Sie sind auf Seite 1von 7

CONTROL NETWORKS AS A BASIS FOR MAPPING

1. Horizontal Control Networks


National horizontal control networks were established from the 18th century until the 1960's,
with the networks' design, observation, and computation changing with the available techniques.
Computations were carried out on a reference ellipsoid fitted to the survey area. Since the 1960's,
spatial geodetic methods have allowed orientation of the classical networks with respect to the
global reference system.

1.1. Design and Observation


Horizontal control networks are realized by trigonometric (triangulation) points, which in
principle should be distributed evenly over the country. One distinguishes between different
orders of trigonometric points, from first order or primary (station separation 30 to 60 km) to
second order (about 10 km) to fourth or even fifth order (down to one to two km) stations. The
maximum distance between first-order points was determined by the terrestrial measurement
methods, which required intervisibility between the network stations. Consequently, first and
some second-order stations were established on the top of hills and mountains; observation
towers (wooden or steel constructions with heights of 30 m and more) were erected especially in
flat areas. The stations have been permanently marked by underground and surface monuments
(stone plates, stone or concrete pillars, bolts in hard bedrock).
Eccentric marks have been set up in order to aid in the recovery and verification of the center
mark.
Classical first and second-order horizontal control networks have been observed by the methods
of triangulation, trilateration, and traversing.

a) Triangulation with baseline extension net and b) Trilateration with Laplace


Laplace azimuth azimuth

Notes by Sichangi
Page 1 of 7
In triangulation, all angles of the triangles formed by the trigonometric points are observed with
a theodolite (a). The instrument is set up on the observation pillar or tower; at large distances the
targets are made visible by light signals. Either directions (successive observation of all target
points) or angles (separate measurement of the two directions comprising one angle) are
observed in several sets (i.e., in both positions of the telescope), distributed over the horizontal
circle of the theodolite. The scale of a triangulation network is obtained from the length of at
least one triangulation side, either derived from a short base line through a base line extension
net or measured directly by a distance meter. Astronomic observations provide the orientation of
the network, whereas an astronomic azimuth is needed for the horizontal orientation.
In extended networks, base lines and Laplace stations often were established at distances of a
few 100 km in order to control the error propagation through the network with respect to scale
and orientation (effects of lateral refraction).
Trilateration employs electromagnetic distance meters in order to measure the lengths of all
triangle sides of a network, including diagonals (b). At least one Laplace azimuth is needed for
the orientation of the net. Electromagnetic distance measurements put less demands on the
stability of observation towers as compared to angular measurements, and the use of laser light
and microwaves makes the method more independent from weather conditions.
Traverses combine distance and angular measurements, where the traverse stations are arranged
along a profile. Again, a Laplace azimuth is required in order to orientate the traverse. Traversing
represents a very effective and flexible method for establishing horizontal control networks, with
no more need to establish stations on hilltops. It has been employed primarily for the
densification of higher order networks, with the coordinates of the existing control points
providing orientation.
Horizontal control networks can also be formed by combining the methods of triangulation,
trilateration, and traversing. Such networks are very stable in design, and allow establishment of
first and second-order control simultaneously.
Optimization methods have been developed for the design and survey of trigonometric networks.
Starting from the demands on accuracy and reliability, these methods provide information on the
optimum point configuration and the distribution of the measurements in the network given the
limitations of available equipment and the maximum allowable cost of the survey
Notes by Sichangi
Page 2 of 7
1.2. Resection and intersection
Using these techniques, one can establish the coordinates of a point P, by observations to or from
known points. These techniques are useful for obtaining the position of single points, to provide
control for setting out or detail survey in better positions than the existing control may be.

