Sie sind auf Seite 1von 8

I.

EXCAVATION AND BACKFILL

INPUT AREA TO BE REMEDIATED

Area No. length(ft) width(ft)

1 672,400.00 7.00
2
3
4
5
6
7
Total area

INPUT THE DISTANCE BETWEEN EXCAVATION SITE AND DISPOSAL SITE


Milage
3 mile

RESULTS
Activity Maximum rate
Excavation and loading $10.67 /cu yd
Transportation of contaminated soil $8.75 /cu yd
Disposal of contaminated soil $13.13 /cu yd
Backfill and compaction (purchase, transport, compact 7.66 /cu yd
backfill material)
Remove and dispose of asphalt or concrete $2.19 /sq f
Milage over 40 miles $0.11 /mile/cu yd

Note: 11¢/mile/cubic yard for each mile over 40 miles


from excavation site to disposal site, not to exceed 200
miles total one-way.
Area of the site Volume of soil
thickness(ft)
remediated (square ft) remediated (cu yd)

4,706,800.00 6.00 1,045,955.56


0 0

4706800 Total volume 1045955.55555556

Area/volume/distance Cost
1,045,955.56 cu yd 11,160,345.78
1,045,955.56 cu yd 9,152,111.11
1,045,955.56 cu yd 13,733,396.44

1,045,955.56 cu yd 8,012,019.56

6.00 sq f 13.14
- mile*cu yd -

Total Cost $42,057,886.03


II CAPPING WITH CLEAN SOIL

INPUT AREA TO BE REMEDIATED


Area of the site
Area No. length(ft) width(ft) remediated (square ft)

1 125 55 6875
2 145 100 14500
3
4
5
6
7
Total area 21375

RESULTS
Name price soil volume
top soil $33.50 /ton $3,166.67

Note: delivery included


1.4 ton=1 cu yd
Volume of soil
thickness(ft) remediated (cu yd)

4 1018.5185185185
4 2148.1481481482

Total volume 3166.6666666667

soil volume Total cost


cu yd $75,773.81
Asphaut Removal

ACTIVITY MAXIMUM RATE Area(sq f) Total Cost


Remove and dispose of asphalt or concrete $2.19 /sq f 1 $2.19
COST COMPARISON BETWEEN DIFFERENT REMEDIATION OPTIONS
Options Cost
Excavation and backfill $42,057,886.03
Capping with clean soil $75,773.81
RATES FOR ACTIVITIES ASSOCIATED WITH THE EXCAVATION, TRANSPORTATION AND DISPOSAL OF PETROLEUM-CONTAMIN
ACTIVITY MAXIMUM RATE
Excavation and loading $10.67 /cu yd
Transportation of contaminated soil $8.75 /cu yd
Disposal of contaminated soil $13.13 /cu yd
Backfill and compaction (purchase, transport, compact backfill materia $7.66 /cu yd
Backfill and compaction (clean excavated material) $5.07 /cu yd
Remove and dispose of asphalt or concrete $2.19 /sq f
Replace asphalt $2.74 /sq f
Replace concrete $4.92 /sq f
Source: http://oil.cdle.state.co.us/oil/fund/consultant/cost%20guidelines/excvdisp.asp