Sie sind auf Seite 1von 6

Selection of equipment – b) Excavator with bucket Komatsu

PC 400 – productivity –800 m3/per day considered.Option -2 –


Cost working for PC 400: 1 . H i r e c h a r g e s p e r H o u r –
R s . 1 2 0 0 . 0 0 r a t e f o r 1 0 h r s = 1 2 , 0 0 0 2. Cost of Diesel
10 litres per hour @ 70 Rs per litre conside red for 10 hrs
= 7,000 3 . O p e r a t o r w a g e s i n c l u d e d
4. Operator food, accommodation & transport per
day =Rs.300 5 . Wa g e s f o r B a n k s m a n – R s . 4 0 0
TOTAL COST PER DAY = RS.19,700
X2.5(2+1Excavator10days)Excavatorsreq
uired=Rs.49,250perdayandtotalcostestimate
dfor45daysis49,250x45=Rs.22.16lacsSe
lectionofequipment–
c)Excavatorwithbucket–productivity–
300m3/perdayconsidered.Option-3-
CostworkingforHITACHIEX-220:1 .
HirechargesperHour–
 R s . 6 0 0 . 0 0  r a t e  f o r  1 0  h r s  =  6 , 0 0 0 2. Cost 
ofDiesel5litresperhour@70Rsperlit
re considered for10hrs =3,5003 . O p e r a t o r
 w a g e s  i n c l u d e d 4. Operatorfood,accommo
dation&transportperday=Rs.3005 . Wa g e s
forBanksman–
 R s . 4 0 0 TOTALCOSTPERDAY=RS.10,200X
6Excavatorsrequired=Rs.61,200perdayand
totalcostestimatedfor56daysis49,250x4
5=Rs.34.27lacsF ) C o s t  w o r k i n g  f o r  D i s p
o s a l  w o r k s Selectionofequipment–Dozer–
1No,Wheelloader–
1Nos,Tippertruck18m3capacityconsiderin
g800m3disposalofsurplusearth/perdayand
completingtheworkby25days1) Hire chargesf
orDozer –1NosperHour–
Rs.600.00rate for10hrs =8,0002) Hirecha
rges forWheel loader–1NoperHour–
Rs.600.00rate for10hrs =6,0003) Hirecha
rges forTipper–8NoperHour–
Rs.400.00rate for10hrs =32,0004) Costof
Diesel 5litres perhour each@70Rsper
litre considered for10hrs=35,0005 ) O p e r a
t o r  w a g e s  i n c l u d e d 6) Operatorfood,acco
mmodation&transportperday=Rs.3007 ) W
agesforBanksman–
 R s . 8 0 0 TOTALCOSTPERDAY=Rs.84,200pe
rdayandtotalcostestimatedfor25daysis=
Rs.21.20lacs,unitratearrivedfor20,000m3i
sRs.106/m3alsobyusingthesameequipmentsc
anbeusedforremoving&stockingthebalance
requiredearthatnearbysitearea.G ) C o s t  w o r
k i n g  f o r  s a n d  F i l l i n g SupplyofSandasper
specificationbylocalsupplierandspreading&l
evelingbydept.(own)considered.1.
Supply ofsand includingtransporta tion delivery
atsite 18m3Truck –
Rs.6,000.00ratefor18m3=perm3Rs.6,000/18
=Rs.333/m32. CostofShowel forspreading &
leveling thesand –Deprec iation cost–
Rs.266perdayx15daysconsidered=Rs.3,990,
perday200m3productivitytaken,costperm3
=19.95Rs.3. Operator wages permonth–
Rs.20,000permonth required for15days, c
ostperm3=10,000/200=Rs.50/m34. Diesel charg
es4ltrsperhourxRs.70/ltr =Rs.280x10
hrs =Rs.2,800/2 00=Rs.14/m3considered.5. Water
tanker 5,000gallons –
Rs.2,600/trip =2,600/200 =Rs.13/m3conside re d
6. Compactionusingplatecompactor/roller=
Rs.500/day=Rs.2.50/m37. Operatorfood,a
ccommodation&transportperday=Rs.300/2
00=1.50/m3

8 ) Wa g e s  f o r  l a b o u r  f o r  c o m p a c t i o n  –
 R s . 8 0 0 / p e r  d a y, 8 0 0 / 2 0 0  =  R s . 4 . 0 0 / m 3 TOTAL
COST=Rs.437.95/m3xtotalqty3,000m3=R
s.13.14lacs.H ) B O Q  f o r  B i t u m e n  P a v e m e n
t

Surfacedressing&preparation

Penetrationgroutingsemigrouting/fullgrouting

Premixcarpet/SealCoat

HotmixedbituminousmacadamI )    C o s t  W o r
kingforBitumenwork

Surfacedressing&preparation:ConsideringTotalqt
yofareais100mx20mwidth=2,000m
2willbestartedon60thdayasperprogramme.
1. Cost ofShowelfor spreading &leve ling the
earth –Depreciation cost–
Rs.266perdayx10daysconsidered=Rs.2,6602.
Operator wages permonth–
Rs.20,000permonth required for10days, c
ost=Rs.6,6663. Dieselcharges 4liters perhour
xRs.70/ltr =Rs.280x10hrs =Rs.28,000.4 .
Compactionusingplatecompactor/roller=R
s.8000/day=Rs.80,0005. Operatorfood,acco
m m o d a t i o n  &  t r a n s p o r t  p e r  d a y  = R s . 3 0 0 TOTA
LCOST=Rs.1.17lacs.

