Beruflich Dokumente
Kultur Dokumente
www.cpaa.asn.au
of Australasia
CONCRETE PIPE ASSOCIATION OF AUSTRALASIA
A.C.N. 007 067 656
~O . 0000'\32.
PROGRAM
12 . 00 noon Luncheon.
Subject:
Pipe Design, Manufacture, and Testing
Presented by C W Simpson, Dip CE RMIT
.. . /2
,-
#
-2-
1.2 Specifications
Specifications can be of three basic types, -
.. . /3
~.
•
-3-
Prescription and Design specifications are used for
bui1dings and structures which are difficu1t or
impossib1e to test. They are of necessi~ conservative.
. .. /4
.
~
-4- •
This can be illustrated, if further evidence is
required, by calculating the apparent stresses in
pipes specified in the American prescription
specification ASTM C76-1972. The apparent stresses
will be found to be unrealistically high, despite the
fact that the concrete strengths specified are much
lower than those obtained by pipe manufacturers in
Australia. In fact of course, the actual stress is
not as high as the calculation indicates.
.. ./5
J
- 5-
2.2 Specification
The Australian Standard is A.S. A124-1962.
It is essentially a performance specification but has
some stress limitations.
. .. /6
.1"
•
-6-
3.1 Combinedloading
Almost every pressure pipe laid has to carry external
load as well as internal pressure, so it is important -
particularly under roads, or where the earth fill over
the pipe exceeds 1 metre - that the combined effect is
considered.
3.2 Specification
Appendix G of A.S. 124-1962 covers this situation.
1. Methods
Australian pipe manufacturers are world leaders in
methods for making steel reinforcing cages and high
strength concrete pipes. Continuously welded spiral-
wound reinforcing cages are almost universally used in
this country, whereas in America it is still common for
cages to be fabricated from flat mesh. Machine-made
spiral-wound cages are very accurate and economical.
2. Quality
Very low water/cement ratios and high densities are
features of Australian pipe-making processes.
A characteristic concrete stren~th (the strength above
which 97t% of results will fall) of 50 MFa (7 , 250 Ib/in2 )
is easily attained.
. .. /7
-7-
J. Quality Control
As with all machine-made factory products, quality is
easier to control than is the case with in-situ work in
the field. Factory work is unaffected by the weather,
varying trench conditions, or the difficulty of
providing and operating pipe-casting equipment in remote
areas. A built-in control is the low water-cement
ratio, which is inherent in the processes.
PIPE TESTING
1, Types of tests
Pipes are regularly tested in accordance with Australian
standards for load carrying capacity, hydrostatic
pressure capacity, joint water-tightness, absorption, and
material quality. Pipes are inspected for dimensional
correctness, cover thickness, and internal finish.
Subject:
Economic Use of Concrete Pipes
Presented by W M MILLER, MIE Auet, MNZIE, FAD(
Introduction
Engineers live in a world of compromise and this 1s most
true when faced with the three basic economic factors :
Initial Cost
. . . /2
~ .
"
Page 2.
Pipe class cost and bedding cost. CA33-1962 gives you
a choice o~ beddings - some costlier than others.
A 54" (1350 mm) diameter pipe in a trench O.D. + 18" (450 mm)
wide in clayey sand under 14 ~eet o~ ~ill above crown can
be speci~ied as either _
. .. /3
"
Page 3.
An economical comparison per metre o~ pipe between the
items which di~~er in the three alternatives may then
look like this:
. .. /4
Page 4.
Pressure Pipes
The walls in pressure pipes are stressed in combined
tension and bending. Usually pressure pipes are bedded
in shallow trenches, and unless subjected to traffic or
other superimposed loads, the bending stresses in pipes of
moderate diameter (smaller than 1200 mm) are relatively
unimportant for pipes conforming to minimum requirements
of AS124-l962.
. .. /5
Page 5.
Trench excavations must be wider and left open longer
(for curing) and thus the risk of exposure to heavy rains,
cave-in risk is much greater. Again the great advantage
of the spun concrete pipe is its density and 1/4" of dense
concrete over reinforcement is worth several hundred times
the cover of the same thickness of less dense concrete.
This is particularly important in sewers.
