay for said
they handled other projects do not negate their amount (P76,000.00), Rodzssen refused to pay
administrative liability. Instead, it is indicative of a without any valid
conscious design to delegate the vital task reason.
incumbent upon them as engineers whose
appointment to such position is by reason of their Rodzssen contends that there was a breach of
academic preparation and work experience to contract by Far East Bank who in bad faith paid
conceptualize, plan, implement and manage a Ekman, knowing that the 2 units of hydraulic
development project of the government. loaders had been delivered to Rodzssen after the
expiry date of subject LC; and that in view of the
Evidently, they failed to timely perform their breach of contract, Rodzssen offered to return to
assigned duties with dedication, efficiency, and Far East Bank the 2 units of hydraulic loaders,
utmost responsibility, ideals which men and 'presently still with Rodzssen’ but Far East Bank
women in public service ought to cherish and refused to take possession thereof.
dutifully observe. On the whole, petitioners as
construction engineers in charge of the Inaclagan The trial court ruled that Far East Bank was
project, should be fully cognizant not only of the entitled to recover from Rodzssen the amount of
P76,000 on the ground that acceptance by,
Rodzssen of the 2 remaining units of the 5 loaders, UNEXPLAINED INACTION OF PETITIONER
Rodzssen became liable to Ekman for the payment Granting that petitioner was bound under such
of said 2 units. However, as Rodzssen did not pay arrangement to accept the late delivery of the
Ekman, the latter pressed Far East Bank for the equipment, we note its unexplained inaction for
payment of said two loaders in the amount of almost four years with regard to the status of the
P76,000.00. ownership or possession of the loaders.
Bewildering was its lack of action to validate the
While Rodzssen, indeed offered to return the two ownership and possession of the loaders, as well
loaders to Far East Bank, this offer was made 3 as its stolidity over the purported failed sales
years after Rodzssen’s receipt of the goods, when transaction. Significant too is the fact that it
Far East Bank pressed for payment. By said formalized its offer to return the two pieces of
voluntary acceptance of the 2 loaders, estoppel equipment only after respondent's demand for
works against Rodzssen who should have refused payment, which came more than three years after
delivery of, and/or immediately offered to return, it accepted delivery.
the goods.
BOTH PARTIES NEGLIGENT
The Court of Appeals affirmed trial court’s When both parties to a transaction are mutually
decision. negligent in the performance of their obligations,
the fault of one cancels the negligence of the
Issue: other and, as in this case, their rights and
W/N petitioner is liable to pay respondent. obligations may be determined equitably under the
law proscribing unjust enrichment.
Held:
YES.

DEFENDANT PAYED FOR PETITIONER AFTER


EXPIRY
Clearly, the bank paid Ekman when the former was
no longer bound to do so under the subject Letter
of Credit. The records show that respondent paid
the latter P76,000 for the last 2 hydraulic loaders
on March 14, 1980, 5 months after the expiration of
the Letter of Credit on October 16, 1979.

In fact, on December 27, 1979, the bank had


informed Rodzssen of the cancellation of the
commercial paper and credited P22,800 to the
account of the latter. The amount represented the
marginal deposit, which petitioner had been
required to put up for the unnegotiated portion of
the Letter of Credit — P76,000 for the two
hydraulic loaders.

The subject Letter of Credit had become invalid


upon the lapse of the period fixed therein. Thus,
respondent should not have paid Ekman; it was not
obliged to do so.
SOUTHEASTERN COLLEGE, INC. V. COURT OF
PETITIONER STILL HAS TO PAY DEFENDANT APPEALS
Be that as it may, we agree with the CA that GR NO. 126389| July 10, 1998 | PURISIMA, J.
petitioner should pay respondent bank the amount Force Majeure
the latter expended for the equipment belatedly SCHOOL BUILDING; TYPHOON SALING; OCULAR
delivered by Ekman and voluntarily received and INSPECTION; ROOFINGS
kept by petitioner.

