Sie sind auf Seite 1von 11

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/220592837

Sizing of Energy Storage for Microgrids

Article in IEEE Transactions on Smart Grid · March 2012


DOI: 10.1109/TSG.2011.2160745 · Source: DBLP

CITATIONS READS

253 1,861

3 authors, including:

Chen Shuaixun Mingqiang Wang


DNV KEMA Energy and Sustainability Shandong University
28 PUBLICATIONS 645 CITATIONS 23 PUBLICATIONS 490 CITATIONS

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Energy-Efficient Driving for Railway Vehicles View project

All content following this page was uploaded by Chen Shuaixun on 09 December 2014.

The user has requested enhancement of the downloaded file.


142 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 1, MARCH 2012

Sizing of Energy Storage for Microgrids


S. X. Chen, Student Member, IEEE, H. B. Gooi, Senior Member, IEEE, and M. Q. Wang, Student Member, IEEE

Abstract—This paper presents a new method based on the cost-


benefit analysis for optimal sizing of an energy storage system in
a microgrid (MG). The unit commitment problem with spinning
reserve for MG is considered in this method. Time series and feed-
forward neural network techniques are used for forecasting the
wind speed and solar radiations respectively and the forecasting
errors are also considered in this paper. Two mathematical models
have been built for both the islanded and grid-connected modes
of MGs. The main problem is formulated as a mixed linear in-
teger problem (MLIP), which is solved in AMPL (A Modeling Lan-
guage for Mathematical Programming). The effectiveness of the
approach is validated by case studies where the optimal system
energy storage ratings for the islanded and grid-connected MGs
are determined. Quantitative results show that the optimal size of
BESS exists and differs for both the grid-connected and islanded
MGs in this paper.
Index Terms—Energy storage system, microgrid, optimal sizing,
renewable energy.
Fig. 1. A simple architecture of microgrid.

I. INTRODUCTION
power systems. How to mitigate renewable power intermitten-
cies, load mismatches, and negative impacts on MG voltage sta-

T HE MICROGRID (MG) concept assumes a cluster of


loads and microsources operating as a single controllable
system that provides both power and heat to its local area. This
bility are some key problems to be solved. A potential candidate
solution to the identified problems is using ESS to store elec-
trical/renewable energy at the time of surplus and redispatch it
concept provides a new paradigm for defining the operation of appropriately later when needed [2].
distributed generation. The MG study architecture is shown in ESS plays an important role in the MG, which is desirable to
Fig. 1 [1]. It consists of a group of radial feeders, which could shave the peak demand and store the surplus electrical/renew-
be part of a distribution system. There is a single point of con- able energy [3]. Sizing of ESS is to be considered first when
nection to the utility called point of common coupling (PCC). considering ESS in the MG. Much research works have been
The MG also has microsources consisting of a photovoltaic done to address this question. Battery storage is being used
(PV) system, a wind turbine (WT) system, two microturbines in conjunction with renewable energy resources, i.e., solar and
(MTs), a fuel cell (FC), and an energy storage system (ESS). wind, where they provide a means of converting these nondis-
The fuel input is needed only for the MT and FC as the energy patchable and highly variable resources into dispatchable ones
input for the WT and PV comes from wind and sun. To serve [4]–[6]. ESS could also increase the reliability of power systems
the load demand, electrical power can be produced directly by [7]. The sizing problem of the ESS for customers of time-of-use
MT, FC, PV, and/or WT. The upstream power system can also (TOU) rates has been addressed in [8]. References [9] and [10]
support the power in grid-connected MGs. Furthermore, the introduce the ESS sizing problem for only one kind of renew-
central controller (smart energy manager) is the main control able energy to cover the peak load requirement.
interface between the upstream grid and the MG. The central This paper focuses on determining the size of ESS for MGs. It
controller has the main responsibility for optimizing the MG aims to find the optimal size of ESS for MGs by formulating it in
operation, or alternatively, coordinating the actions of local the unit commitment problem both in the islanded and grid-con-
controllers to produce the optimal output. nected modes of MGs. This paper also tries to find the relation-
With renewable energy sources connected online, their inte- ship between the size of ESS and the total cost of the MG. Con-
gration and control pose more challenges to the operation of sidering the daily cycle of the solar and wind pattern in Singa-
pore, ESS will also follow the same charge and discharge cycle
Manuscript received February 22, 2011; revised April 22, 2011; accepted everyday. Typical results will be obtained based on the case
June 21, 2011. Date of publication August 12, 2011; date of current version
study of a chosen day in this paper. Most MGs operate in the
February 23, 2012. Paper no. TSG-00057-2011.
The authors are with the School of Electrical & Electronic Engineering, grid-connected mode. However, islanded MGs are also built for
Nanyang Technological University, Singapore (e-mail: nosper@pmail.ntu. isolated islands or remote places. That is why both the grid-con-
edu.sg; ehbgooi@ntu.edu.sg; wang0367@ntu.edu.sg).
nected and islanded modes of MGs are considered.
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. For grid-connected MGs, the upstream grid can support
Digital Object Identifier 10.1109/TSG.2011.2160745 power to the MG during the peak load period. The extra power