REMARKS
OPERATION
CONCRETE AC
1. Set up a site SAME FOR BOTH
5. Purchase bedding Where excavated material is unsuitable, AC must have suitable bedding material so
material (if selected material must be brought in. that the whole 13 ft long pipe will
necessary) Concrete will tolerate practically all uniformly bed over its ru11 lengths with-
excavated material except big lump of out any settlement. Bedding material
sticky colloidal clay and rock. must be incompressible and not "flow"
Broken friable stone to say 3/4" size or be squeezed. Thus AC cannot tolerate
OK. the same range of excavated material for
bedding as can concrete. If there is
bad soft movable ground AC pipes should
have 6 ft lengths and thus dearer.
6. Place and grade Concrete requires this over 6 ft or For AC this takes more time and care
bedding material 8 ft length depending on pipe length. especially on flat grades. As stated
Thus effort, care and time not so in (5) above AC will break their backs
great as AC (longer lengths) and thus unless the bedding is perfectly on one
more jOints make the line more plane.
flexible.
7. Pipe deliveries Concrete suppliere will place pipes AC are delivered in approx 3 T pallets
to site along the trench so there is little which are dumped at depot or site along
transport on pre-laying handling trench. The cost of unpacking these,
effort or costs. assembling the sockets and rubber rings
and trench distribution, must be cos ted
to make a correct comparison.
. .. / 2
- 2 -
REMARKS
OPERATION
CONCRETE AC
8. Lay and joint If there is any advantage over concrete AC 13 ft lengths require two men similar
pipes it is in this part of the exercise. to concrete. The whole operation of
Comparing directly the time to pick pipe preparing bed, introducing and placing
up from the trench side and lay it on a selected material, grading and laying
previously prepared bed is an unreal pipe, must be considered for a fair
one. In both cases, it is the rate comparison with concrete.
the digger can progress that decides
the laying rate and in sewers which can
be deep, this part decides the speed of
laying.
11. Surface
maintenance SAME FOR BOTH
12. Life of pipe This is determined by many factors of AC has an absorption factor of 12%-13%
which relative density is but one. measured by the same methods as concrete.
This is measured by absorption. Thus as the AC concrete mortar absorbs
Concrete has an absorption factor of soil aggressives at a greater rate than
under 6.1/2%. concrete, its life can be shorter.
Added to this the thinner AC walls which
when attacked give less strength than
the thicker concrete.
13. Summary As can be seen from this comparison and the introductory notes, claims made by some
that 4 m pipes can be laid faster, are marginal and the actual cost of physically
picking up the pipe and placing it in the trench is a very small part of the total
laying cost.
,.
CONCRETE PIPES IN TRENCH
TYPES OF BEDDING ON EARTH
TYPE:A
C_li"vovs CDIt",.".
Crad/e.: af monolffnil:. aoss-secf,Ot1 iI'I""'t,"nfol'uQ
~ -
~ 7.:;::: .,- ~r:
- -
::-.: ~-;
_-=-.
• , Orai""'r" Fill
~J -lJ
.-SJ ~ _<0_
• r--lt~=.-.~-~"'=-::
TYPE: B
~o ~/eclecT Compae leo' Fill
.....
" :: : :: ::" CompaclecT Sana' or
Grahu/ar /'fede,.ia/ 3'min.
.,.-.....",.",----_-o- -:- :-
- .....,.