1.2.1. Intersection
This involves sighting in to P from known positions (see figure below).

a. Intersection by angles
If the bearings of the rays are used, then using the rays in combinations of two, the coordinates of
P are obtained as follows:
In the figure below it is required to find the coordinates of P, using the bearings α and β to P
from known points A and B whose coordinates are EA, NA and EB, NB.

b. Intersection by bearing

Notes by Sichangi
Page 3 of 7
……. (1)

……. (2)

Subtracting equation (2) from (1) gives

……. (3)

……. (4)

Using equations (3) and (4) the coordinates of P are computed. It is assumed that P is always to
the right of A → B, in the equations.
If the observed angles α and β, measured at A and B are used (Figure a above) the equations
become

The above equations are also used in the direct solution of triangulation. The inclusion of an
additional ray from C, affords a check on the observations and the computation.

Notes by Sichangi
Page 4 of 7
1.2.2. Resection
This involves the angular measurement from P out to the known points A, B, C (Figure c below).
It is an extremely useful technique for quickly fixing position where it is best required for
setting-out purposes. Where only three known points are used a variety of analytical methods is
available for the solution of P.

Resection
Method 1

…………….……a
……………….…b

Equating equation (a) and (b)

Thus, knowing θ and (S – θ), the triangles can be solved for lengths and bearings AP, BP and
CP, and three values for the coordinates of P obtained if necessary.
The method fails, as do all three-point resections, if P lies on the circumference of a circle
passing through A, B and C because it has an infinite number of possible positions which are all
on the same circle.

Notes by Sichangi
Page 5 of 7
2. Vertical Control Networks
Vertical control networks have been established separately from horizontal control nets. This is
due to the demand that heights have to refer to the gravity field rather than the ellipsoidal system
used for horizontal positioning. Vertical control networks are determined by geometric leveling
and occasionally by hydrostatic leveling, the control points being designated as bench marks.
According to the leveling procedure and the accuracy achieved, national geodetic surveys
distinguish between different orders of leveling. First-order leveling is carried out in closed loops
(loop circumferences of some 100 km) following the rules for precise leveling. The loops are
composed of leveling lines connecting the nodal points of the network. The lines, in turn, are
formed by leveling runs that connect neighboring benchmarks (average spacing 0.5 to 2 km and
more). The first order leveling network is densified by second to fourth-order leveling.

Leveling network

Leveling lines generally follow main roads, railway lines, and waterways. The benchmarks
consist of bolts in buildings, bedrock, or on concrete posts. Long pipes are set up in alluvial
regions. Underground monuments are established in geologically stable areas in order to secure
the network stability with respect to variations with time. An accuracy of about 1 mm per km is
achieved for first-order networks. They should be re-observed at time intervals of some 10 years,
as regional and local height changes can reach 1 mm/year and more, especially in areas which
experience crustal motion.
Prior to the adjustment of a leveling network, the observed raw height differences have to be
transformed either to geopotential differences or to differences of normal or orthometric heights
by considering surface gravity.
The adjustment then utilizes the loop misclosure condition of zero and is carried out either by the
method of condition equations or, preferably, by the method of parameter variation.

Notes by Sichangi
Page 6 of 7
The vertical datum (zero height surface) is defined by mean sea level (MSL) as derived from tide
gauge records. National height systems may differ by some dm to 1 m, and more, between each
other. They may also differ from the geoid as a global reference surface, which is due to the
effect of sea surface topography. Network distortions arise if the vertical datum is constrained to
MSL of more than one tide gauge.
Leveling networks are characterized by high accuracy, but systematic errors may accumulate
over large distances. Due to the time-consuming measurement procedure, repetition surveys are
feasible only after long time intervals. A more rapid establishment of vertical control networks
can be achieved by trigonometric leveling, and a drastic change is to be expected by GPS-
heighting in connection with precise geoid or quasi-geoid models. In this way, vertical control
networks will be integrated into three dimensional control systems. Geometric leveling will
maintain its importance over short distances, and especially in areas of recent crustal movements,
such as regions of land subsidence and zones of earthquake or volcanic activity.

Notes by Sichangi
Page 7 of 7

Das könnte Ihnen auch gefallen