1949-3053/$26.00 © 2011 IEEE


CHEN et al.: SIZING OF ENERGY STORAGE FOR MICROGRIDS 143

generated by renewable energy generators during the low load


period can be sold back to the upstream grid. Market prices
need to be considered in this mode and the objective function
is to maximize the market profit. In the islanded mode, the MG
must cover the power balance by itself. ESS is used to store the
extra power generated by renewable energy resources during
the low load period and redispatch it during the peak load
period. The objective function is to minimize the total cost.
In Section II, system models are introduced. Time series and
feed-forward neural network (FNN) techniques are used for
forecasting the wind speed and solar radiations respectively.
The cost functions of the distributed generators and ESS are
also presented. The main problem is formulated in Section III.
The method of choosing the optimal size of ESS for the is- Fig. 2. Measured and forecasted wind speed using time series model.
landed MG is shown in Section III-A. The mathematical model
for the grid-connected MG is introduced in Section III-B. The
Some error exists between the calculated wind power and the
algorithm developed and used to solve the optimal size of
real wind power due to the error in the forecasted wind speed.
ESS is shown in Section III-C. A case study and analysis of
It is expressed as a root mean square error (RMSE) for the time
the results are shown in Section IV. The final conclusion is
series model and has been addressed in many research papers
presented in Section V.
[12], [18]. The RMSE of the installed wind turbine capacity for
the day ahead forecast is obtained at 13% in this paper.
II. SYSTEM MODELING
B. Solar Photovoltaic Power
A. Wind Power
Solar photovoltaic power is a generic term used for electrical
Wind power is the electrical power generated by wind tur- power that is generated from sunlight. A solar photovoltaic
bines, which are installed in locations with strong and sustained system converts sunlight into electricity. The fundamental
winds. The wind pushes against the fan blades of a wind turbine, building block of solar photovoltaic power is the solar cell
mounted on a tower at an elevation high above and away from or photovoltaic cell [19]. A solar cell is a self-contained
ground obstructions and obstacles. Wind turbines have no con- electricity-producing device constructed of semiconducting
trol over their energy output and are constrained by their phys- materials. Light strikes on the semiconducting material in the
ical limits in their operation and applications. solar cell, creating dc. For high energy transfer efficiency the
The availability of the power supply generated from wind PV should work at the maximum power point [20], [21].
energy depends on the availability of the wind. Thus, wind In the PV system, we assume that a maximum power point
speed forecasting plays a key role in wind power prediction of tracker will be used. The maximum power output is presented
an electrical energy system. Consequently, extensive research by (2) [22], [23]
has been directed toward the development of good and reli-
able wind power forecasts in recent years and many different (2)
forecasting approaches have been developed [11]–[16]. A
time-series model is built in this paper to forecast the wind where is the conversion efficiency of the solar cell array (%);
speed. Fig. 2 shows the time series results of the 1-h ahead is the array area (m ); is the solar radiation (kW/m ); and
and day ahead forecast for the wind speed and its wind speed is the outside air temperature ( C).
measurements over 200 h. The high forecast accuracy will be FNN is used to forecast the solar radiation based on the past
obtained using historical data. One year wind speed data is one month solar radiation and weather data in this paper. Be-
used in this paper. Fig. 2 also shows that the accuracy of the sides, the forecasted weather data on the study day also needs
1-h ahead forecast is better than that of the day ahead forecast to be obtained from Nature Environment Agency (NEA). These
using the time series model. original data is included in the input layer. The output layer is
The wind power generation output can be considered as a the solar radiation on the study day [24]. Fig. 3 shows the actual
function of wind velocity [17]. A piecewise function can be used and forecasted solar radiation of one day using FNN.
to fit the relationship between the output power and wind speed Mean absolute percentage error (MAPE) is used to express
. The formulation in (1) is used in this paper the difference between the actual and forecasted radiation.
MAPE can be calculated by (3) [25]
(1)
% (3)
where is the rated electrical power; is the cut-in wind
speed; is the rated wind speed; and is the cut-off wind and are the forecasted and actual radiation respectively.
speed. is the data size. The MAPE is 8.96% in this paper using FNN.
144 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 1, MARCH 2012

Power limits:

(6)

Stored energy limits:

(7)

Starting and ending limits:

