Beruflich Dokumente
Kultur Dokumente
Chapter 12
Dependent vs. Independent Demand
• Independent demand: Demand for end items.
A Dependent Demand
(component parts)
B(4) C(2)
Demand
Demand
“Lumpy” demand
Stable demand
Time Time
Amount on hand
Amount on hand
Safety stock
Time Time
Material requirements planning (MRP)
Assembly
Subassembly
Fabrication
Procurement
1 2 3 4 5 6 7 8 9 10
Time period (weeks)
MRP Inputs: Bill-of-Materials
3
Example 1
Example 1
• Using the information above to do the
follows:
a) Determine the quantities of B, C, D, E, and F
needed to assemble one X.
Solution to Example 1
a) X X :1
B : 2 1 2 B(2) C C : 11 1
D : 3 16 48 E :0 F :0
E : 116 16
8 D(3) E E(2) F(2)
40 • Thus, given the amounts of on-hand
E(4) inventory, 10 Xs will require
E : 4 40 160 • B: 16 C: 0
60
• D: 40 F: 0
100
• E: 116 (=16+100)
Low-Level Coding
• Low-level coding
– Restructuring the bill of materials so that multiple
occurrences of a component all coincide with the
lowest level at which the component occurs
Level 0 X
Level 1 B(2) C
1 A B C D E
F E G H
2
3 E
MRP Inputs: Inventory Records
• Inventory records
– Includes information on the status of each item by
time period, called time buckets
• Information about
– Gross requirements
– Scheduled receipts
– Expected amount on hand
• Other details for each item such as
– Supplier
– Lead time
– Lot size policy
– Changes due to stock receipts and withdrawals
– Canceled orders and similar events
Assembly Time Chart
Example
Seat
Front legs (2)
Chair
Back
Legs (2) Cross Side Cross Supports
bar rails (2) bar (3)
Assembly Time Chart
• When to order
• Allowance for the lead time
• How much to order
• How often to order
Items Already On Order
Purchase Orders Outstanding or Open
Orders
Open Orders Open Orders
(Purchased Items) (Manufactured Items)
• Items being ordered • Items being
• Items being processed by
processed by production
suppliers • Items waiting for
components
• Items in transport
• Items waiting for
• Items being processing
inspected by • Items being inspected
38
receiving.
Lead Times
• Primary Outputs
– Planned orders
• A schedule indicating the amount and timing of
future orders
– Order releases
• Authorizing the execution of planned orders
– Changes
• Revisions of the dates or quantities, or the
cancellation of orders
MRP Outputs: Secondary
• Secondary Outputs
– Performance-control reports
• Evaluation of system operation, including deviations from
plans and cost information
– e.g., missed deliveries and stockouts
– Planning reports
• Data useful for assessing future material requirements
– e.g., purchase commitments
– Exception reports
• Data on any major discrepancies encountered
– e.g., late and overdue orders, excessive scrap rates,
requirements for nonexistent parts
MRP Processing
Week Number 0 1 2 3 4 5 6 7 8
Item:
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
MRP Processing
– Gross requirements: Total expected
demand for an item or raw material in a time
period.
– Scheduled receipts: Open orders scheduled
to arrive from vendors or elsewhere in the
pipeline by the beginning of a period.
– Projected on hand: Expected amount of
inventory that will be on hand at the beginning
of each time period:
Scheduled receipts + inventory carried
forward
MRP Processing
A C
B D D(2) F
Projected on hand
Net requirements 80
Planned-order receipts 80
Planned-order releases 80
times 1
Solution to Example -- MRP for Item C
Week Number 0 1 2 3 4 5 6
Quantity of A 80
Quantity of C 50
Projected on hand
Net requirements 50
Planned-order receipts 50
Planned-order releases 50
times 2
Solution to Example -- MRP for Item D
80 50
Item A Item C
times 1 times 2
D LT=1 week 1 2 3 4 5 6
Gross requirements 80 100
Scheduled receipts
Chair
Back
Legs (2) Cross Side Cross Supports
bar rails (2) bar (3)
Assembly Time Chart
Chairs
LT = 1 week Week
1 2 3 4 5 6 7
Planned order receipts 0 0 0 0 500 400 400
Planned order releases 0 0 0 500 400 400 0
Seat
LT = 2 weeks Week
Minimum Order = 1 1 2 3 4 5 6 7
Gross Requirements 0 0 0 500 400 400 0
Scheduled Receipts
Projected On Hand 0 0 0 0 0 0 0 0
Net Requirements 500 400 400
Planned Receipts 500 400 400
Planned Order 500 400 400
Where do the gross requirements come from?
Seat
LT = 2 weeks Week
Minimum Order = 1 1 2 3 4 5 6 7
Gross Requirements 0 0 0 500 400 400 0
Scheduled Receipts
Projected On Hand 0 0 0 0 0 0 0 0
Net Requirements 500 400 400
Planned Receipts 500 400 400
Planned Order Releases 500 400 400
Leg Assembly
LT = 1 week Week
Going Minimum order = 1000 1 2 3 4 5 6 7
Back Assembly
LT = 1 week Week
Multiple of 250 1 2 3 4 5 6 7
Gross Requirements 0 0 0 500 400 400 0
Scheduled Receipts 250
Projected On Hand 0 0 250 250 250 0 100 200
Net Requirements 250 400 300
Planned Receipts 250 500 500
Planned Order Releases 250 500 500
Leg Assembly
LT = 1 week Week
Minimum Order = 1000 1 2 3 4 5 6 7
Moving from “Level 1” items
to “Level 2” items . . .
Leg Assem bly
LT = 1 week Week
Minimum Order = 1000 1 2 3 4 5 6 7
Gross Requirements 0 0 0 500 400 400 0
Scheduled Receipts
Projected On Hand 25 25 25 25 25 525 125 725
Net Requirements 475 275
Planned Receipts 1000 1000
Planned Order 1000 1000
Legs
LT = 2 weeks Week
Minimum Order = 1 1 2 3 4 5 6 7
Gross Requirements 0 0 2000 0 2000 0 0
Scheduled Receipts
Projected On Hand 0 0 0 0 0 0 0 0
Net Requirements 2000 2000
Planned Receipts 2000 2000
Planned Order 2000 2000
chair
schedule?
Example MRP
Shutter
Wood
Frames (2)
sections (4)
Example MRP (cont.)
Lot-Sizing in MRP
Legs
LT = 2 weeks Week
Minimum Order = 1 1 2 3 4 5 6 7
Gross Requirements 0 0 2000 0 2000 0 0
Scheduled Receipts
Projected On Hand 0 0 0 0 0 0 0 0
Net Requirements 2000 2000
Planned Receipts 2000 2000
Planned Order 2000 2000
Legs
LT = 2 weeks Week
Minimum Order = 1 1 2 3 4 5 6 7
Gross Requirements 0 0 950 800 800 0 0
Scheduled Receipts
Projected On Hand 0 0 0 0 0 0 0 0
Net Requirements 950 800 800
Planned Receipts 950 800 800
Planned Order 950 800 800