Sprayingofmetal&bitumenmixintwolayers:
1. Supply costfor bitumento beprocured
fromBongaingaon in Assam–
1,50,000liters@Rs.20/litersconsidered–
costfortotalqty=30.00Lacs2 . T r a n s p o r t a t i o n
costperlitersRs.5.00/Litre=7.50Lacs3.
Wa s t a g e s  1 0 %  =  3 0  +  7 . 5  =  3 7 . 5  *  1 0 %
=3.75Lacs4. Stocking&shiftingtosite
 R s . 1 . 0 0 / l i t r e  = 1 . 5 0  L a c s 5. Cost of10-
20mmmetal delivery atsitefor 2000m2x
0.2mtrht=400m3@600rs/m3=2.400
Lacs6 . W a s t a g e s  1 0 %  =  0 . 2 4  L a c s 7. Co
stofHotmixplant–
Depreciation cost =Rs.4500/day x40daysreq
uired -1.80Lacs8.
Transportation ofhotbituminousmixthrough ti
pper truck–
Rs.4000/day includingdriver&dieselchargesx
40days=1.60Lacs9. Spreading &Layingby
using paver–
Depreciation cost Rs.8,000perday–
costfor40daysis=3.20Lacs10. Operator w
ages permonth–
Rs.20,000permonth required for40days, c
ost=Rs.27,000x4operators=1.08Lacs11. Diesel
charges 10liters perhour xRs.70/ltr=Rs.7
000x40days =Rs.2.80Lacs12. Compaction
using roller10Ton Rs.8000/day x40days 
=Rs.3.20Lacs13. Opera torfood, accommoda tion
&transportperday=Rs.300x8=2,400
x40days–
0.960LacsTOTALCOST=Rs.59.07lacs.J )  
 P u r c h a s e  O r d e r  S c h e d u l e 1. Supply ofBitu
men from assam includingtransporta tion &deli
very atsiteforthetotalqty–1stday–
deliveryintwolots2 . D e l i v e r y  o f  1 s t  l o t 
willbereceivedon46thday3. Deliveryof
2ndlotwillbereceivedon60thday4. O
rderforsupplyofsand,metaltobedone
 o n  1 s t  w e e k K ) P r o g r a m m e  O u t l i n e Tot
alscopewillbeexecutedintwoparts1 . P a
r t  - 1 1.
Excavation,Dozing&disposalofsurpluse
arth–1to25thday2.
Importedmaterials&Sandfilling–
startfrom10thDay–25thdays3.
Surfacepreparation,levelingandcompaction
–26thto46thdays4 . M e t a l  s p r e a d i n g  –
46thdayto60thday5. Bitumenpaveme
nt–61stdayto80thday

2 . P a r t  - 2 1.
Excavation,Dozing&disposalofsurpluse
arth–26thto50thday2.
Importedmaterials&Sandfilling–
startfrom26thDay–46thday3.
Surfacepreparation,levelingandcompaction
47thdayto65thdays4 . M e t a l  s p r e a d i n g
–66thdayto80thday5.
Bitumenpavement–
81stdayto100thdayL )  C o s t  S u
m m a r y : 1. CostforExcavationworks=
Rs.22.16Lacs2. CostforDisposalworks
=Rs.21.20Lacs3. SandFilling =Rs.1
3.14Lacs4. CostofBitumenPavement=
 R s . 6 0 . 2 4  L a c s GRANDTOTALCOST=116.74
LacsM ) B i t u m e n  o r d e r i n g  P l a n : Note:
Averagedailyconsumptionofbitumenis3750Ltrs
.Asafetystockof3daysconsumptionisalway
smaintained.N ) B i t u m e n  I n v e n t o r y  c h a r t :
O ) B i t u m e n  L o g i s t i c  P l a n : 1 . B i t u m e n  s h
allbesuppliedindrums,eachdrumcontai
n i n g  2 0 0  L t r s .  2. Itwillbecarriedin trucks
/longtrailersfromthe loading point ands
hallbeunloadedatsitewithforklift.3 . E a c h 
truckwillcarry50drumsx200Ltrs=
1 0 , 0 0 0  L t r s . 4. Foreachorder qtyof30,000L
trsx5orders,3trucksperordershallbe
engagedforbringinginbitumenfromrefineryto
airportsite.P ) R e c o m m e n d a t i o n s  /  C o n c l u s i o
n s : 1. Asthe project tobeexecuted within s
hort duration anditistime bound,allmaterial
sandequipmentsshallbemobilizedasperthe
aboveplanandHOapprovalsonresourcesshould
notbedelayed.2. Asbitumenisbroughtin 
fromlong distance andthelead timeismore,
itisbettertopostamaterialexpeditorandlo
adingpointforbetterfollowupandensuringtim
elydeliveryatsite.Q ) B i b l i o g r a p h y : 1 . N I
CMARLesssonbook–
ConstructionEquipment&Materialsmanage
m e n t .  2. Other misce llaneous handbooksonco
nstruction equipments &ma teria ls.

Das könnte Ihnen auch gefallen