Sie sind auf Seite 1von 8

Real Contracts IS PERFECTED ONLY UPON DELIVERY OF THE

OBJECT OF THE CONTRACT; CASE AT BAR. — A loan


[G.R. No. 133632. February 15, 2002.] contract is not a consensual contract but a real contract.
It is perfected only upon the delivery of the object of the
BPI INVESTMENT CORPORATION, petitioner, vs. contract. Petitioner misapplied Bonnevie. The contract in
HON. COURT OF APPEALS and ALS MANAGEMENT & Bonnevie declared by this Court as a perfected
DEVELOPMENT CORPORATION, respondents. consensual contract falls under the first clause of Article
1934, Civil Code. It is an accepted promise to deliver
SYNOPSIS
something by way of simple loan. In Saura Import and
The appellate court affirmed the judgment of the Export Co. Inc. vs. Development Bank of the Philippines,
Regional Trial Court of Pasig City in a case for 44 SCRA 445, petitioner applied for a loan of P500,000
foreclosure of mortgage by petitioner BPI Investment with respondent bank. The latter approved the
Corporation (BPIIC for brevity) against private application through a board resolution. Thereafter, the
respondents ALS Management and Development corresponding mortgage was executed and registered.
Corporation and Antonio K. Litonjua, consolidated with However, because of acts attributable to petitioner, the
Civil Case No. 52093, for damages with prayer for the loan was not released. Later, petitioner instituted an
issuance of a writ of preliminary injunction by the action for damages. We recognized in this case, a
private respondents against said petitioner. The trial perfected consensual contract which under normal
court held that private respondents were not in default circumstances could have made the bank liable for not
in the payment of their monthly amortization, hence, the releasing the loan. However, since the fault was
extrajudicial foreclosure conducted by BPIIC was attributable to petitioner therein, the court did not
premature and made in bad faith. In the instant petition, award it damages. A perfected consensual contract, as
petitioner contended that the Court of Appeals erred in shown above, can give rise to an action for damages.
ruling that because a simple loan is perfected upon the However, said contract does not constitute the real
delivery of the object of the contract, the loan contract in contract of loan which requires the delivery of the object
this case was perfected only on September 13, 1982. of the contract for its perfection and which gives rise to
Petitioner claimed that a contract of loan is a consensual obligations only on the part of the borrower. In the
contract, and a loan contract is perfected at the time the present case, the loan contract between BPI, on the one
contract of mortgage is executed conformably with the hand, and ALS and Litonjua, on the other, was perfected
Court's ruling in Bonnevie v. Court of Appeals. In the only on September 13, 1982, the date of the second
present case, the loan contract was perfected on March release of the loan. Following the intentions of the
31, 1981, the date when the mortgage deed was parties on the commencement of the monthly
executed, hence, the amortization and interests on the amortization, as found by the Court of Appeals, private
loan should be computed from said date. HaAISC respondents' obligation to pay commenced only on
October 13, 1982, a month after the perfection of the
The Supreme Court affirmed the judgment of the Court contract.
of Appeals with modification as to the damages. The
Court ruled that a loan contract is not a consensual 2. ID.; ID.; ID.; INVOLVES RECIPROCAL
contract but a real contract. It is perfected only upon the OBLIGATION WHEREIN THE OBLIGATION OR PROMISE
delivery of the object of the contract. Petitioner OF EACH PARTY IS THE CONSIDERATION FOR THAT
misapplied Bonnevie. The contract in Bonnevie declared OF THE OTHER. — We also agree with private
by the Court as a perfected consensual contract falls respondents that a contract of loan involves a reciprocal
under the first clause of Article 1934, Civil Code. It is an obligation, wherein the obligation or promise of each
accepted promise to deliver something by way of simple party is the consideration for that of the other. As
loan. In the present case, the loan contract between BPI, averred by private respondents, the promise of BPIIC to
on the one hand, and ALS and Litonjua, on the other, extend and deliver the loan is upon the consideration
was perfected only on September 13, 1982, the date of that ALS and Litonjua shall pay the monthly
the second release of the loan. Following the intentions amortization commencing on May 1, 1981, one month
of the parties on the commencement of the monthly after the supposed release of the loan. It is a basic
amortization, as found by the Court of Appeals, private principle in reciprocal obligations that neither party
respondents' obligation to pay commenced only on incurs in delay, if the other does not comply or is not
October 13, 1982, a month after the perfection of the ready to comply in a proper manner with what is
contract. incumbent upon him. Only when a party has performed
his part of the contract can he demand that the other
SYLLABUS party also fulfills his own obligation and if the latter
fails, default sets in. Consequently, petitioner could only
1. CIVIL LAW; CONTRACTS; LOAN; NOT A demand for the payment of the monthly amortization
CONSENSUAL CONTRACT BUT A REAL CONTRACT; IT after September 13, 1982 for it was only then when it
complied with its obligation under the loan contract. Village, Muntinlupa. Said house and lot were mortgaged
Therefore, in computing the amount due as of the date to AIDC to secure the loan. Sometime in 1980, Roa sold
when BPIIC extrajudicially caused the foreclosure of the the house and lot to private respondents ALS and
mortgage, the starting date is October 13, 1982 and not Antonio Litonjua for P850,000. They paid P350,000 in
May 1, 1981. HESCcA cash and assumed the P500,000 balance of Roa's
indebtedness with AIDC. The latter, however, was not
3. ID.; DAMAGES; NO BASIS FOR AWARD OF willing to extend the old interest rate to private
MORAL AND EXEMPLARY DAMAGES; NOMINAL respondents and proposed to grant them a new loan of
DAMAGES AWARDED TO RESPONDENTS BY REASON P500,000 to be applied to Roa's debt and secured by the
OF PETITIONER'S NEGLIGENCE. — As admitted by same property, at an interest rate of 20% per annum
private respondents themselves, they were irregular in and service fee of 1% per annum on the outstanding
their payment of monthly amortization. Conformably principal balance payable within ten years in equal
with our ruling in SSS, we can not properly declare monthly amortization of P9,996.58 and penalty interest
BPIIC in bad faith. Consequently, we should rule out the at the rate of 21% per annum per day from the date the
award of moral and exemplary damages. However, in our amortization became due and payable.
view, BPIIC was negligent in relying merely on the
entries found in the deed of mortgage, without checking Consequently, in March 1981, private respondents
and correspondingly adjusting its records on the amount executed a mortgage deed containing the above
actually released to private respondents and the date stipulations with the provision that payment of the
when it was released. Such negligence resulted in monthly amortization shall commence on May 1, 1981.
damage to private respondents, for which an award of
nominal damages should be given in recognition of their On August 13, 1982, ALS and Litonjua updated Roa's
rights which were violated by BPIIC. For this purpose, arrearages by paying BPIIC the sum of P190,601.35.
the amount of P25,000 is sufficient. This reduced Roa's principal balance to P457,204.90
which, in turn, was liquidated when BPIIC applied
DECISION thereto the proceeds of private respondents' loan of
P500,000.
QUISUMBING, J p:
On September 13, 1982, BPIIC released to private
This petition for certiorari assails the decision dated respondents P7,146.87, purporting to be what was left of
February 28, 1997, of the Court of Appeals and its their loan after full payment of Roa's loan.
resolution dated April 21, 1998, in CA-G.R. CV No.
38887. The appellate court affirmed the judgment of the In June 1984, BPIIC instituted foreclosure proceedings
Regional Trial Court of Pasig City, Branch 151, in (a) against private respondents on the ground that they
Civil Case No. 11831, for foreclosure of mortgage by failed to pay the mortgage indebtedness which from May
petitioner BPI Investment Corporation (BPIIC for brevity) 1, 1981 to June 30, 1984, amounted to Four Hundred
against private respondents ALS Management and Seventy Five Thousand Five Hundred Eighty Five and
Development Corporation and Antonio K. Litonjua, 1 31/100 Pesos (P475,585.31). A notice of sheriff's sale
consolidated with (b) Civil Case No. 52093, for damages was published on August 13, 1984.
with prayer for the issuance of a writ of preliminary
injunction by the private respondents against said On February 28, 1985, ALS and Litonjua filed Civil Case
petitioner. SAHaTc No. 52093 against BPIIC. They alleged, among others,
that they were not in arrears in their payment, but in
The trial court had held that private respondents were fact made an overpayment as of June 30, 1984. They
not in default in the payment of their monthly maintained that they should not be made to pay
amortization, hence, the extrajudicial foreclosure amortization before the actual release of the P500,000
conducted by BPIIC was premature and made in bad loan in August and September 1982. Further, out of the
faith. It awarded private respondents the amount of P500,000 loan, only the total amount of P464,351.77
P300,000 for moral damages, P50,000 for exemplary was released to private respondents. Hence, applying the
damages, and P50,000 for attorney's fees and expenses effects of legal compensation, the balance of P35,648.23
for litigation. It likewise dismissed the foreclosure suit should be applied to the initial monthly amortization for
for being premature. the loan.