The Supreme Court held that petitioner school


True, it erred in paying Ekman, but petitioner itself
should not be held to account for the damage
was not without fault in the transaction. It must be
caused to respondents’ house as there was no
noted that the latter had voluntarily received and
clear and convincing evidence that they were
kept the loaders since October 1979.
negligent in the construction and maintenance of the trial court imputed negligence to the
their school building. petitioner.
 The Court believes otherwise. After a careful
FACTS scrutiny of the records and the pleadings
 This is a petition for review seeking to set aside submitted by the parties, the Court finds that
the Decision of the Court of Appeals which the trial court misappreciated the evidence
reduced the moral damages awarded to private proffered.
respondent from P1,000,000 to P200,000.  There is no question that a typhoon or storm is
 Private respondents are owners of a house at a fortuitous event, a natural occurrence which
326 College Road, Pasay City, while petitioner may be foreseen but is unavoidable. But private
owns a 4-storey school building along the same respondents merely relied on the
College Road. On October 11, 1989, a powerful aforementioned report submitted by a team
typhoon named “Saling” hit Metro Manila. which made an ocular inspection of petitioner’s
Buffeted by very strong winds, the roof of school. As the term imparts, an ocular
petitioner’s building ripped off and blown away, inspection is one by means of actual sight or
landing on and destroying portions of the viewing. What is visual to the eye though is not
roofing of private respondents’ house. always reflective of the real cause behind. The
After the typhoon had passed, an ocular relationship of cause and effect must be clearly
inspection conducted by a team of engineers shown.
headed by the city buildings official, Engr. Jesus  In the present case, other than said ocular
L. Reyna. Their report indicated that one of the inspection, no investigation was conducted to
reasons for the dislodging of the roofing’s determine the real cause of the partial
structural trusses is the improper anchorage of unroofing of petitioner’s school building. Private
the said trusses on roof beams. It then respondent did not even show that the plans,
recommended that the fourth floor of subject specifications and design of said building were
school building be declared as a “structural deficient and defective. Neither did they prove
hazard.” any substantial deviation from the approved
 In their complaint for damages based on cupla plans and specifications. Nor did they
aquliana, private respondents alleged that the conclusively establish that the construction of
damage to their house rendered the same such building was basically flawed.
uninhabitable, forcing them to stay temporarily  ‘On the other hand, petitioner elicited from Engr.
in other’s houses. Reyna that the original plans and design were
approved prior to its construction. Having
ISSUE obtained both building permit and certificate of
 W/N the damage on the roof the building of occupancy, these are, at the very least, prima
private respondents was due to fortuitous event facie evidence of regular and proper
 W/N petitioner was negligent when its roofings construction of subject school building.
caused damage to respondents’ house  Petitioner also presented its VP for Finance and
Administration who testified that an annual
HELD maintenance inspection and repair of subject
 Petition is GRANTED and the challenged school building were regularly undertaken.
decision is REVERSED. The complaint of private  Moreover, Engr. Reyna admitted that no
respondent is DISMISSED. Private respondents complaint regarding any defect on the same
are ordered to return to petitioner any amount structure has even been lodged before his
received from them. office. It is a matter of judicial notice that
 In order that a fortuitous event may exempt a typhoons are common occurrences in the
person from liability, it is necessary that he be country.
free from any previous negligence or  Thus, there is no clear and convincing evidence
misconduct by reason of which the loss may to sustain the judgment of the appellate court.
have been occasioned. When a person’s Petitioner has not been shown to be negligent
negligence concurs with an act of God in or at fault regarding the construction and
producing damage or injury to another, such maintenance of its school building and that
person is not exempt from liability by showing typhoon “Saling” was the proximate cause of
