‐ Normally 7% to 10% of the cost of materials is the cost of overhead.

10.5 Permits – show the plans to the municipal electrical engineer or his assistant and 
request for an estimate. Add 5% to cover the exingencies.

10.6 a. the sum cost as computed in 10.1 and 10.5 is to be multiplied by 0.03 to get the 
contractor’s tax.

b. Add the contractor’s tax to the sum of sections 10.1 to 10.5 and round off. This will be your 
bid price.

TERM TEST

1. A school classroom with general dimension of 24 x 30 feet is lighted with 10 fluorescent lamp 4F 40 T12
WW rapid start lamp. Calculate the initial and maintaned illumination in foot candle and lux, assuming
that the coefficient of utilization is 0.35 and the maintenance factor is 0.70.

2. An office room with general dimension of 8 x 20 meters is to be lighted at an average maintaned foot
candle of 50. How many 3 lamp fixtures of 120 centimeterslong F40 T12 WW rapid start fluorescent
lamps are required assuming 0.38 cu and 0.75 mf?