The facts are as follows: On August 31, 1988, the trial court rendered its
judgment in Civil Case Nos. 11831 and 52093, thus:
Frank Roa obtained a loan at an interest rate of 16¼%
per annum from Ayala Investment and Development WHEREFORE, judgment is hereby rendered in favor of
Corporation (AIDC), the predecessor of petitioner BPIIC, ALS Management and Development Corporation and
for the construction of a house on his lot in New Alabang Antonio K. Litonjua and against BPI Investment
Corporation, holding that the amount of loan granted by This fact constituted sufficient ground for moral
BPI to ALS and Litonjua was only in the principal sum of damages in favor of private respondents.
P464,351.77, with interest at 20% plus service charge of
1% per annum, payable on equal monthly and The motion for reconsideration filed by petitioner BPIIC
successive amortizations at P9,283.83 for ten (10) years was likewise denied, hence this petition, where BPIIC
or one hundred twenty (120) months. The amortization submits for resolution the following issues:
schedule attached as Annex "A" to the "Deed of
Mortgage" is correspondingly reformed as aforestated. I. WHETHER OR NOT A CONTRACT OF LOAN IS A
CONSENSUAL CONTRACT IN THE LIGHT OF THE RULE
The Court further finds that ALS and Litonjua suffered LAID DOWN IN BONNEVIE VS. COURT OF APPEALS,
compensable damages when BPI caused their 125 SCRA 122.
publication in a newspaper of general circulation as
defaulting debtors, and therefore orders BPI to pay ALS II. WHETHER OR NOT BPI SHOULD BE HELD
and Litonjua the following sums: LIABLE FOR MORAL AND EXEMPLARY DAMAGES AND
ATTORNEY'S FEES IN THE FACE OF IRREGULAR
a) P300,000.00 for and as moral damages; PAYMENTS MADE BY ALS AND OPPOSED TO THE
RULE LAID DOWN IN SOCIAL SECURITY SYSTEM VS.
b) P50,000.00 as and for exemplary damages; COURT OF APPEALS, 120 SCRA 707.