that the immediate or proximate cause of the the damage suffered by private respondents’
damage was a fortuitous event. house.
 In the case under consideration, the lower court
accorded full credence to the finding of the
investigating team that subject school
building’s roofing had “no sufficient anchorage
to hold it in position.” Based on such finding,
as well as for the portion sold, shall be
borne by the parties share and share alike
3. The Buot spouses, as vendees, paid
Encarnacion the earnest money of 1,000. And
paid additional sums of money totalling P2,774
duly receipted as part payment of the subject
lot.
4. The controversy arose when Alfredo Buot, to
protect his interest, informed the Provincial
Assessor of Cebu that he had acquired certain
rights on the said parcel of land, which was not
titled. The Provincial Assessor annotated his
said right on a tax declaration.
5. On May 18, 1977 Alfredo Buot received a
subpoena requiring him to appear for a
confrontation with Encarnacion Diaz. It was
then when they found out that Encarnacion
executed a Deed of Absolute Sale to spouses
Mariano Del Rosario for the whole parcel of
land including the portion which was sold to
them.
6. Mariano was able to secure a Free Patent Title
to the entire property.
7. Encarnacion filed his answer stating that she
offered the land to spouses Buot if he could
furnish amounts in order to have the land
registered. She said that she exerted effort to
register the property but the amount the
petitioners provided were in small insufficient
SPOUSES ALFEDO AND SUSANA BUOT V CA, amounts to pay for the registration expenses.
ENCARNACION DIAZ Because she was in financial distress, she
Justice De Leon; May 18 2001 informed petitioners she could not wait any
----------------------------------------------------------------- longer and just offered to reimburse. But the
Contract of Sale, Contract to Sell latter refused.
8. On the part of Mariano Del Rosario, he testified
Facts that Encarnacion Diaz mortgaged the land to
1. Spouses Alfredo and Susana Buot, alleged in him evidenced by a deed of real estate
their complaint that on December 6, 1974, mortgage executed on May 17, 1977. As a
Encarnacion Diaz Vda. de Reston sold to them mortgagee he was given an option to purchase
the eastern portion of her property with an area the property, and thus purchased it about 3
of 19,042 sqm in Tulay, Cebu as evidenced by a months later.
Memorandum of Agreement 9. Mariano invoked that Encarnacion represented
2. The Memorandum of Agreement stated to him that she was the absolute owner of the
✓ The Purchase Price of P19,042 shall be property; and that at the time of free patent he
paid— 1,000 in the concept of earnest did not know of any transaction between
money upon the execution of the said Encarnacion and the buot spouses. However
instrument; and the balance of 18,042 he admitted that he did not check whether
within 6 months from the date the Encarnacion was the owner of the mortgaged
vendees and notified by the vendor of the property and merely relied on the
fact that the Certificate of Title is ready representation of Encarnacion, he did not also
for transfer in the names of the vendees. check with the Office of the Provincial
✓ The title to, ownership, possession and Assessor whether there was an annotation on
enjoyment of the portion sold shall remain the tax declaration of the property.
with the vendor until the full consideration 10. The trial Court declared the Buot spouses the
of the sale shall have been received by her absolute owners of the eastern portion of land,
and acknowledged in a document duly but the decision was reversed by the CA.
executed for said purpose 11. The Buot spouses filed this petition submitting
✓ Expenses for the registration of the lot that contrary to the holding of the Court of
under the Torrens system, with a view to Appeals, the MOA was not an option to
securing a certificate of title for the same, purchase but a valid and partially executed
contract of sale; thus the subject property is only fair that the Buot spouses be allowed to
could not anymore be the valid subject of recover what they had paid in expectancy that
another sales contract in favor of Mariano the condition would happen, otherwise there
regardless of the allegation of good faith. would be unjust enrichment on the part of
Encarnacion Diaz.
Issue 19. Respondent Mariano on the other hand, held a
W/N petitioners are entitled to recover the property contract of sale evidenced by the Deed of
in question this resolving that the MOA entered Definite sale covering the said entire property
into by them with Encarnacion is a contract of sale of Encarnacion.
[NO]

