PRESENTASI KUNJUNGAN PROYEK AEON MALL SENTUL

GROUP 1 - OPB PT. PP XXXVII


PROJECT OVERVIEW
PROJECT OVERVIEW

Project Name : AEON Mixed Use Sentul City

Address : MH. Thamrin Street, Bogor, West Java

Contract Type : Lump Sum Fixed Price

Contract Value : Rp 758.890.000.000,00

Down Payment : 10%

Retention : 5%

Time of Project : 880 Calendar Days

Area of Project : 8 ha

GROUP 1 - OPB PT. PP XXXVII


SITE PLAN FLOW CHART

SITE PLAN
FUNCTION

Project Transportation Materials Position and Function Cost

Mechanism / method
Neccesary of project Total area that need Mechanism of Can predict the cost
of the project Position of materials Place of temporary
transportation to placement the transfering materials of Project operational
transportation building is setting well
materials to the site plan
and can give the
optimum function

GROUP 1 - OPB PT. PP XXXVII


SITE PLAN FLOW CHART

START

Enviroment observation

Design project site plan


Area and building

Accessibility
Determine the temporary project facilities

Study & understand


Evaluate the position and function
the scop of work item
Change the position No
Yes

Exixtence Building
Construction project appropriate with PT.PP plan and standart

Work Method
FINISH

GROUP 1 - OPB PT. PP XXXVII


TOWER CRANE

Sumber: http://www.selectplanthire.com
GROUP 1 - OPB PT. PP XXXVII
SITE PLAN FLOW CHART

4 5 6 7 8

3 2 1

GROUP 1 - OPB PT. PP XXXVII


SITE PLAN ON THE PROJECT

1 : Site Office
2 : Barracks
6 3 : Temporary Service 1
9 4 : Security
5 : Gate for Labor
6 : Gate for Equipment
7 : Tower Crane
5
8 : Access for Worker
10
8 3
4

11 1
2
7

9 : Access for Equipment


10 : Temporary Service 2
11 : Meeting Point
GROUP 1 - OPB PT. PP XXXVII
Foundation

Type of Foundation : Bore Pile


Raft Foundation
Soil Condition : Clay Silt

Reason :

“The condition of soil is very easy to be change. The soil will be cracked if
exposed by heat and it will be sliding if poured by rain. So it will be hard to find
the hard soil. That’s why bore pile and raft foundation was decided for this
project“

GROUP 1 - OPB PT. PP XXXVII


Advantage and Disadvantage
Bore Pile

• Advantage
1. Less vibrations, so recommended to preserve the safety of the
adjoining structure.
2. Could be use for poor soil condition

• Disadvantage
1. Installation of cast-in-situ piles requires careful supervision
2. The method is quite cumbersome if compared with concrete spun
pile.

GROUP 1 - OPB PT. PP XXXVII


Advantage and Disadvantage
Raft Foundation

• Advantage
1. Increase the efficiency of progress
2. It can cope with mixed or poor ground condition.
3. It reduces differential settlement.

• Disadvantage
1. Mat foundation requires specific treatment for point loads.
2. Crack occurs if not treated properly.

GROUP 1 - OPB PT. PP XXXVII


Foundation

Determination of
Next Point Point by Surveyor

Concrete Set Up
Casting Equipment

Bore Pile
Installation of Pre Boring
Reinforcement Process

Installation of
Boring Process
Chasing

GROUP 1 - OPB PT. PP XXXVII


Foundation

Intallation the
reinforcement

Finish the mass Intallation the


concrete formwork
Raft Foundation
(Mass Concrete)

Control the
Start The Mass
temperature of
Concrete Process
concrete every 1 layer

GROUP 1 - OPB PT. PP XXXVII


RETAINING WALL

GROUP 1 - OPB PT. PP XXXVII


RETAINING WALL

Retaining walls are relatively rigid walls used for


supporting the soil mass laterally so that the soil can
be retained at different levels on the two sides.

GROUP 1 - OPB PT. PP XXXVII


SOLIDER PILE

Soldier pile is used as a retaining


structural system that support
excavation work to prevent it from
collapsing.
On this project, soldier pile are used
at the west side of the project
because there is an existing building
next to it.
GROUP 1 - OPB PT. PP XXXVII
SOLIDER PILE METHOD

Soldier pile Preparing work

Survey and marking


Lateral load pile test

Waterproofing
Ok?
Reinforcement bar

Caping beam work


Formwork

Laging panel work Concrete work

GROUP 1 - OPB PT. PP XXXVII


Basement slab
Coloumn Method of Work

START

Determination of Coloumn As

Coloumn reinforcement installation

Sepatu Kolom Installation

Formwork installation

Adjustment

Inspection
NOT OK
OK

Concrete casting

Formwork Dismantling

CURING

GROUP 1 - OPB PT. PP XXXVII


Coloumn Method of Work

• Determination of Coloum
As
Coloumn As is determinated using total
station according to shopdrawing and
measured from nearest benchmark
(BM)