~
<.> >
J-
- -- - -
Ordihary FIll
-= 15-- TYPE:D
CLAY
•
C
8·5
6
14
,
NL
24
NL
NL
6
4·5
8·5
6·5
I'
12
NL
21
D 4 5·5 II 20 3 4 7 II
A 14 NL NL NL '·5 13 NL NL
SANDY • ' ·5 18 NL NL 6·5 ' ·5 26 NL
CLAY C
D
6·5
4
10
6
NL
12
NL
NL
5
3
6·5
4·5
I)
7:5
))
12
IS"
A 17 NL NL NL , 14 NL NL
CLAYEY
SAND
•
C
II
7
18
II
NL
NL
NL
NL
7
5
10
7
NL
IS
NL
NL
D 4·5 6 14 NL )·5 4·5 8 14
A NL NL NL NL 10 20 NL NL
SAND •
C
14
7·5
NL
14
NL
NL
NL
NL
7·5
5 7·5
12 NL
21
NL
NL
D 4·5 7 27 NL 3·5 4·5 9 18
•
~
12 NL NL 7·5 13 NL NL
SAND
C 7 14 NL NL 5 8 21 NL
D 4·5 7 19 NL ]·5 5 , 20
Annex to "Economic Use of Concrete Pipes"
CLAY
•
C 4·5
6
8·5
12 21
IS
36 5·5 10 18 28
- -- - -
23 4 7·5 13 19
-- - - - -
D 3·5 6 9·5 14 3 5·5 8·5 12
A 8 16 34 NL 7 13 26 55
-- - - - - ----- -----
SANDY
• 6·5 12 23 49 5·5 II 19 II
- - - - -----
CLAY C
D 3·5
5 9
6
16
10
25
IS
4·5
3
8 14
5·5
21
----- --- -
9 13
54"
A 8 16 040 NL 7 14 29 NL
----
CLAYEY
• 6·5 13 2S NL 5·5
" 21 38
----
SAND C 5 9 16 29 4·5 8 14 22
-J - - - - ---- - - - -
D 3·5 6 10 16 5·5 9 H
A 8 ·5 18 NL NL 7 IS 38 NL
._- ----
SAND •
C
6·5
5 9·5
14 33
18
NL 6 12 24
---- ----
78
40 4·5 8·5 IS 26
3·5 6·5
-----
D 18
" 3 5·5 10 15
A 6 20 32
WET B 5
"
9·5 16 23
CLAY 4 7
C
D 3 5
"8
16
A 6 12 21
"
37
SANDY
CLAY
•
C
5
4
10
7
16
12
26
17 54"
0 3 5 8
A 6·5 12 23
"
43
CLAYEY B 5·5 10 17 28
..
SAND C 4 7·5 12 18
0 3 5 8· 5 12
A 6·5 13 27 NL
SAND •
C
5·5
4
"
7·5
19
13
36
20
D 3 5 8 ·5 12
CONCRETE PIPE ASSOCIATION OF AUSTRALIA
1974 Seminars for Civil Engineers
T 1 -- 22800
T 2 = 16700
W
F = 12500
w
F = 12,500 1bs / ft. (see AS CA33-1962)
Subject:
Performance of Reinforced Concrete Pipes
Presented by Clifford A Baker, BA, BSc, ARMTC,MIE Aust.
Scope
The broad subject of performance of reinforced concrete
pipe can, at best, only be superficially reviewed in a
short paper such as this, so after a brief look at the
basic physical and chemical properties of reinforced
concrete, attention will be directed primarily to
a. Chemical Composition
Concrete normally consists of inert aggregates bound
together by hydrated cement and most of the fundamental
concrete properties derive from the cement properties,
although mix proportions, the degree of compaction
or consolidation achieved when the concrete is placed
and subsequent curing can have important modifying
effects.
. .. /2
:A
·-
Page 2
b. Physical Properties
The general principles of concrete technology are
applicable to pipes but any general assessments of
pipe concrete should be made in the context of the
usage of extremely low water cement ratios and very
high compactive forces. In the literature relating
to reinforced concrete one seldom sees reference to
water cement ratios below 0.40 by weight, but this
is near the upper limit for concrete pipe and water
cement ratios significantly below this are the norm.
These low wlc ratios are only practicable because of
the high compactive forces possible in the centrif-
ugation, vibration and pressure methods used by pipe
manufacturers.
. .. . / 3
"
Page J
c. Permeability
Low permeability is one o~ the most important properties
of pipe concrete, not only because it is an essential
feature o~ an hydraulic pipe, but most importantly,
it is an indicator o~ concrete durability.
d. Rei~orcement
.. . / 4
Page 4
e. Cracks
f. Autogenous Healing
Concrete which is cracked or porous and showing
permeability will often heal itself in the presence
of moisture by thA process known as autogenous healing.
The water passage is sealed by one or more of the
following
. . . /5
Page 5
Autogenous healing of reinforced concrete allows
pipes which are overloaded and crack to again become
watertight when the overload is removed, or, in the
case of internal pressure to heal whilst still under
working pressure.
