Beruflich Dokumente
Kultur Dokumente
METHOD
1. INTRODUCTION
The penalty provisions for late completion found in construction contracts are for the benefit of the employer.
If the contractor does not meet the agreed completion date (or sectional completion dates) it would be liable
to pay to the employer a fixed amount of money for each day that the project is late either as a liquidated
damage or a penalty (delay damages). It may be that the penalty for such non-completion is capped, however.
In order to avoid liability for liquidated damages or delay damages, the contractor has to prove that the event
or circumstance has delayed completion of the project beyond the agreed date for completion for reasons
that are not of the contractors own making and are admissible as reasons for extension of time in accordance
with the contract.The contractor therefore has to prove that the cause of the delay is an employer cause or a
neutral cause, not a cause attributable to the contractor himself. A neutral cause is a cause which is not the
fault of the employer or contractor (IBC Construction Summer Law School 2010, Specialist Workshop – Time
and Delay: The basics under the Common Law and Standard forms, Patrick Holmes, Macfarlanes LLP). In
achieving this object, the contractor must employ a delay analysis methodology acceptable to the engineer,
adjudicator or arbitrator as the case may be. There are 5 commonly used delay analysis methods which are as
follows:
• Impacted-as planned method;
• Time impact analysis method;
• Collapsed as-built or ‘but-for’ analysis method;
• Snapshot/windows/time slice analysis method; and
• As-planned versus as-built windows analysis method (David Barry, Society of Construction Law, January
2005, D95) .
In this article the author examines only the first two methods of delay analysis. The remainder will be analysed
in a later article.
4. CONCLUSION
In order to achieve the most accurate result of the time impact analysis method, detailed as-built data is
required, and contracts therefore require contemporaneous notice and record documents supporting
the contractor’s claim for an EOT. This means that the contractor has to have accurate records on site to
substantiate a claim for an EOT and that it must prove, on a balance of probabilities that the event has delayed
completion. Jargon such as ‘dynamic schedule calculations’ and ‘prospective technique’ aside, the following
was said by Lord Drummond Young in City Inn v Shepherd Construction, 2007, CSOH 190 and [2008] 1 BLR “It
seems to me that it is a question of fact in any given case whether a relevant event has caused or is likely to
cause a delay to the works beyond the completion date…”.