works(Common SR 2009-10)
Materials Labour charges
SL.NO Particulars Unit
rate in Rs. (Casual) in Rs
1 2 3 4 5
I RCC Poles
a) 9M 145kg WL Nos. 4241 466
b) 9M 150kg WL Square section Nos. 5695 466
c) 8M 115kg WL Nos. 3011 373
II PCC Poles
8M PCC Poles 140kg WL Nos. 1871 373
III PSC Poles
a) 9M 200kg WL Nos. 2658 466
b) 8M 200kg WL Nos. 2214 373
IV Pre-Stressed Tubular Spun Pole
11M Long Nos. 13250 1250
Double Pole Structure complete including 5
V KG , 8SWG G.I. Wire for Structure
Grounding
a) 9M RCC Poles Set 12267 1430
Note: The items V, VI, VII includes the cost of poles, structure materials & about 10 to 12 kg of G.I wire required for
earthing of structure materials.
1
Materials Labour charges
SL.NO Particulars Unit
rate in Rs. (Casual) in Rs
265
Providing guarding at Road Crossings, Telephone Line
XVII mtr 39 (each upto a span
Crossings . (excluding fixing of necessary cross arms)
of 60 mtrs)
2
Materials Labour charges
SL.NO Particulars Unit
rate in Rs. (Casual) in Rs
265 (each
Providing guarding between HT & LT line. (excluding fixing
mtr 39 upto a span of 40
of necessary cross arms)
mtrs)
3
Materials Labour charges
SL.NO Particulars Unit
rate in Rs. (Casual) in Rs
As per Drawing
No.
a) Guy concreting with Boulders, Mud & Sand 45 -
BESCOM/GM/CP/
7/dt: 24.10.07
Providing Coping for Poles with CC 1:2:4 (As per
CMT -
actuals)
1 for 15/25 kVA DTC with CT ratio 50/5 Set 9466 504
2 for 50/63 kVA DTC with CT ratio 100/5 Set 9148 504
3 for 100 kVA DTC with CT ratio 150/5 Set 8923 504
4 for 250 kVA DTC with CT ratio 400/5 Set 8923 504
5 for 500 kVA DTC with CT ratio 800/5 Set 8923 504