... /6
Page 6
and similar pipes, totalling nearly 30,500 m (100,000
:ft.) :for Kerang, Wangaratta, _Mitcham, Flinders Naval
Base, Swan Hill and Corryong. Pressure pipes were
also known to be installed prior to 1920, in Queensland,
South Australia, Western Australia and Tasmania.
a. Clay Soils
In many clay soils, typified by the Horsham and
Gee10ng areas in Victoria, changing soil moisture
content causes significant movement which, unlike
settlement, persists through the life of the
pipeline. As a result a history of failure of
3.96 m (13 ft.) long fibro pipes has been built uP.
due to their having insufficient beam strength.
With reinforced concrete pipes in 1.68 m (6 ft.) or
2.44 m (8 ft.) length, and flexible joints, the beam
strength is adequate to resist these soil loads.
b. Effect of Overload
Reinforced concrete pipe will remain serviceable
even if subjected to occasional or accidental
overload - for pressure pipe the autogeneous healing
effect has already been mentioned. For reinforced
concrete pipe under external load an overload of
up to nea~ly 50% will not cause disastrous failure
and, if the overload is removed recovery will occur,
usually leaving the line serviceable. Non reinforced
pipes are destroyed in these circumstances.
. .. /8
Page 8
d. Dimensional Stability
Concrete kept moist is completely stable in dimensions,
and dimensional changes due to wetting and drying are
basically cyclic about a constant value. "Growth"
or continuing increase in length, leading to failure
as a column, is not experienced as with some other
materials.
f. Susceptibility to Corrosion
... /9
"
Page 9
b. "!!2S Attack"
When certain combinations of circumstances occur in a
sewer, pipes can be subjected to acid corrosion known
as H2 S attack. Sulphur compounds existin~ in the
sewage have a dissolved hydrogen sulphide lH 2 S)
fraction which can be released into the atmosphere.
In aerobic conditions this H S is oxidised on the
pipe surface by bacterial action with progressive
reduction of pH and formation of sulphuric acid which
attacks the cement compounds (in concrete or asbestos
cement pipes). This process is only likely to occur
with stale sewage (high biochemical oxygen demand),
high temperatures, poor ventilation, flat grades and
low flows, and where industrial wastes or other
sulphate sources are admitted to the system. In
general, aggressive combination of these adverse
circumstances oC,c urs only in the larger collecting
trunk and outfall sewers.
. . . . . /1 0
"
Page 10
••• / 11
Page 11
d. Aggressive Effluents
The possibilities of internal attack by aggressive
trade wastes are basically similar to those arising
from aggressive ground waters but because these wastes
are usually sufficient in quantity to maintain
corrosion rates, acceptable concentrations are lower
than for ground waters - for example the pH limit
is nearer 6 than 5. Protective measures similar
to those adopted for H S attack are applicable
2
for acid industrial wastes.
e. Reinforcement Corrosion
Because of the protection provided by the high pH
of the concrete, attack on the reinforcement as
distinct from the concrete is unusual. The only
troublesome source can be very high chloride
concentrations e.g. brine. Steel corrosion due to
pH reduction by carbonation, sometimes experienced
in cast in situ concrete is not a problem with
precast pipe because the concrete impermeability
prevents carbonation to significant depth.
Conclusions
f
120 L2000xI012
em/sec .
~ 110 .-
'Q
)(
100
v
~ 90
E
v
I 80
--
~
70
~
>- J
60
..J
m
~ !50
1
UJ
~
a= 40
/
~ 30
~ I
/
0
J
u.: 20
lL
/
--
W 10
0
u ~
o
0,2 0,3 0,4 0,5 0·6 0,7 0 ,8
W/C RATIO - by weight.
FIG I
EFFECT OF INITIAL WIC RATIO ON PERMEABILITY
•
Ref'erences
A f'ull range of' ref'erence material can be obtained from
the CPAA. A brief list of suggested reading is given
below.
Permeability
Sea Water
~S Attack
Subject:
Installation of Reinforced Concrete Pipes
Presented by Ian G Hope, BE,M Eng Sc, MIE Aust.
Introduction
The discussions so far covered the selection of a
suitable reinforced concrete pipe, for a particular
application. It is now proposed to outline
significant aspects of pipeline installation, which
must be appreciated by Engineers responsible for
construction.