c) P50,000.00 as and for attorney's fees and On the first issue, petitioner contends that the Court of
expenses of litigation. Appeals erred in ruling that because a simple loan is
perfected upon the delivery of the object of the contract,
The foreclosure suit (Civil Case No. 11831) is hereby the loan contract in this case was perfected only on
DISMISSED for being premature. September 13, 1982. Petitioner claims that a contract of
loan is a consensual contract, and a loan contract is
Costs against BPI. perfected at the time the contract of mortgage is
executed conformably with our ruling in Bonnevie v.
SO ORDERED. 2
Court of Appeals, 125 SCRA 122. In the present case,
Both parties appealed to the Court of Appeals. However, the loan contract was perfected on March 31, 1981, the
private respondents' appeal was dismissed for non- date when the mortgage deed was executed, hence, the
payment of docket fees. amortization and interests on the loan should be
computed from said date.
On February 28, 1997, the Court of Appeals
promulgated its decision, the dispositive portion reads: Petitioner also argues that while the documents showed
that the loan was released only on August 1982, the loan
WHEREFORE, finding no error in the appealed decision was actually released on March 31, 1981, when BPIIC
the same is hereby AFFIRMED in toto. issued a cancellation of mortgage of Frank Roa's loan.
This finds support in the registration on March 31, 1981
SO ORDERED. 3 of the Deed of Absolute Sale executed by Roa in favor of
ALS, transferring the title of the property to ALS, and
In its decision, the Court of Appeals reasoned that a ALS executing the Mortgage Deed in favor of BPIIC.
simple loan is perfected only upon the delivery of the Moreover, petitioner claims, the delay in the release of
object of the contract. The contract of loan between the loan should be attributed to private respondents. As
BPIIC and ALS & Litonjua was perfected only on BPIIC only agreed to extend a P500,000 loan, private
September 13, 1982, the date when BPIIC released the respondents were required to reduce Frank Roa's loan
purported balance of the P500,000 loan after deducting below said amount. According to petitioner, private
therefrom the value of Roa's indebtedness. Thus, respondents were only able to do so in August 1982.
payment of the monthly amortization should commence
only a month after the said date, as can be inferred from In their comment, private respondents assert that based
the stipulations in the contract. This, despite the express on Article 1934 of the Civil Code, 4 a simple loan is
agreement of the parties that payment shall commence perfected upon the delivery of the object of the contract,
on May 1, 1981. From October 1982 to June 1984, the hence a real contract. In this case, even though the loan
total amortization due was only P194,960.43. Evidence contract was signed on March 31, 1981, it was perfected
showed that private respondents had an overpayment, only on September 13, 1982, when the full loan was
because as of June 1984, they already paid a total released to private respondents. They submit that
amount of P201,791.96. Therefore, there was no basis petitioner misread Bonnevie. To give meaning to Article
for BPIIC to extrajudicially foreclose the mortgage and 1934, according to private respondents, Bonnevie must
cause the publication in newspapers concerning private be construed to mean that the contract to extend the
respondents' delinquency in the payment of their loan.
loan was perfected on March 31, 1981 but the contract the parties on the commencement of the monthly
of loan itself was only perfected upon the delivery of the amortization, as found by the Court of Appeals, private
full loan to private respondents on September 13, 1982. respondents' obligation to pay commenced only on
October 13, 1982, a month after the perfection of the
Private respondents further maintain that even granting, contract. 7
arguendo, that the loan contract was perfected on March
31, 1981, and their payment did not start a month We also agree with private respondents that a contract of
thereafter, still no default took place. According to loan involves a reciprocal obligation, wherein the
private respondents, a perfected loan agreement imposes obligation or promise of each party is the consideration
reciprocal obligations, where the obligation or promise of for that of the other. 8 As averred by private
each party is the consideration of the other party. In this respondents, the promise of BPIIC to extend and deliver
case, the consideration for BPIIC in entering into the the loan is upon the consideration that ALS and Litonjua
loan contract is the promise of private respondents to shall pay the monthly amortization commencing on May
pay the monthly amortization. For the latter, it is the 1, 1981, one month after the supposed release of the
promise of BPIIC to deliver the money. In reciprocal loan. It is a basic principle in reciprocal obligations that
obligations, neither party incurs in delay if the other neither party incurs in delay, if the other does not
does not comply or is not ready to comply in a proper comply or is not ready to comply in a proper manner
manner with what is incumbent upon him. Therefore, with what is incumbent upon him. 9 Only when a party
private respondents conclude, they did not incur in delay has performed his part of the contract can he demand
when they did not commence paying the monthly that the other party also fulfills his own obligation and if
amortization on May 1, 1981, as it was only on the latter fails, default sets in. Consequently, petitioner
September 13, 1982 when petitioner fully complied with could only demand for the payment of the monthly
its obligation under the loan contract. amortization after September 13, 1982 for it was only
then when it complied with its obligation under the loan
We agree with private respondents. A loan contract is contract. Therefore, in computing the amount due as of
