Beruflich Dokumente
Kultur Dokumente
ROSATOM:
Financing Opportunities and Challenges
Vyacheslav Ivanov
May 2016
Global Nuclear Technology Footprint
JSC Rosatom Energy International - subsidiary of State Corporation ROSATOM – integrator and project developer of ROSATOM solutions in
Russian nuclear business abroad
1
Tested Nuclear Technology – key reference factor for financing
2
Russian nuclear technology – Water-Water Power Reactor (VVER)
* According to WANO it is one of the most reliable reactors in the world today.
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to Rosatom and its affiliated companies. Rosatom disclaims all responsibility for any and all mistakes, quality and
completeness of the information. 3
ROSATOM VVER Technology
Nuclear Power Plants (NPP) Perspective pipeline
BOO*
South Africa
Argentina 8
1
43
25
24
4
Our Approach to Financing New NPP Generation
Financing terms and structures for new NPP are unique and driven by:
Rosatom has successful track record arranging multibillion financing for Russia design NPPs (both EPC and
BOO models) new NPP generation across the world.
5
Contracting and risk sharing
6
Representative Financing Structure: EPC plus IGA Financing
Focus on Intra-Government Debt
Russian
Rosatom Family Host Country
Government
7
Representative Financing Structure: BOO plus Financing
Focus on project financing and international economics
Host Country
New Investors REIN
Consortium
8
Hanhikivi-1 Case. Project snapshot
• Project: construction of Hanhikivi 1 nuclear power plant on a greenfield site Pyhäjoki in Northern Finland, Baltic Sea
• Mankala structure: NPP will produce electricity which will be sold to the shareholders at cost (Finnish “Mankala model”)
• Shareholder base: majority shareholder is Voimaosakeytiö SF (“VSF”) which comprises some 47 Finnish corporates
(industrials and utilities). Rosatom also became shareholder in April 2014.
• Local support and government approval: In 2010, the Government of Finland and the Finnish parliament granted their
permit (Decision-in-Principle) to FV for the Project. The Project also benefits from strong and consistent local support
• Vendor and technology: Rosatom is the exclusive turn-key EPC contractor providing its AES-2006 / VVER nuclear reactor
technology (1,200MW). Its Leningrad 2 is the reference plant
• Timetable: It is currently planned that construction works will commence in 2018, and that the commercial operation date will
occur in 2024
• Project funding: project costs are to be funded 72.5% by debt financing and 27.5% by equity
• Competitiveness: Target Mankala price over 2024-2035 is expected to be highly competitive in Nord Pool.
Key project strengths Strong and balanced financing Proven and competitive Russian
structure technology
9
Finland Sources of Funding
• Rouble devaluation
Other EUR ~0.5 billion ~EURIBOR+300(*) contributed
Finnish real yearly prices SKM, forecast € / MWh Domestic electricity balance (base case) TWh
70 120
SKM — forecast 102
57 96 93 95 95 98
60 FV Mankala 55 100 90
50 87
82
87 84 85 86 82 90
50 46 47 78 77 76
43 80 74
42 70 70 68
40 38 38 38 39 38
42 39 60
30
38 38 38
35
40
20
20
10
0 0
2015f 2020f 2025f 2030f 2035f 2007 2008 2009 2010 2011 2012 2015 2020 2025 2030 2035
High Central Low
Source: SKM (all except “Mankala price”), FV (“Mankala price” only) Source: SKM Production Consumption
2 500 10 000
2 000 8 000
1 500 6 000
1 000 4 000
500 2 000
- -
(500) (2 000)
(1 000) (4 000)
(1 500) (6 000)
(2 000) (8 000)
(2 500) (10 000)
Cummulative FCFF, right scale Revenue, left scale Equity, left scale NWF funds, left scale Other commercial debt, left scale FCFF, left scale
11
Hanhikivi-1. Preliminary project schedule
2007 2010 Dec. 2013 July. 2017 Jan.2023 Mar.2023 Jan.2024 Dec.2025 2083
First criticality
Provisional Acceptance
FV Project EPC, SHA
company signed
Construction
established permit Commercial Operation
Decision-in- Decommissioning
Principal
Final work acceptance
granted to FV
NWF drawdowns
ECA
drawdowns
12
NPP in Jordan. Project snapshot
• Government approval: The Project benefits from strong and consistent Egypt Israel
political and state support
Saudi Arabia
• Vendor and technology: Rosatom is to be the exclusive turn-key EPC Syria
contractor providing its AES-92/VVER nuclear reactor technology (1000 Iraq
MW)
• Timetable: It is currently planned that engineering and designing works
will commence in 2017, and that the commercial operation date will
occur in 2025
• EPC contract price (estimation): ~10+ bn US dollars
13
NPP in Jordan. Preliminary contractual and shareholder structure
1500
0
Jordan imports more than 97% of energy,
Current installed capacity accounting for 20% of GDP.
Installed capacity, including commissioned units and imported capacity
Oct. 2013 July 2014 May 2016 Dec.2017 2025 2027 2085
Unit 1
Unit 2
GK Rosatom Ratification
was elected of the IGA
NPP construction
as a preferred for the
documents package
supplier of the construction
signing (PPA, EPC
first NPP in and
Signing of contract, NFS Decommissioning
Jordan operation of
Project contract, SHA) of the first unit
NPP by the
Development Parliament
Agreement of Jordan
16
Strong Relationships with Capital Providers
NPP Financing Considerations
(1)
Russian State, Ministry of Finance, Ministry of Economic Development, National Wealth Fund (NWF), Export Insurance Agency of Russia (EXIAR), State Corporation Bank for Development and
Foreign Economic Affairs (VEB), Savings Bank of Russia (Sberbank), International Trade Bank (VTB), ECAs such as COFACE, EGAP, NEXI, ECGD and EKN
17
THANK YOU FOR YOUR ATTENTION
18