Beruflich Dokumente
Kultur Dokumente
This paper was prepared for presentation at the SPE Annual Technical Conference and Exhibition held in Amsterdam, The Netherlands, 27–29 October 2014.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
It was more than a decade ago that the visionaries of Project Azure predicted that possibly by 2004, a
complete floating LNG chain could be built including floating FPSO (FLNG) and a floating LNG FSRU
(Floating Storage, Regasification Unit), linked by LNG shuttle tankers transporting LNG from the FLNG
to the FSRU. Today in 2014, the chain still does not exist. Although there are many floating LNG
receiving terminals operating successfully around the world, the elusive FLNG has still not materialized.
However, now that construction has started on Shell’s Prelude and Petronas’s PFLNG-1, realization of the
vision of floating LNG chain is imminent.
Many technology advancements have combined to make floating LNG chain a reality. Maturation of
subsea well and control systems have mitigated the risks of subsea well operations. Proven glycol (MEG)
and other regenerative hydrate management systems have allowed longer tie-back distance. Cost-effective
mooring systems for large FPSO, flexible flow-lines and catenary risers have enabled floating system of
FLNG size to be seriously considered. However, it is the advance of floating LNG technologies that have
evolved over the past 20 years that finally tipped the risk-reward equation. Technologies such as offshore
ship-to-ship LNG transfer, motion tolerant processing and rotating equipment, LNG spill and gas safety,
and deep water cooling water lift systems have matured to an acceptable level.
The rewards of FLNG are very compelling. Major cost savings can be achieved by eliminating:
● Well head/production platform(s)
● Processing platform to facilitate gas treating, liquids recovery and stabilization
● FSO for condensate and NGL products
● Gas compressor and pipeline to transport gas to an onshore LNG plant
and replace with a FLNG system located in the field. There are also the intangible cost savings such
as efficiency gains by constructing the entire system in a ship yard, material and manpower logistics, and
shorter project duration. In places where space constraint and regulatory restrictions make land-based
LNG liquefaction and regasification difficult, FLNG and FSRU are cost-effective alternatives.
This paper will present the economics drivers that make floating LNG chain attractive to producers and
buyers alike, and the many conventional production technologies and those unique to FLNG that
combined to enable FLNG chain to be developed with confidence. The realization of floating LNG chain
will enhance the economics of LNG as a preferred fuel.
2 SPE-170600-MS
Introduction
More than a decade has passed since the conclusion of Project Azure, a development program funded
under the European Union THERMIE program, for a floating LNG chain, i.e. a floating FPSO (FLNG)
and a LNG floating storage, regasification unit (FSRU), linked by LNG shuttle tankers transporting LNG
from the FLNG to the FSRU, which delivers gas into the pipeline grid onshore. The goal of the project
was to position the participants to start Front End Engineering Design (FEED) that leads to real field
development projects. The Azure consortium, made up of experienced LNG EPC contractors, technology
providers, classification authorities, and 5 major International Oil & Gas Companies, concluded in March
2000 that a FSRU can be built and operated safely within 3 years and a FLNG within 4 years.
The consortium was not too far off on the FSRU, as a Storage Regasification Vessel (SRV) was
started-up in 2005 for the Gulf Gateway project in the USA, and a full FSRU in 2008 for the Bahia Blanca
Gas Port in Argentina. Currently, there are13 FSRU/FSU projects in operation, 11 under construction, and
more than 8 being considered. Wood Mackenzie reported import through FSRU terminals totaled nearly
10 million tons in 2012 and will comfortably exceed that level in 2013.
In contrast, there is still no FLNG in operation anywhere in the world. Why is it taking so long for
floating LNG chain to become a reality?
The missing link in the chain, of course, is a FLNG (FPSO for LNG production in the field). It is the
most technologically complex and costly piece of the system. Although at the conclusion of Project Azure,
there did not appear to be any “show stoppers” than would prevent FLNG to be built in 4 years, it is not
until recently that all the necessary technologies have matured and applied individually that the first-of-
a-kind risks associated with the entire system have become acceptable.
Technology Enablers
Discussion of LNG facility begins with the liquefaction process, and FLNG is no different. The industry
has conducted numerous studies and the conclusion is that all the commercially available technologies are
acceptable. As with onshore plants, the selection is more to do with operator experience and preference
SPE-170600-MS 3
than technical attributes. What is more important is the marinization of the process and mechanical
equipment to accommodate the space limitation and vessel motions.
Reliable offshore ship-to-ship LNG transfer in all but the worst storm conditions is a must. Systems for
both tandem and side-by-side loading have been developed and qualified. Tandem loading has the
advantage of being able to tolerate rougher seas and familiar to mariners for open sea oil transfer. The
disadvantage is that custom built or specially modified LNG carriers are needed to accept LNG at the bow.
All existing carriers have LNG manifolds at the side of the vessel. Two major tandem loading configu-
4 SPE-170600-MS
Conclusion
Realization of the floating LNG chain has been a long process, some 25 years in the making. After more
than a decade since completion of Project Azure, the last link in the chain has finally been forged with
the launching of Shell’s Prelude FLNG hull. Much of the credits can be attributed to companies like Shell
and ConocoPhillips who have the perseverance and focus to devote resources toward the research and
development of all the necessary floating LNG process technologies. However, FLNG also benefited from
industries relentless advances into further and deeper offshore. Much of the enabling technologies for deep
water production can be directly applied to FLNG. Reliable subsea well and control systems have
mitigated the risks of well operations. Glycol (MEG) and other regenerative hydrate management systems
proven on deep water platforms have allowed longer tie-back distance. Robust subsea architecture and
hardware have reduced failure rate and need for frequent invention. Cost-effective mooring and risers
systems have enabled floating system of FLNG massive size to be engineered with confident.
All these and more industry-wide technological advances have complimented the research and
development that are exclusive to FLNG. Technologies such as offshore ship-to-ship LNG transfer,
motion tolerant process and rotating equipment, LNG spill and gas safety, and membrane containment
system that can withstand sloshing loads in partially filled tanks. The success of FLNG will hinge on the
meticulous integration of the complimentary deep water production and floating LNG technologies.
The pioneers of FLNG are challenged by first-of-a-kind uncertainties. Not all FLNG technologies are
field proven. Some can only be qualified through computer simulations and pro-type testing. However, the
value addition of FLNG is worth the risk. Billions of dollars of NPV may be gained over a conventional
offshore production, pipeline and onshore LNG plant development. Now that Shell Prelude FLNG vessel
has been launched and completion is imminent, the vision of a floating LNG chain will finally be realized.
Acknowledgments
The author thanks Shell, FMC, FRAMO, ConocoPhillips, Saimpan, Petronas, IHI, ThyssenKrupp and
Technigaz for the graphics in the paper; and the ConocoPhillips colleagues who provided information and
support in the marine and subsea disciplines.