not a consensual contract but a real contract. It is the date when BPIIC extrajudicially caused the
perfected only upon the delivery of the object of the foreclosure of the mortgage, the starting date is October
contract. 5 Petitioner misapplied Bonnevie. The contract 13, 1982 and not May 1, 1981.
in Bonnevie declared by this Court as a perfected
consensual contract falls under the first clause of Article Other points raised by petitioner in connection with the
1934, Civil Code. It is an accepted promise to deliver first issue, such as the date of actual release of the loan
something by way of simple loan. and whether private respondents were the cause of the
delay in the release of the loan, are factual. Since
In Saura Import and Export Co. Inc. vs. Development petitioner has not shown that the instant case is one of
Bank of the Philippines, 44 SCRA 445, petitioner applied the exceptions to the basic rule that only questions of
for a loan of P500,000 with respondent bank. The latter law can be raised in a petition for review under Rule 45
approved the application through a board resolution. of the Rules of Court, 10 factual matters need not tarry
Thereafter, the corresponding mortgage was executed us now. On these points we are bound by the findings of
and registered. However, because of acts attributable to the appellate and trial courts.
petitioner, the loan was not released. Later, petitioner
instituted an action for damages. We recognized in this On the second issue, petitioner claims that it should not
case, a perfected consensual contract which under be held liable for moral and exemplary damages for it did
normal circumstances could have made the bank liable not act maliciously when it initiated the foreclosure
for not releasing the loan. However, since the fault was proceedings. It merely exercised its right under the
attributable to petitioner therein, the court did not mortgage contract because private respondents were
award it damages. irregular in their monthly amortization. It invoked our
ruling in Social Security System vs. Court of Appeals,
A perfected consensual contract, as shown above, can 120 SCRA 707, where we said:
give rise to an action for damages. However, said
contract does not constitute the real contract of loan Nor can the SSS be held liable for moral and temperate
which requires the delivery of the object of the contract damages. As concluded by the Court of Appeals "the
for its perfection and which gives rise to obligations only negligence of the appellant is not so gross as to warrant
on the part of the borrower. 6 moral and temperate damages," except that, said Court
reduced those damages by only P5,000.00 instead of
In the present case, the loan contract between BPI, on eliminating them. Neither can we agree with the findings
the one hand, and ALS and Litonjua, on the other, was of both the Trial Court and respondent Court that the
perfected only on September 13, 1982, the date of the SSS had acted maliciously or in bad faith. The SSS was
second release of the loan. Following the intentions of of the belief that it was acting in the legitimate exercise
of its right under the mortgage contract in the face of DEPARTMENT OF COMMERCIAL AND SAVINGS
irregular payments made by private respondents and BANK, in his capacity as statutory receiver of Island
placed reliance on the automatic acceleration clause in Savings Bank, petitioners, vs. THE HONORABLE
the contract. The filing alone of the foreclosure COURT OF APPEALS and SULPICIO M. TOLENTINO,
application should not be a ground for an award of respondents.
moral damages in the same way that a clearly
unfounded civil action is not among the grounds for DECISION
moral damages.
MAKASIAR, C.J p:
Private respondents counter that BPIIC was guilty of bad
faith and should be liable for said damages because it This is a petition for review on certiorari to set aside as
insisted on the payment of amortization on the loan even null and void the decision of the Court of Appeals, in
before it was released. Further, it did not make the C.A.-G.R. No. 52253-R dated February 11, 1977,
corresponding deduction in the monthly amortization to modifying the decision dated February 15, 1972 of the
conform to the actual amount of loan released, and it Court of First Instance of Agusan, which dismissed the
immediately initiated foreclosure proceedings when petition of respondent Sulpicio M. Tolentino for
private respondents failed to make timely payment. injunction, specific performance or rescission, and
damages with preliminary injunction.
But as admitted by private respondents themselves, they
were irregular in their payment of monthly amortization. On April 28, 1965, Island Savings Bank, upon favorable
Conformably with our ruling in SSS, we can not properly recommendation of its legal department, approved the
declare BPIIC in bad faith. Consequently, we should rule loan application for P80,000.00 of Sulpicio M. Tolentino,
out the award of moral and exemplary damages. 11 who, as a security for the loan, executed on the same
day a real estate mortgage over his 100-hectare land
However, in our view, BPIIC was negligent in relying located in Cubo, Las Nieves, Agusan, and covered by
merely on the entries found in the deed of mortgage, TCT No. T-305, and which mortgage was annotated on
without checking and correspondingly adjusting its the said title the next day. The approved loan application
records on the amount actually released to private called for a lump sum P80,000.00 loan, repayable in
respondents and the date when it was released. Such semi-annual installments for a period of 3 years, with
negligence resulted in damage to private respondents, for 12% annual interest. It was required that Sulpicio M.
which an award of nominal damages should be given in Tolentino shall use the loan proceeds solely as an
recognition of their rights which were violated by BPIIC. additional capital to develop his other property into a
12 For this purpose, the amount of P25,000 is sufficient. subdivision.