(8)
Fig. 3. Actual and forecasted solar radiation using FNN.
where is the maximum discharge rate; is the
C. Microturbines and Fuel Cells maximum charge rate; and are the minimum and
maximum energy stored in the battery bank; is the ini-
Microturbines are small single-staged combustion turbines tial energy inside the battery bank; and is the initial stored
that generate from few kWs to few MWs of power, although energy limit of the battery bank. For the energy balance of the
their size varies. Microturbines are usually powered by natural energy storage system, the stored energy inside the battery bank
gas, but can also be powered by biogas, hydrogen, propane, or is set the same as the initial stored energy.
diesel. Considering the installation cost and the fuel cost, the The cost of ESS includes the one-time ESS cost and the
total cost function of microturbines can be obtained in (4) [26] annual maintenance cost. The battery energy storage system
where and are the cost coefficients (BESS) in this paper is made up of small battery blocks.
This means that the one-time ESS cost, FC in $/kWh, which
(4) includes the purchase of batteries and their installation is a
variable cost proportional to the size of BESS. The maintenance
Fuel cells are on the cutting edge of future technologies and cost per year is also a variable cost proportional to the size
have the potential to reshape our energy future. They use an of BESS. If BESS’s life time is years and the maintenance
electrochemical process to turn hydrogen and oxygen into pol- cost is MC($/kWh) per year, then the total cost of BESS is
lution-free electricity and heat. The total cost of fuel cells can ($). is the size of BESS.
also be presented in (4) with different cost coefficients. In this paper, the cost of generation is calculated in 24 h,
which is one day. Hence we need to normalize the total cost of
D. Energy Storage Systems BESS in $/day. If the interest rate for financing the installed
In recent years, several forms of energy storage are studied in- BESS is considered, the annualized one-time ESS cost (AOTC)
tensely. These include electrochemical battery, supercapacitor, in $/year for BESS is shown in (9)
compressed air energy storage, superconducting magnetic en-
ergy storage, and flywheel energy storage. Lithium ion (Li-ion) (9)
batteries are chosen in this paper. They are currently one of the
most popular types of batteries for portable electronics, with one
The total cost of BESS can be obtained by adding AOTC and
of the best energy-to-weight ratios, no memory effect, and a
the maintenance cost together. Then the cost per day (TCPD) of
slow loss of charge when not in use. Mistreatment may cause
BESS installed in $/day can be found in (10)
Li-ion batteries to explode. Li-ion batteries are growing in pop-
ularity for defense, automotive, and aerospace applications due
to their high energy density [27]. (10)
The charge and discharge equations are shown in (5). is
the power discharged by the battery bank during the time period
. is the power charged by the grid to the battery bank, III. PROBLEM FORMULATION
i.e., the battery bank is being charged up. is the energy
stored in the battery bank at time . is the duration time of A. Islanded Microgrids
each interval. and are the discharge efficiency and charge 1) Minimum Size of Battery Energy Storage System: When
efficiency respectively. The battery bank should also satisfy the BESS is installed, one also needs to consider the minimum size
constraints from (6) to (8) for BESS needed by islanded MGs. Sizing a suitable battery
bank, in terms of its power and energy rating, not only could
help in shaving the peak demand but also for storing the excess
(5) renewable energy and supplying the load when the renewable
energy is low. The amount of peak power shaving should be as-
subject to the following battery constraints: sociated with the marginal cost of generating or importing elec-
CHEN et al.: SIZING OF ENERGY STORAGE FOR MICROGRIDS 145

tricity during the specified peak hours while the cost of the bat- are sets of wind energy and PV renewable resources re-
tery system is largely associated with its energy storage rating spectively; and are subscripts indicating generator/energy
(kWh) rather than the power rating (kW) [6]. Hence a small dis- resource and hour index respectively; and are the cost
charge period is desired if it is possible [28]. Once the peak coefficients of microturbines and fuel cells; and are
shaving is established, then the minimum energy supplied by vectors of binary integers representing unit status and start up
BESS is defined as status; and are the reserve cost and start up cost respec-
tively; is the generator output power; and is the spin-
(11) ning reserve of dispatchable distributed generators; and
are the wind and PV energy cost respectively.
where is the end of the time period set, which is one day in Spinning reserve is the term used to describe the total
this paper; is the time interval, which is one hour in this paper; amount of generation available from all units synchronized in
is the system load at time includes the power from the system, minus the present load and losses being supplied
both the renewable energy and traditional energy at time ; and and plus the available energy storage in ESS. The unit com-
is the maximum power supplied by all the generators in mitment problem may involve various classes of scheduled
a smart power system. reserves or offline reserves.
For a smart power system, renewable energy resources are To solve the problem in (14), one needs to consider the fol-
supposed to supply electric power to the grid as much as they lowing constraints:
could. This means that renewable energy resources are kept on Real power balance
all the time if conditions permit. When the power supplied by
renewable energy resources is more than the load in the system,
it will be used to charge up the BESS. Then the minimum energy
charged to BESS is defined as
(15)

