CALCULO DE COSTO FINANCIERO

PRESUPUESTO PROGRAMA DE OBRA


C. DIRECTO $ 3,000,000.00 MES % % ACUMULADO
C.INDIRECTOS 9% $ 270,000.00 1 10% 10%
SUMA 1 $ 3,270,000.00 2 18% 28%
FINANCIAMIENTO 6.32% $ 206,664.00 3 29% 57%
SUMA 2 $ 3,476,664.00 4 31% 88%
UTILIDAD 8.53% $ 296,559.44 5 12% 100%
IMPORTE $ 3,773,223.44

FACTOR DE SOBRE COSTO 1.2577411464

CONCEPTO 1 2 3 4 5 6 7 TOTAL

EGRESOS
C. DIRECTO $ 300,000.00 $ 540,000.00 $ 870,000.00 $ 930,000.00 $ 360,000.00
C. INDIRECTO $ 27,000.00 $ 48,600.00 $ 78,300.00 $ 83,700.00 $ 32,400.00
SUMA EGRESOS $ 327,000.00 $ 588,600.00 $ 948,300.00 $ 1,013,700.00 $ 392,400.00

INGRESOS
ANTICIPO 30% $ 1,131,967.03 113196733%
ESTIMACIONES $ 366,944.26 $ 660,499.66 $ 1,064,138.34 $ 1,137,527.19 $ 440,333.11 $ 3,669,442.56
AMORTIZACION ANT -30% -$ 110,083.28 -$ 198,149.90 -$ 319,241.50 -$ 341,258.16 -$ 132,099.93 -$ 1,100,832.77
SUMA INGRESOS $ 1,131,967.03 $ - $ 256,860.98 $ 462,349.76 $ 744,896.84 $ 796,269.03 $ 308,233.18 $ 3,700,576.82

ING- EGR $ 804,967.03 -$ 588,600.00 -$ 691,439.02 -$ 551,350.24 $ 352,496.84 $ 796,269.03 $ 308,233.18


ING- EGR ACUM $ 804,967.03 $ 216,367.03 -$ 475,071.99 -$ 1,026,422.22 -$ 673,925.39 $ 122,343.65 $ 430,576.82

COSTO FINANCIERO 34.4% $ 276,908.66 $ 74,430.26 -$ 163,424.76 -$ 353,089.2 -$ 231,830.33 $ 42,086.21 $ 148,118.43 -$ 206,800.44
% DE FINANCIEMIENTO 6.32%
CAT febrero 2012
Santander prestamo personal 34.40%
Bamanex pretamo personal 69%