Lastly, as in SSS where we awarded attorney's fees On May 22, 1965, a mere P17,000.00 partial release of
because private respondents were compelled to litigate, the P80,000.00 loan was made by the Bank; and
we sustain the award of P50,000 in favor of private Sulpicio M. Tolentino and his wife Edita Tolentino signed
respondents as attorney's fees. a promissory note for P17,000.00 at 12% annual
interest, payable within 3 years from the date of
WHEREFORE, the decision dated February 28, 1997, of execution of the contract at semi-annual installments of
the Court of Appeals and its resolution dated April 21, P3,459.00 (p. 64, rec.), An advance interest for the
1998, are AFFIRMED WITH MODIFICATION as to the P80,000.00 loan covering a 6-month period amounting
award of damages. The award of moral and exemplary to P4,800.00 was deducted from the partial release of
damages in favor of private respondents is DELETED, P17,000.00. But this pre-deducted interest was refunded
but the award to them of attorney's fees in the amount of to Sulpicio M. Tolentino on July 23, 1965, after being
P50,000 is UPHELD. Additionally, petitioner is informed by the Bank that there was no fund yet
ORDERED to pay private respondents P25,000 as available for the release of the P63,000.00 balance (p.
nominal damages. Costs against petitioner. ACTIcS 47, rec.). The Bank, thru its vice-president and
treasurer, promised repeatedly the release of the
SO ORDERED. P63,000.00 balance (p. 113, rec.).