• Coloumn reinforcement
Installation
After coloumn reinforcement steel arranged
in the workshop, it will be installed to the
detereminated place with TC help. Then it will
be tied with

• Sepatu kolom Installation


Used for coloumn marking position and
formwork temporary holder

GROUP 1 - OPB PT. PP XXXVII


Formwork Installation

• Formwork Installation Hollow frame


After sepatu coloumn is fixed to its position, the
formwork will be placed to the position which have
been marked by the sepatu kolom then tied the
formwork with T rod and adjust the vertivicality of
formwork with pushprop
Hollow frame

plywood
GROUP 1 - OPB PT. PP XXXVII
Inspection

Re-check the dimension,quantity and position steel reinforcement

Check moulding area cleanliness

Check formwork condition

Make sure the formwok is well oiled to make sure its not stuck to the concrete

GROUP 1 - OPB PT. PP XXXVII


Concrete Casting

Apply super
Check concrete Concrete lifting
bonding
quality with TC
agent

cast in situ

Vibration

GROUP 1 - OPB PT. PP XXXVII


Formwork Dismantling

Loosen up T-rod

Remove push
pull

Put the
formwork to the
workshop

• Smooth edge
Quality control
• Uniform color
• No segregation

GROUP 1 - OPB PT. PP XXXVII


Curing

Spray the curing


Prepare the Wet the
compound to
equipment and coloumn with
the coloumn
ingredients water
surface

GROUP 1 - OPB PT. PP XXXVII


Beam work method

Beam formwork
installation

GROUP 1 - OPB PT. PP XXXVII


Framework panel and scaffolding installation

• Uitzet Survey purpose is to determine the coordinate of beam according to shopdrawing


• Framework panel installation purpose is to shape the beam based on dimension of the
design
• Scaffolding installation purpose is to support the structure until the strength of the
structure has complied.

GROUP 1 - OPB PT. PP XXXVII


Rebar Installation

Rebar that has lifted then


Rebar production start Lifted with tower crane putted in upside beam Installing decking concrete
on the fabrication for beam cover
into the location formwork and inserted
down into the formwork

GROUP 1 - OPB PT. PP XXXVII


Clearance and Concrete Casting

• Casted area are cleared by air compressor tool


• Pouring concrete into the casted area then the concrete are compacted by vibrator

GROUP 1 - OPB PT. PP XXXVII


Curing and Formwork dismantling

• Casted area are cleared by air compressor tool


• After the strength of concrete are complied , dismantling the formwork of the beam

GROUP 1 - OPB PT. PP XXXVII


S H E (SAFETY, HEALTH, and ENVIRONMENT)

A Process consist of Planning,

SHE
Organizing, and Action to reach
the goals in Safety, Health and
Environment of a Project

GROUP 1 - OPB PT. PP XXXVII


GOALS

Zero Lost Time Injury

Implementing the SHE Management

Implementing the Standard of Safety Equipment

Quick Response Report SHE

SHE Skill Training

SHE Patrol and SHE Inspection

Environmental Control
GROUP 1 - OPB PT. PP XXXVII
SHE POLICY

1 SAFETY INDUCTION 4 SHE TALK

3 SHE MEETING

2 SAFETY PATROL AND INSPECTION 5 SHE TRAINING

GROUP 1 - OPB PT. PP XXXVII


SOME OF THE SHE PROCEDURE IN THE PROJECT
SOME OF THE SHE IMPLEMENTATION IN PROJECT

GROUP 1 - OPB PT. PP XXXVII


INNOVATIONS AND GREEN BUILDING APPLICATIONS

CUTTING LIST WIREMESH

BIM SOFTWARE TO CALCULATE REBAR QUANTITY

BIM SOFTWARE TO COORDINATE WITH THE PLANNER

FINAL CAD FOR MONITORING WORKS

HALF SLAB METHOD

FORMWORK USING PCH SYSTEM

MEVA FORMWORK

GREEN BUILDING IMPLEMENTATIONS

GROUP 1 - OPB PT. PP XXXVII


CUTTING LIST WIREMESH

USING CUTTING TOOLS USING MACHINE

LONGER TIME BECAUSE USING MAN


FASTER
POWER

NEED MORE TIME TO PRECISE THE


EFFICIENCY AND QUALITY
CUTTING

CHEAPER EXPENSIVE BUT EFFECTIVE

GROUP 1 - OPB PT. PP XXXVII


BIM SOFTWARE TO CALCULATE REBAR QUANTITY

USING USUAL PROGRAM (ex. MS EXCELL)