General
When preparing drawings or instructions for installation
of pipes, it is necessary that the following basic
information be incorporated;
... /2
Page 2.
al diameter
b class and joint type of pipe
c type of bedding
d invert levels
e condition of installation i.e., wide
or narrow trench, or embankment
conditions
(f) backfill requirements
Conditions of Installation
The magnitude of loads imposed upon a buried pipe, by
the overlying soil and by any uniformly distributed or
concentrated surface surcharge of large or infinite
extent, depends first on the nature, density and depth
of soil cover, the intensity of the surcharge, the
nature of the pipe -whether rigid or flexible, and on
the conditions in which it is installed - whether
trench or embankment.
Trench Widths
For pipes in trench conditions the fill and surcharge
loads depend upon the effective trench width and
whether it is wide or narrow with respect to the
outside diameter of the pipe and depth of soil cover.
Figure 1 refers.
Assumptions
... /3
.
•
~
lAI
In·
. I I
I
."
i iI
_1 ~ .---.
'~~'
~! 'I
11\ ·k
• N' .~'
-#- - ~ ... -t -t
I :
i~1 H.'
,I
-f
I
I
8.
t
-
t I,
I .
I' ' .
. I!
I
I f D. t H
~
,
. - . ---~
Page 3 a
101M + MentaV"
NOU. 10 NOO
H:>tlilfJ.
--
--
--
-- -- .".. '"
---.t!-I\
-, i
.i
I ,
I t-- =h-- ~
'HI
,t..
l~
'g
(eI"/4iOO'I),u!JflIOOI. M
(N"'£)I,o~1 • If
F()()(X} ,6L· '00
. (WWOOi/) /,U '" '0 'I ~3J3H"'O
: StcOudWnssv
: I ~'dHVXl
Page 3.
Case 1 Narrow Trench Reference Appendix A of
CA33-1962, Section A1 Trench Condition.
therefore
W
e = 1.09 x 100 x (103)2
12
W , = C W D2
e e
Beyond the critical width at which this equality occurs,
any further increase in trench width produces no further
increase in the fill load since W , is independent of
trench width B, but is dependent 8n 0, the overall pipe
diameter.
D = 79" = 6.58 1
H/D = 12/6.58 = 1.83
C , the load coefficient for positive
e
projection embankment conditions, is
obtained from Figure 2, AS CA33-1962 = 2.7
therefore
2
we , = 2.7 x 100 x 6.58
= 11690 1b/ft length of pipe as
compared with the loading
(calculated as a trench) :-
2
W
e
= 0.5 x 100 x 22.75
= 25878 lb/ft length of pipe
where
= 136.5 x 2 22.75 1
+ 12 -
= 12/22.75 = 0.527
= 0.5 (from Figure 1 of CA33-1962
... /4
Page 4.
Summary
. . . /5
Page 5.
Load Factors
Fi~re 2
Case 2
Backfill compaction less than 90% of
the Maximum Dry Density F t = 1.9
(minimum value).
W = 8030 = 4200 lbf/ft
1.9
... / 6
Page 6.
p = 0.5 x = 0.423
0.7 0.594
0.9 0.655
1.0 0.638
W = C p 0(..
c p
L
. .. / 7
Page 7.
where
coefficient used in the calculation
of the vertical load on a pipe
due to concentrated superimposed
loads (Figure 5 GA33-l962)
P _ concentrated load in lbf.
oc = impact factor
L = length of a pipe over which a
vertical concentrated load is
assumed to be distributed
L = 1.15 H + 2D + S but not
greater than length of the pipe
where
S = length of a concentrated load along
a pipe in feet
Axle Loads
Pavement
Spreader Barber Green 62820 2 15700
PM=Prime Mover
Axle
S =Scraper 260 PM 34100 1 17050
Axle S 49200 1 24600
Catapillar
c PM 77400 1 38700
63l
s 71300 1 35650
Figure :3
.•. /8
Page 8.
Figure 4
Cover H (ft) 3 6 9 12
Required
Test
1 For
Load 1 2.5 1494 2060 2748 3270
Loads Factor 2661
Ft 1.9 1965 3616 430.5
W/Ft
Class of Pipe S X Y
Figure .5
· .. /9
COVER DEPTH H- It
15 13 II 10 9 8 7 G A FOR RIGID PIPES WITH
eeOOING ClASSES B,G,D
90
WOTE :
- IMPACT EFFECTS ).jOT
LNGlUOEO ,
70
,
, , I:;: ITM fi ....