On August 13, 1965, the Monetary Board of the Central


Bank, after finding Island Savings Bank was suffering
liquidity problems, issued Resolution No. 1049, which
provides:
[G.R. No. L-45710. October 3, 1985.]
"In view of the chronic reserve deficiencies of the Island
CENTRAL BANK OF THE PHILIPPINES and ACTING
Savings Bank against its deposit liabilities, the Board, by
DIRECTOR ANTONIO T. CASTRO, JR. OF THE
unanimous vote, decided as follows:
"1) To prohibit the bank from making new loans and M. Tolentino's petition for specific performance, but it
investments [except investments in government ruled that Island Savings Bank can neither foreclose the
securities] excluding extensions or renewals of already real estate mortgage nor collect the P17,000.00 loan (pp.
approved loans, provided that such extensions or 30-31, rec.). prcd
renewals shall be subject to review by the
Superintendent of Banks, who may impose such Hence, this instant petition by the Central Bank.
limitations as may be necessary to insure correction of
the bank's deficiency as soon as possible; The issues are:

. . ." (p. 46, rec.). 1. Can the action of Sulpicio M. Tolentino for
specific performance prosper?
On June 14, 1968, the Monetary Board, after finding
that Island Savings Bank failed to put up the required 2. Is Sulpicio M. Tolentino liable to pay the
capital to restore its solvency, issued Resolution No. 967 P17,000.00 debt covered by the promissory note?
which prohibited Island Savings Bank from doing
3. If Sulpicio M. Tolentino's liability to pay the
business in the Philippines and instructed the Acting
P17,000.00 subsists, can his real estate mortgage be
Superintendent of Banks to take charge of the assets of
foreclosed to satisfy said amount?.
Island Savings Bank (pp. 48-49, rec.).
When Island Savings Bank and Sulpicio M. Tolentino
On August 1, 1968, Island Savings Bank, in view of non-
entered into an P80,000.00 loan agreement on April 28,
payment of the P17,000.00 covered by the promissory
1965, they undertook reciprocal obligations. In
note, filed an application for the extra-judicial
reciprocal obligations, the obligation or promise of each
foreclosure of the real estate mortgage covering the 100-
party is the consideration for that of the other (Penaco
hectare land of Sulpicio M. Tolentino; and the sheriff
vs. Ruaya, 110 SCRA 46 [1981]; Vda. de Quirino vs.
scheduled the auction for January 22, 1969.
Pelarca, 29 SCRA 1 [1969]); and when one party has
On January 20, 1969, Sulpicio M. Tolentino filed a performed or is ready and willing to perform his part of
petition with the Court of First Instance of Agusan for the contract, the other party who has not performed or is
injunction, specific performance or rescission and not ready and willing to perform incurs in delay (Art.
damages with preliminary injunction, alleging that since 1169 of the Civil Code). The promise of Sulpicio M.
Island Savings Bank failed to deliver the P63,000.00 Tolentino to pay was the consideration for the obligation
balance of the P80,000.00 loan, he is entitled to specific of Island Savings Bank to furnish the P80,000.00 loan.
performance by ordering Island Savings Bank to deliver When Sulpicio M. Tolentino executed a real estate
the P63,000.00 with interest of 12% per annum from mortgage on April 28, 1965, he signified his willingness
April 28, 1965, and if said balance cannot be delivered, to pay the P80,000.00 loan. From such date, the
to rescind the real estate mortgage (pp. 32-43, rec.). obligation of Island Savings Bank to furnish the
P80,000.00 loan accrued. Thus, the Bank's delay in
On January 21, 1969, the trial court, upon the filing of a furnishing the entire loan started on April 28, 1965, and
P5,000.00 surety bond, issued a temporary restraining lasted for a period of 3 years or when the Monetary
order enjoining the Island Savings Bank from continuing Board of the Central Bank issued Resolution No. 967 on
with the foreclosure of the mortgage (pp. 86-87, rec.). June 14, 1968, which prohibited Island Savings Bank
from doing further business. Such prohibition made it
On January 29, 1969, the trial court admitted the legally impossible for Island Savings Bank to furnish the
answer in intervention praying for the dismissal of the P63,000.00 balance of the P80,000.00 loan. The power of
petition of Sulpicio M. Tolentino and the setting aside of the Monetary Board to take over insolvent banks for the
the restraining order, filed by the Central Bank and by protection of the public is recognized by Section 29 of
the Acting Superintendent of Banks (pp. 65-76, rec.). R.A. No. 265, which took effect on June 15, 1948, the
validity of which is not in question.
On February 15, 1972, the trial court, after trial on the
merits, rendered its decision, finding unmeritorious the The Monetary Board Resolution No. 1049 issued on
petition of Sulpicio M. Tolentino, ordering him to pay August 13, 1965 cannot interrupt the default of Island
Island Savings Bank the amount of P17,000.00 plus Savings Bank in complying with its obligation of
legal interest and legal charges due thereon, and lifting releasing the P63,000.00 balance because said