• USING SOME PROGRAM (EXCELL, WORD, AUTOCAD)
• NEED MORE TIME TO FIX THE FALSE CALCULATION

USING BIM SOFTWARE (REVIT)


• ONLY USING ONE PROGRAM
• EFFICIENCY
• THE COST OF BUYING THE SOFTWARE IS EXPENSIVE
• REDUCE DIRECT SCHEDULE
• INCREASE PRODUCTIVITY
• REDUCE DIRECT COST

GROUP 1 - OPB PT. PP XXXVII


BIM SOFTWARE TO COORDINATE WITH THE PLANNER

USING DIRECT COORDINATION


• SPENT MORE COST FOR TRANSPORTATION AND COMMUNICATION
• NEED MORE TIME TO CALL THE PLANNER AND TO EPLAIN THE
CHANGE ORDER

USING BIM SOFTWARE (REVIT)


• ONLY USING ONE PROGRAM TO ADMIT THE CHANGE ORDER EVEN
FROM LONG DISTANCE
• EFFICIENCY
• THE COST OF BUYING THE SOFTWARE IS EXPENSIVE BUT COULD BE
USE FOR FORWARD PROJECT

GROUP 1 - OPB PT. PP XXXVII


FINAL CAD FOR MONITORING WORKS

USING DIRECT COORDINATION


• SPENT MORE COST FOR TRANSPORTATION AND COMMUNICATION
• NEED MORE TIME TO CALL THE PLANNER AND TO EXPLAIN THE CHANGE
ORDER

USING FINAL CAD


• GOOD MANAGEMENT (STRUCTURE, ARCHITECTURAL, MECHANICAL AND
PLUMBING
• EASY TO CONTROL QUALITY AND TO COMMUNICATE WITH OTHER CO-
WORKERS BY USING SMARTPHONE
• CENTRALIZE THE WORKSHEET AND THE INVENTORY

GROUP 1 - OPB PT. PP XXXVII


HALF SLAB METHOD

USING CONVENTIONAL SLAB USING HALF SLAB


• SPENT MORE COST FOR FORMWORK • FAST INSTALATION
• NEED MORE TIME TO INSTAL FORMWORK • ACT AS PERMANENT FORMWORK, REDUCE
ERECTING AND FORMWORK STRIKING TIME
• SIZE CAN BE EASILY CUSTOMIZED TO SUIT
STRUCTURAL AND ARCHITECTURAL
REQUIREMENTS.

GROUP 1 - OPB PT. PP XXXVII


FORMWORK USING PCH SYSTEM

USING CONVENTIONAL FORMWORK USING PCH SYSTEM


FAST INSTALATION
LESS WORKERS
TOUGH MATERIAL ( QUALITY AND LOAD CAPACITY)
SPENT MORE COST FLEXIBLE USE FOR HIGH RISE BUILDING (COULD REACH
5M HIGH)
NEED MORE TIME TO INSTAL FORMWORK
WITHOUT USING FRAME FOR BEAM FORMWORK

GROUP 1 - OPB PT. PP XXXVII


FORMWORK USING MEVA

USING CONVENTIONAL FORMWORK USING MEIVA


• SPENT MORE COST • FLEXIBLE HEIGHTS, WIDTHS AMD FORMING METHOD
• NEED MORE TIME TO INSTAL FORMWORK • LESS SPACE NEEDED BECAUSE THE PANELS COULD BE
• NEED MORE SPACE TO INSTAL AND REPLACE STRIPPED AND LOWERED BY 19 CM

GROUP 1 - OPB PT. PP XXXVII


GREEN BUILDING

REUSABLE MATERIALS
• USING WASTED
CONSTRUCTION MATERIALS
FOR STOCK CAR STOPPER
• USING WASTED STEEL REBAR
FOR SIMPLE COLUMN
• USING WASTED STEEL REBAR
TO BUILD TEMPORALLY OFFICE
WASTED MATERIALS AND SUPPORTING TOOLS

•REDUCING WASTE IN THE PROJECT


•REDUCING THE COST FOR SIMPLE
STRUCTURE (ex. USING WASTED STEEL REUSABLE
REBAR FOR SIMPLE COLUMN)
USING WASTED STEEL
REBAR FOR SIMPLE
COLUMN
USING WASTED STEEL
REBAR TO BUILD
TEMPORALLY OFFICE
WASTED STEEL REBAR AND SUPPORTING TOOLS

•REDUCING WASTE IN THE PROJECT


•REDUCING THE COST FOR SIMPLE
STRUCTURE (ex. USING WASTED STEEL
REBAR FOR SIMPLE COLUMN)

GROUP 1 - OPB PT. PP XXXVII


GROUP 1 - OPB PT. PP XXXVII