Ii
I 60
"i
t· [1
'
"t':'
tt
.
,it 'tt; +,
t :.. ~ ....
+i"fj
- IT
~~
"'-'- u
_. »,
t'
..
.., .,:; ~-+ , :I , W.
- "
50 ,~
..
..... , IbI';" -~f-I- : • .-
..
40
:r -: .
.f!
- . [} :~dF: :: ; ( . -
;' I :;::;-
~c;:: ':'....
50
~ ::l- ,.; II ~~;:' ::t
!t ; , .' ,::: I:t '"I
~ 1:1 ,j ..... ;t' ;..;
7:" •. ~ •• J!. ~ . :.~ ::: . t~ EfFECOVE UOAOS W,
. .. :. ,... ... ..,..: i .. ~ t
~o
20
- , ~' .. " ::r.;. F . IMPOSED 8V TWO 1OOO1b.
I-." t 1
. IT WHEELS 3ft APART.
10 •
, .
, :
0 n n ~ riif r Ht Ii Iii Iii li
0 200 «10 ~oo 800 1000 rJOO 1400 1&00 1800 2000 2200 2AOO 2CiOO 2800 !OOO FIGURE 7.
"'d EFFl'CTIVI! LOAD, WL ¥t nm ofpope
P>
OQ
CD
-.0
P>
COVER DEPTH, H-ft.
j:;.:
__
t--~+~C;jl::~
71-; 1---
~~l:• ; .. i j •• ~ ~
"JtifffifullW'''fill!:fitfti-llrlffitt''t r
~:: ~T3, t ~, •• ~ h;;l :: J1' T
r; :::::: ::tc~:. '. il t , tc· j:nn-tl1 I: I ; 3It~
I . 'R-
......
~. ... ... t
.'!: r+I"7
~ r:-:: 'I!t t
I.. ~ ;- -
: I
. 20000 lb. WHEEL LOADS .
!fI1fll~~1i '
OI'I'ttt
"d o 1000 2000 3000 ~ !IOOO ~ 1000 eooo 9000 IOOClO 11000
po FIGURE 8.
IlQ
(I) EmcnvE LOAD Wg lIy!t. run ofpip! .
\0
t:r
Page 9.
·Cover H (f't ) 12
l
3 6 9
l
Total W 7199 6920 7809 8630
l
Required 2880
For 2.5 2768 3124 3452
Test Load
Loads Factor
Ft 1.9 3789 3642 4110 4542
W/Ft
Class of Pipe X Y
Figure 6
W = C D U
u u
where
C
u
= coefficient used in the calculation
of the vertical load on a pipe due
to a uniformly distri~uted superimp-
osed load of U lbf/ft
D = Outside pipe diameter
U = UnifO~lY distributed load in
lbf /ft
• .. /10
Page 10.
Bearing Pressures
Figure 11
Assumptionl!l
2 2
U = 1000 Ib£/£t (4882 Kg/m )
B1 = 10 £eet (3048 mm)
L = 1 £oot (305 mm)
Cu = ~IC'
Cover
H (Feet) 3 6 9 12
Figure 12
•.• /11
UNIFORM LY DlSTIIIBUTYO Ul~D UsuS
B -
~L drfffiJJP;:''' '
' : m .l/II
r~ n =~
o 6TRESHT 0 • U Ier
-
N.B: THE AREA B. L IS RECn.NGULA~ IN TRUE PLAt.! IN BOTH CASES .
,""
0.
o.~
""';'0::
". '1- M
0._ ~:~ ~
M.t~J:
0.72
1ft .1.( ~ ::::,... ",.~
.
~
1.
O.~
0.19 ~ ",.
0.1'
'// .~
0.17 '(// M. ~l
0.16 V/
0.15 V L ",.11
G.l4 L
In. 46
0." Not.: 1Jf ;- It ore
V
/"
0.12
0.11
ohM IJ .
0.10 I ~'J V
0.0
fJ rl --11 .f>.
o.ClI M rl ~
0.00 ...J ~ III/
0. l1li
'I. VJ II ~'!.J
'J /
V
0116
"
~
~/
0." ~ I'L ~ U! • !,l
~
~
--
0.01 L
I::;::~~ ......
~
"'_ C»~.....