Decision
1. The Court dismissed the petition and affirmed
the decision of the Court of Appeals but
ordered the return of the partial payments
made by spouses Buot to Encarnacion Diaz.
12. Petitioners assert that the MOA was a contract
of sale which was perfected from the moment SILVESTRE DIGNOS V. COURT OF APPEALS
the parties agreed on the object of the contract Justice Bidin; February 29, 1988
and the price. The downpayment of P1,000 was
Contract of Sale/Contract to Sell
proof that the contract had been perfected.
13. The Court disagrees. An examination of the
Facts:
MOA shows that is is neither a contract of sale
nor an option to purchase, but it is a contract to Petitioners Dignos spouses were owners of a
sell. An option is a contract granting a privilege parcel of land in Opon, Lapu-Lapu City. On June 7,
to buy or sell at a determined price within an 1965, they sold the said parcel of land to
agreed time, the element of specific length or respondent Atilano J. Jabil payable in two
duration was not present in the MOA. installments, the first installment in the sum of
14. In a contract to sell, the title over the subject P12,000.00, was paid and acknowledged by the
property is transferred ti the vendee only upon vendors in the deed of sale (Exh. C) executed in
the full payment of the stipulated favor of respondent. The next installment in the
consideration. Unlike in a contract of sale, the sum of P4,000.00 wasto be paid on or before
title in a contract to sell does not pass the
September 15, 1965.
vendee upon the execution of the agreement or
the delivery of the thing sold.
On November 25, 1965, the Dignos spouses sold
15. This is shown in the proviso found in the MIA
where it states that “title to, ownership, the same land in favor of Luciano Cabigas and
possession and enjoyment of that portion Jovita L. De Cabigas. A deed of absolute sale was
herein sold, shall remain with the vendor until executed and which was registered in the Office of
the full consideration of the sale thereof shall the Register of Deeds.
have been received by the vendor and duly
acknowledged by her in a document duly As the Dignos spouses refused to accept from
executed for said purpose” respondent the balance of the purchase price of
16. From the nature of the contract to sell, vendor, the land, and as respondent discovered the second
Encarnacion Diaz clearly reserved to herself sale made by petitioner to the Cabigas spouses,
ownership and possession of the property until respondent initially brought suit.
full payment of the purchase price, such
payment being a suspensive condition, the
On this motion for reconsideration, petitioners
failure of which is not considered a breach but
contend that the Deed of Sale is a mere contract
simply an event which prevented the obligation
from acquiring obligatory force. to sell and not an absolute sale; that the same is
17. Petitioners argue that their obligation to pay subject to 2 positive suspensive conditions,
the balance had not arisen due to the fact that namely:
the vendor did not notify them that the 1. the payment of the balance of P4,000.00 on or
certificate of title could already be transferred before September 15,1965 and the immediate
in their names. assumption of the mortgage of P12,000.00 with
18. Such argument does not change the nature of the First Insular Bank of Cebu
the contract they entered into. Being a contract 2. title or ownership over the property was
to sell, there was no actual sale until full expressly reserved in the vendor, the Dignos
payment was made by the vendees. However, it spouses until the suspensive condition of full
and punctual payment of the balance of the petitioners sold said land to the Cabigas spouses,
purchase price shall have been met. they were no longer owners of the same and the
sale is null and void.
Further, Petitioners insist that Exhibit "C" is a
private instrument and the absence of a formal 2. No. Under Article 1358 of the Civil Code, it is
deed of conveyance is a very strong indication that required that acts and contracts which have for
the parties did not intend "transfer of ownership their object the extinguishment of real rights over
and title but only a transfer after full payment". immovable property must appear in a public
document.
Issues:
1. Whether or not subject is a deed of absolute The contract of sale being absolute in nature is
sale or a contract to sell governed by Article 1592 of the Civil Code. It is
2. Whether or not there was a valid rescission undisputed that petitioners never notified private
thereof. respondents Jabil by notarial act that they were
rescinding the contract, and neither did they file a
suit in court to rescind the sale. The most that
Held: they were able to show is a letter of Cipriano
1. The contract is a deed of absolute sale. It has Amistad who, claiming to be an emissary of Jabil,
been held that a deed of sale is absolute in nature, informed the Dignos spouses not to go to the
although denominated as a "Deed of Conditional house of Jabil because the latter had no money
Sale," where nowhere in the contract in question is and further advised petitioners to sell the land in
a proviso or stipulation to the effect that title to litigation to another party. As correctly found by
the property sold is reserved in the vendor until the Court of Appeals, there is no showing that
full payment of the purchase price, nor is there a Amistad was properly authorized by Jabil to make
stipulation giving the vendor the right to such extra-judicial rescission for the latter who, on
unilaterally rescind the contract the moment the the contrary, vigorously denied having sent
vendee fails to pay within a fixed period. Amistad to tell petitioners that he was already
waiving his rights to the land in question.
All the elements of a valid contract of sale under
Article 1458 of the Civil Code, are present, such Petitioners laid considerable emphasis on the fact
as: that private respondent Jabil had no money on the
(1) consent or meeting of the minds; stipulated date of payment on September 15,1965
(2) determinate subject matter; and and was able to raise the necessary amount only
(3) price certain in money or its equivalent. by mid-October 1965. It has been ruled, however,
that "where time is not of the essence of the
In addition, Article 1477 of the same Code provides agreement, a slight delay on the part of one party
that "The ownership of the thing sold shall be in the performance of his obligation is not a
transferred to the vendee upon actual or sufficient ground for the rescission of the
constructive delivery thereof." In the absence of agreement" Considering that private respondent
stipulation to the contrary, the ownership of the has only a balance of P4,000.00 and was delayed
thing sold passes to the vendee upon actual or in payment only for one month, equity and justice
constructive delivery thereof. mandate as in the aforecited case that Jabil be
given an additional period within which to
While it may be conceded that there was no complete payment of the purchase price.
constructive delivery of the land sold in the case
at bar, as subject Deed of Sale is a private WHEREFORE, the petition filed is hereby Dismissed
instrument, it is beyond question that there was for lack of merit and the assailed decision of the
actual delivery thereof. As found by the trial court, Court of Appeals is Affirmed in toto.
the Dignos spouses delivered the possession of
the land in question to Jabil as early as March
27,1965 so that the latter constructed thereon
Sally's Beach Resort also known as Jabil's Beach
Resort in March, 1965; Mactan White Beach Resort
on January 15,1966 and Bevirlyn's Beach Resort on
September 1, 1965. Such facts were admitted by
petitioner spouses. It is evident that when
JACINTO v. KAPARAZ ISSUE
Justice Davide, Jr.; May 22, 1992 W/N respondents have the right to rescind the
Contract of Sale v. Contract to Sell agreement? [NO]

