S No.
Project Cost 1
Sl. No. Component Amount (Rs. Lacs)
1 Land 2,160.00
2 Basic Enabling Infrastrcture
Site Development and Compound Wall 989.00
Road Network 1,853.00
Storm Water Drainage 550.00
Water Supply System 244.00 2
Sewerage System 114.00
Solid Waste Management System 17.00
Power Supply System 1,150.00
Street Lighting 109.00
Landscaping 50.00
IT and Telecom 25.00
3 Common Facilities
Administration Complex 257.00
Plastic Product Evaluation Centre 639.00
Warehouse 418.00
Truck Parking 21.00 3
Hostel and Staff Accommodation 500.00
4 Equipment 975.00
5 Soft Intervention 70.00
6 Contingenciees and Pre-operatives 158.00
7 Design, Engineering and Supervision Fees 277.00
8 Financing Charges 32.00
9 IDC 69.00
Total Project Cost 10,677.00
Means of Finance
Sl. No. Source Amount (Rs. Lacs)
1 Grant from GoI 4,000.00
2 Unsecured Advance from IDCO to SPV 2,160.00
3 Contribution from SPV/ Other Stakeholder 2,931.00
4 Loan 1,587.00
Total Means of Finance 10,678.00
cheme for Development of Plastics Park
Total Cost (Land + Infra.)/ acre - Without Grant 152.70 Rs. Lacs
Grant Working
Total Infrastructure Development Cost 8,485.00 Rs. Lacs
GoI Grant (DCPC) 4,000.00 Rs. Lacs
Net Infrastructure Development Cost 4,485.00 Rs. Lacs
Total Cost (Land + Infra.)/ acre - With Grant 95.32 Rs. Lacs
Seafood Park, Deras - Scheme for De
Means of Finance
Sl. No. Source Amount (Rs. Lacs)
1 Grant from MoFPI 5,000.00
2 Grant from GoO 1,500.00
3 Promoters Contribution 3,913.68
4 Loan 3,000.00
Total Means of Finance 13,413.68
, Deras - Scheme for Development of Food Parks
Grant Working
Total Infrastructure Development Cost 12,569.86
GoI Grant (DCPC) + GoO Grant 6,500.00
Net Infrastructure Development Cost 6,069.86
Rs. Lacs
acres
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Rs. Lacs
Infovalley EMC - Scheme for Development of Electr
S No.
Project Cost 1
Sl. No. Component Amount (Rs. Lacs)
1 Basic Development
Site Development & Boundary Wall 1,631
Internal Roads 2,079
Storm Water Drains 989
Street Lighting 352
Landscaping 50 2
2 Essential Services
Water Supply/ Disposal/ Harvesting 767
Sewage Lines 531
Solid Waste Management System 25
Electricity Distribution 1,956
Warehouse & Packaging 1,154
3 Support Services
Telecom & IT Infrastructure 40
R&D Centre 297
4 Manufacturing Support
Flatted Factory Complex 810
Production Support 1,123
Equipments 6,177
5 Common Facilities 3
Administration Complex 446
Logistics/ Truck Parking 59
Hostels 714
6 Pre-Operatives
Consultancy / Proj Management Fees 456
BG Charges 119
IDC 433
7 Administrative Expenses 277
8 Margin Money for WC 32
Total Project Cost 20,517
Means of Finance
Sl. No. Source Amount (Rs. Lacs)
1 Grant from GoI 9,511.00
2 Grant from GoO 2,500.00
3 Contribution from SPV/ Other Stakeholder 5,300.00
4 Loan 3,205.00
Total Means of Finance 20,516.00
e for Development of Electronics Manufacturing Cluster
Total Cost (Land + Infra.)/ acre - Without Grant 264.66 Rs. Lacs
Grant Working
Total Infrastructure Development Cost 20,485.00 Rs. Lacs
GoI Grant (DeitY) + GoO Grant 12,011.00 Rs. Lacs
Net Infrastructure Development Cost 8,474.00 Rs. Lacs
Total Cost (Land + Infra.)/ acre - With Grant 160.96 Rs. Lacs
Bhadrak Apparel Park - Scheme for Integ
S No.