0.01 ~.as.: ~v
0.00 ~~p- ..m../M
0.01 2 ~ 4 5' 7 e QJ 2 S" I ' 7 & 1.0 2 5 4 5 ' 7 4 10.0
"ALUES on..... 'iH .
FADU"'~ GRAPH OF INflUENCE VALUES FOR COMCENTIlATEO SURCHARGE Iv
LOADS AND fOQ UNIFOQM SU~AR'E LOADS OF SAALL EXTENT.
FIGUR.E 9.
Page 10 a
(JIIDO)~/? = (jan) s>/
&
Hl/fl :JqD Oll Nt/7· JIIDOlU l/g";)9 Z/7· q"
.NOI.JJSOd JSlJOM N/ ( 37:J11I3A
Oi1)(:JY~) ~'l/YHJlIns .1N7ISNt?Ji. lJO ilN/l-illJJN1' JlnaN()J
at J.~dSi111 HJ/II ODnt A77Y'RtJ.;N~ YglJY rBOfl()7 :J/J.YJS :9
t
'g
I
(pOO)PI - (IiqDO)J>/ - (JPI{O) PI + (l{:JOO) PI =('iP:Jq) PI
.,
/ •-
7 e -_ -~
, - - -- ::- ~ .:o ,",0
j I
I
I
I
I
It - - . I :
I
•... " 0 I
" '---.
Page 11.
2. Socketted Pipes
When installing R.R.J. or S & S pipes, the bedding
must be shaped to provide even bearing along the
pipe barrel with provision made for the socket
by excavating a chase to prevent the socket from
bearing upon the foundation.
3. Joint Failures
Uneven resistance in the foundation, such as the
presence of natural or artificial hard or soft,
spots will unduce dangerous beam action or excessive
local loading in all pipelines and may cause joint
failure.
. .. /12
Page 12.
4. Settlement
Engineers should consider directing that the layer
of fill above a pipeline, layed with embankment
conditions, be given less than normal compaction, so
as to minimise the formation of a bump in the
surface above a pipe.
5. Markings
Pipes which have marks indicating the crown or invert,
should be laid strictly in accordance with the
markings. This is very important for proper
performance of pipe with elliptical reinforcement.
6. Sand Backfilling
Where trenches are backfilled with sand a ten (10)
foot length of subsoil drain should be constructed
at the bottom of the trench, immediately upstream
from each drainage pit or headwall. The upstream
end of the subsoil drain should be sealed with
cement mortar and the downstream end shall discharge
through the wall of the pit/headwall.
7. Strutting
In the case of pipes four (4) feet or more , in diameter
laid in situations where embankments are to be more
than ten (10) feet high, measured above the invert of
the pipe, pipes should be stiffened temporarily by
interior strutts, erected before filling is placed.
One strutt should be placed in a vertical position
at each pipe joint and thence at a spacing not
greater than four (4) feet. Strutts should bear
against a sill, laid along the invert and a cap
bearing against the crown of the pipe.
8. Jointing
The faces of the pipes to be jointed should be
thoroughly wetted, then butted as tightly as possible
against each other. The space between the abutting
ends of the pipes shall not exceed one half per cent
of the pipe diameter. The joint should be sealed
with mortar, both on the inside and outside of the
pipe to give neat smooth surfaces, uniform with the
inside and outside surfaces of the pipe. Mortar
joints should be protected from the sun and if
necessary covered with earth or wet bags to prevent
rapid drying of the mortar for at least 48 hours
after placing.
9. Headwalls
In order to minimise the effect of disturbance
during construction of headwalls, the joint between
the end pipe and the remainder of the pipeline
should not be filled with mortar until after the
headwall has been constructed.
· .. /13
,
Page 13.
Summary
It is necesaary to appreciate that proper supervision of
site work and good worlonanship are , essential to the
control and achievement of the des~gn values of both the
load and the load factor, and to the reduction or
elimination of secondary loading. Thus, excessive
trench widths increase the fill and surcharge loads on
all pipes in "narrow" trench conditions; inadequate
depth and uneven compaction of the bedding and
backfilling material, adversely affect the load factor
and so reduce the in-service strength of pipelines;
and excessive local loading during construction, along
with the vibrations which frequently accompany them,
may - collectively induce excessive local loading which
will result in unnecessary cracking of the pipes.
References:
-'