the restraining order so that the sheriff may proceed resolution merely prohibited the Bank from making new
with the foreclosure (pp. 135-136, rec.). loans and investments, and nowhere did it prohibit
Island Savings Bank from releasing the balance of loan
On February 11, 1977, the Court of Appeals, on appeal agreements previously contracted. Besides, the mere
by Sulpicio M. Tolentino, modified the Court of First pecuniary inability to fulfill an engagement does not
Instance decision by affirming the dismissal of Sulpicio discharge the obligation of the contract, nor does it
constitute any defense to a decree of specific Since Island Savings Bank was in default in fulfilling its
performance (Gutierrez Repide vs. Afzelins and Afzelins, reciprocal obligation under their loan agreement,
39 Phil. 190 [1918]). And, the mere fact of insolvency of Sulpicio M. Tolentino, under Article 1191 of the Civil
a debtor is never an excuse for the non-fulfillment of an Code, may choose between specific performance or
obligation but instead it is taken as a breach of the rescission with damages in either case. But since Island
contract by him (Vol. 17A, 1974 ed., CJS p. 650). LexLib Savings Bank is now prohibited from doing further
business by Monetary Board Resolution No. 967, WE
The fact that Sulpicio M. Tolentino demanded and cannot grant specific performance in favor of Sulpicio M.
accepted the refund of the pre-deducted interest Tolentino.
amounting to P4,800.00 for the supposed P80,000.00
loan covering a 6-month period cannot be taken as a Rescission is the only alternative remedy left. WE rule,
waiver of his right to collect the P63,000.00 balance. The however, that rescission is only for the P63,000.00
act of Island Savings Bank, in asking the advance balance of the P80,000.00 loan, because the bank is in
interest for 6 months on the supposed P80,000.00 loan, default only insofar as such amount is concerned, as
was improper considering that only P17,000.00 out of there is no doubt that the bank failed to give the
the P80,000.00 loan was released. A person cannot be P63,000.00. As far as the partial release of P17,000.00,
legally charged interest for a non-existing debt. Thus, which Sulpicio M. Tolentino accepted and executed a
the receipt by Sulpicio M. Tolentino of the pre-deducted promissory note to cover it, the bank was deemed to
interest was an exercise of his right to it, which right have complied with its reciprocal obligation to furnish a
exist independently of his right to demand the P17,000.00 loan. The promissory note gave rise to
completion of the P80,000.00 loan. The exercise of one Sulpicio M. Tolentino's reciprocal obligation to pay the
right does not affect, much less neutralize, the exercise P17,000.00 loan when it falls due. His failure to pay the
of the other. overdue amortizations under the promissory note made
him a party in default, hence not entitled to rescission
The alleged discovery by Island Savings Bank of the (Article 1191 of the Civil Code). If there is a right to
over-valuation of the loan collateral cannot exempt it rescind the promissory note, it shall belong to the
from complying with its reciprocal obligation to furnish aggrieved party, that is, Island Savings Bank. If
the entire P80,000.00 loan. This Court previously ruled Tolentino had not signed a promissory note setting the
that bank officials and employees are expected to date for payment of P17,000.00 within 3 years, he would
exercise caution and prudence in the discharge of their be entitled to ask for rescission of the entire loan
functions (Rural Bank of Caloocan, Inc. vs. C.A., 104 because he cannot possibly be in default as there was no
SCRA 151 [1981]). It is the obligation of the bank's date for him to perform his reciprocal obligation to pay.
officials and employees that before they approve the loan
application of their customers, they must investigate the Since both parties were in default in the performance of
existence and valuation of the properties being offered as their respective reciprocal obligations, that is, Island
a loan security. The recent rush of events where Savings Bank failed to comply with its obligation to
collaterals for bank loans turn out to be non-existent or furnish the entire loan and Sulpicio M. Tolentino failed
grossly over-valued underscore the importance of this to comply with his obligation to pay his P17,000.00 debt
responsibility. The mere reliance by bank officials and within 3 years as stipulated, they are both liable for
employees on their customer's representation regarding damages. Cdpr
the loan collateral being offered as loan security is a
patent non-performance of this responsibility. If ever, Article 1192 of the Civil Code provides that in case both
bank officials and employees totally rely on the parties have committed a breach of their reciprocal
representation of their customers as to the valuation of obligations, the liability of the first infractor shall be
the loan collateral, the bank shall bear the risk in case equitably tempered by the courts. WE rule that the