FACTS DECISION
CONTRACT OF SALE v. CONTRACT TO SELL
On 11 March 1966, herein petitioners and private Vital to the resolution of the controversy is the
respondents entered into an agreement determination of the true nature of the questioned
(hereinafter referred to as Agreement) under which agreement. Is it a contract of sale or a contract to
the private respondents agreed to sell and convey sell?
to petitioners a portion consisting of six hundred
(600) square meters of a lot located in Matiao, In the latter case [a contract to sell], ownership is
Mati, Davao Oriental and covered by Transfer retained by the seller and is not to pass until full
Certificate of Title No. T- 3694 for a total payment of the price. Such payment is a positive
consideration of P1,800.00. suspensive condition the failure of which is not a
breach, casual or serious, but simply an event that
A downpayment of P800.00 was paid upon prevents the obligation of the vendor to convey
execution of the Agreement. The balance of title from acquiring binding force. In such a
P1,000.00 was to be paid by petitioners on situation, to argue that there was only a casual
installment at the rate of P100.00 a month to the breach is to proceed from the assumption that the
Development Bank of the Philippines (DBP) to be contract is one of absolute sale, where non-
applied to private respondents' loan accounts. payment is a resolutory question.

Upon the execution of the agreement, petitioners On the other hand, since in a contract of sale, the
paid the downpayment of P800.00 and were placed non-payment of the price is a resolutory condition,
in possession of the portion described therein. As the remedy of the seller under Article 1191 of the
to the P1,000.00 which was to be paid directly to Civil Code is to exact fulfillment or to rescind the
the DBP, petitioners claim that they had even made contract. In respect, however, to the sale of
an excess payment of P100.00.cdphil immovable property, this Article must be read
together with Article 1592 of the same Code.
In view of the refusal of private respondents to
execute the deed of sale, petitioners filed against This Article applies to instances where no
them a complaint for specific performance with stipulation for automatic rescission is made
the then Court of First Instance (RTC) of Davao because it says "even though"
Oriental. Respondents on the other hand, alleged
that the sale did not materialize because Jacinto JUDGMENT ON THE MERITS
fail to pay DBP on timely basis as stipulated in In this case, the agreement is a contract of sale.
their agreement. The possession of the portion sold was
immediately delivered to the petitioners. They
On 19 November 1981, the CFI rendered a decision were granted the right to enjoy all the
in favor of the petitioners, declaring them the improvements therein effective from the date of
owners of the property, as it found that the the execution of the agreement. Private
petitioners paid the stipulated installments to the respondents unqualifiedly bound themselves to
DBP.. The CA reversed the CFI’s decision, stating execute the final deed of sale "as soon as the
that petitioners had not fully discharged their settlement or partition of the estate of the
obligation under the agreement considering the deceased Narcisa R. Kaparaz shall have been
delayed payments of P300 and P200 to DBP. In consummated and effected, but not later than
addition, granting that there was no evidence as to March 31, 1967" and only upon full payment of the
who violated the agreement first, then the unpaid portion of the purchase price. The private
contract is deemed extinguished pursuant to the respondents did not reserve unto themselves the
second sentence of Article 1192 of the Civil Code: ownership of the property until full payment of the
If it cannot be determined which of the parties unpaid balance of P1,000.00. Finally, there is no
first violated the contract, the same shall be stipulation giving the private respondents the right
deemed extinguished, and each shall bear his own to unilaterally rescind the contract the moment
damage. the vendee fails to pay within a fixed period.

Petitioners then brought this up to the Supreme Second, it is not denied that petitioners made two
Court. (2) payments in the sums of P200.00 and P300.00
at a time when what remained unsettled under the
agreement was only P400.00. There was then an
excess payment of P100.00. These payments were
made to the DBP which applied them to an
outstanding account of the private respondents.
Private respondents neither complained of the
delay in these payments nor rejected their
application to their account. They were,
undoubtedly, benefited by the application because
it either satisfied their account or correspondingly
reduced it. There was no stipulation as to where
the payments would be allocated to, and therefore
the petitioners were in compliance with payment.

Third, the delay incurred by petitioners was but a


casual or slight breach of the agreement, which
did not defeat the object of the parties in entering
into the agreement. A mere casual breach does not
justify rescission.7

Therefore, the CA erred in declaring the agreement


extinguished pursuant to Art. 1192 of the Civil
Code.

7 Philippine Amusement Enterprises, Inc. vs.


Natividad, 21 SCRA 284 [1967]; Angeles vs.
Calasanz, 135 SCRA 323 [1985].

Das könnte Ihnen auch gefallen