Project Cost 1
Sl.No. Project Component Amount (Rs. Lacs)
1 Land 2,000.00
2 Site Development and Compound Wall 1,244.00
3 Internal Roads 977.00
4 Storm Water Drainage 647.00
5 Water Supply System 585.00
6 Sewerage Collection System 257.00 2
Electrical Supply System and Street
7 Lighting 477.00
8 Landscaping 93.00
Adminsitration Building and Other
9 Common facilities: 412.13
Admin Block 63.00
First aid center 10.50
Creche 31.50
Service Area 16.00
Workers Canteen 60.00
Display Hall 31.50
Banking 21.00
Trade Center 150.00
Security 9.00
Contingency @10% 19.63
10 Miscellaneous Fixed Assets 200.00
11 Pre-operatives 147.00
12 IDC 341.00
13 MM for Working Capital 22.00
Total Project Cost 7,402.13
Means of Finance 3
Sl. No. Source Amount (Rs. Lacs)
1 Grant under SITP 1,957.00
2 Promoters Contribution 1,946.00
3 Loan 3,500.00
Total Means of Finance 7,403.00
Park - Scheme for Integrated Textile Parks
Total Cost (Land + Infra.)/ acre - Without Grant 123.17 Rs. Lacs
Grant Working
Total Infrastructure Development Cost 5,380.13 Rs. Lacs
GoI Grant (SITP) 1,957.00 Rs. Lacs
Net Infrastructure Development Cost 3,423.13 Rs. Lacs
Infrastructure Development Cost / acre - With Grant 57.13 Rs. Lacs
Total Cost (Land + Infra.)/ acre - With Grant 90.51 Rs. Lacs
Bhadrak Rice Technology Park - Scheme
S No.
Project Cost 1
Sl. No. Component Amount (Rs. Lacs)
1 Land 2,693.00
2 Basic Enabling Infrastructure
Site Development and Compound Wall 1,560.00
Roads 1,331.00
Storm Water Drainage System 686.00
Water Supply system 872.00 2
Sewerage System 572.00
Electrical works 264.00
Street Lighting 130.00
Landscaping 122.00
3 Admin and Other Common Facilities
Admin Block 63.00
First aid center 10.50
Workers Canteen 30.00
Tender Hall 22.50
Banking 21.00
Guest house 42.00
Former Hostel 105.00
Security 9.00 3
Weigh Birdge including building 35.00
Contingencies @ 5% 16.90
4 Core Processing Facilities
Warehouse 650.00
Primary Processing Center (Drier) 225.00
Primary Processing Center (Cleaner,
DeStoner,Grader) 225.00
Farmers input Center for seeds and
fertilizers 100.00
Farmers information center and training
center 30.00
QC Labs 42.00
Engineering Workshops with dedicated
transformer (welding, barbending, etc.,) 60.00
Contingencies @ 5% 66.60
5 Miscellaneous Fixed Assets 200.00
6 Pre-operatives 225.00
7 IDC 293.00
8 MM for Working Capital 23.00
Total Project Cost 10,724.50
Means of Finance
Sl. No. Source Amount (Rs. Lacs)
1 Grant from MoFPI 3,745.00
2 Grant from GoO 1,498.00
3 Promoters Contribution 2,481.00
4 Loan 3,000.00
Total Means of Finance 10,724.00
logy Park - Scheme for Development of Food Parks
Total Cost (Land + Infra.)/ acre - Without Grant 123.33 Rs. Lacs
Grant Working
Total Infrastructure Development Cost 8,008.50
GoI Grant (MOFPI) + GoO Grant 5,243.00
Net Infrastructure Development Cost 2,765.50
Total Cost (Land + Infra.)/ acre - With Grant 62.91 Rs. Lacs