the collateral turn out to be over-valued. The liability of Island Savings Bank for damages in not
representation made by the customer is immaterial to furnishing the entire loan is offset by the liability of
the bank's responsibility to conduct its own Sulpicio M. Tolentino for damages, in the form of
investigation. Furthermore, the lower court, on penalties and surcharges, for not paying his overdue
objections of Sulpicio M. Tolentino, had enjoined P17,000.00 debt. The liability of Sulpicio M. Tolentino for
petitioners from presenting proof on the alleged over- interest on his P17,000.00 debt shall not be included in
valuation because of their failure to raise the same in offsetting the liabilities of both parties. Since Sulpicio M.
their pleadings (pp. 198-199, t.s.n., Sept. 15, 1971). The Tolentino derived some benefit for his use of the
lower court's action is sanctioned by the Rules of Court, P17,000.00, it is just that he should account for the
Section 2, Rule 9, which states that "defenses and interest thereon.
objections not pleaded either in a motion to dismiss or in
the answer are deemed waived." Petitioners, thus,
cannot raise the same issue before the Supreme Court.
WE hold, however, that the real estate mortgage of "Therefore, the debtor's heirs who has paid a part of the
Sulpicio M. Tolentino cannot be entirely foreclosed to debt can not ask for the proportionate extinguishment of
satisfy his P17,000.00 debt. the pledge or mortgage as long as the debt is not
completely satisfied.
The consideration of the accessory contract of real estate
mortgage is the same as that of the principal contract "Neither can the creditor's heir who have received his
(Banco de Oro vs. Bayuga, 93 SCRA 443 [1979]). For the share of the debt return the pledge or cancel the
debtor, the consideration of his obligation to pay is the mortgage, to the prejudice of other heirs who have not
existence of a debt. Thus, in the accessory contract of been paid."
real estate mortgage, the consideration of the debtor in
furnishing the mortgage is the existence of a valid, The rule of indivisibility of the mortgage as outlined by
voidable, or unenforceable debt (Art. 2086, in relation to Article 2089 above-quoted presupposes several heirs of
Art. 2052, of the Civil Code). the debtor or creditor which does not obtain in this case.
Hence, the rule of indivisibility of a mortgage cannot
The fact that when Sulpicio M. Tolentino executed his apply.
real estate mortgage, no consideration was then in
existence, as there was no debt yet because Island WHEREFORE, THE DECISION OF THE COURT OF
Savings Bank had not made any release on the loan, APPEALS DATED FEBRUARY 11, 1977 IS HEREBY
does not make the real estate mortgage void for lack of MODIFIED, AND
consideration. It is not necessary that any consideration
should pass at the time of the execution of the contract 1. SULPICIO M. TOLENTINO IS HEREBY
of real mortgage (Bonnevie vs. C.A., 125 SCRA 122 ORDERED TO PAY IN FAVOR OF HEREIN PETITIONERS
[1983]). It may either be a prior or subsequent matter. THE SUM OF P17,000.00, PLUS P41,210.00
But when the consideration is subsequent to the REPRESENTING 12% INTEREST PER ANNUM
mortgage, the mortgage can take effect only when the COVERING THE PERIOD FROM MAY 22, 1965 TO
debt secured by it is created as a binding contract to pay AUGUST 22, 1985, AND 12% INTEREST ON THE TOTAL
(Parks vs. Sherman, Vol. 176 N.W. p. 583, cited in the AMOUNT COUNTED' FROM AUGUST 22, 1985 UNTIL
8th ed., Jones on Mortgage, Vol. 2, pp. 5-6). And, when PAID;
there is partial failure of consideration, the mortgage
2. IN CASE SULPICIO M. TOLENTINO FAILS TO
becomes unenforceable to the extent of such failure
PAY, HIS REAL ESTATE MORTGAGE COVERING 21.25
(Dow, et al. vs. Poore, Vol. 172 N.E. p. 82, cited in Vol.
HECTARES SHALL BE FORECLOSED TO SATISFY HIS
59, 1974 ed. CJS, p. 138). Where the indebtedness
TOTAL INDEBTEDNESS; AND
actually owing to the holder of the mortgage is less than
the sum named in the mortgage, the mortgage cannot be 3. THE REAL ESTATE MORTGAGE COVERING
enforced for more than the actual sum due (Metropolitan 78.75 HECTARES IS HEREBY DECLARED
Life Ins. Co. vs. Peterson, Vol. 19, F(2d) p. 88, cited in UNENFORCEABLE AND IS HEREBY ORDERED
6th ed., Wiltsie on Mortgage, Vol. 1, p. 180). LLpr RELEASED IN FAVOR OF SULPICIO M. TOLENTINO.

Since Island Savings Bank failed to furnish the NO COSTS. SO ORDERED.


P63,000.00 balance of the P80,000.00 loan, the real
estate mortgage of Sulpicio M. Tolentino became
unenforceable to such extent. P63,000.00 is 78.75% of
P80,000.00, hence the real estate mortgage covering 100
hectares is unenforceable to the extent of 78.75
hectares. The mortgage covering the remainder of 21.25
hectares subsists as a security for the P17,000.00 debt.
21.25 hectares is more than sufficient to secure a
P17,000.00 debt.

The rule of indivisibility of a real estate mortgage


provided for by Article 2089 of the Civil Code is
inapplicable to the facts of this case.

Article 2089 provides:

"A pledge or mortgage is indivisible even though the debt


may be divided among the successors in interest of the
debtor or creditor.

Das könnte Ihnen auch gefallen