(12) ES is a set of energy storage system; is the power de-


mand at the th bus in time period ; and is the distribution
where represents the minimum power supplied by the line loss in time period .
renewable energy sources in the smart power system. The ESS model is introduced in Section II, which is consid-
Finally the minimum value of BESS energy storage rating ered as a generator here. When ESS discharges its energy to
can be obtained in (13) the power grid, it is generating positive real power. When ESS
absorbs energy from the power grid, it is treated as generating
(13) negative real power. The constraints for ESS in Section II are
also considered here.
where and are the discharge efficiency and charge effi- Unit spinning reserve capacity
ciency respectively. and are the min-
imum discharge energy and charge energy of the battery bank.
2) Unit Commitment With Renewable Energy and Energy (16)
Storage System: The UC schedule is a complex challenging
problem, especially when renewable energy resources and where is the 10-min reserve capacity.
energy storage system are included. The solution method de- Capacity of largest online generator
termines the set of committed generators to meet each hourly
forecasted load over a specific study period. The UC schedule
problem is constrained by limits such as the hourly minimum (17)
spinning reserves, generator start up/down times, ramp rates,
where is the hourly required spinning reserve capacity for
and network security [29].
the system.
The formulation is as follows:
The system reserve criteria are shown in the following two
Minimize the total UC schedule cost (TUCC)
constraints in (18)–(19). The ESS and renewable energy fore-
casting error are both considered in these two criteria.
System spinning reserve

(14)

where is a set of dispatchable distributed generators, which (18)


includes microturbines and fuel cells in this paper; and
146 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 1, MARCH 2012

System 10-min operating reserve

(19)

where is the reserve contribution of the 10-min quick start


units is the minimum spinning reserve require-
ment; is the load forecast error factor; is the factor of hourly
spinning reserve to be maintained online; and is the avail-
Fig. 4. Algorithm used to solve the optimal BESS capacity.
able energy stored in the th ESS at time period .
Meanwhile the generator output limits, ramp rate limits
and minimum up/down time limits are also considered in
this problem. For pollution-free and energy sustainability, the C. Solution Algorithm
renewable energy is always assumed on.
Considering TCPD of BESS introduced in Section II-D for
both the islanded and grid-connected MGs, the objective func-
tion will change to minimizing the total cost (TC) in (21) for the
B. Grid-Connected Microgrids islanded MG and maximizing the total benefit (TB) in (22) for
Consumers are assumed to be charged at the open market the grid-connected MG
prices for grid-connected MGs. The optimization problem is
formulated according to the assumed market policy, which is to
maximize the profit from the energy consumed. The profit can (21)
be considered as revenue minus expenses. Revenue is described (22)
as the energy supplied to the consumers multiplied by the elec-
trical price. Expenses include the cost of the energy bought from To obtain the optimal size of BESS, the main problem is
the upstream grid and the total UC schedule cost. to minimize TC in (21) for the islanded MG or maximize TB
For grid-connected MGs, the upstream grid can be treated in (22) for the grid-connected MG in this paper. Fig. 4 shows
as a bidirectional generator, which can generate positive power the algorithm developed in this paper which is used to solve
when the power is transferred from the upstream grid to the MG the optimal size of BESS. This algorithm will compute the dif-
and negative power when the power is transferred from the MG ferent costs under different sizes of BESS between minimum
to the upstream grid. The output of this bidirectional generator is size and maximum size . The optimal size can
limited by the capacity of the transmission line between the MG then be found at the minimum cost point of (21) for the islanded
and the upstream grid. With this consideration, the minimum MG or maximum benefit point of (22) for the grid-connected
BESS size of a grid-connected MG can be obtained via the ap- MG.
proach described in Section III-A. The set of dispatchable gen- The proposed solution is a mixed-integer linear problem. This
erators will be extended to include this bidirectional gener- algorithm is implemented in AMPL (A Modeling Language for
ator for the grid-connected MG. Mathematical Programming) with CPLEX (A Mixed-integer
Considering the market price for the grid-connected MG, Linear Solver) [30] and the results are double checked with an-
maximum market benefit (MB) can be formulated in (20) other solver KNITRO. They proved to be the same values. The
detail of this algorithm is as follows.
1) Enter the forecasting renewable power and load. Calculate
the minimum capacity of BESS.
(20) 2) Set , which is relatively large for the MG,
and the unit and system parameters. Initialize the variables.
3) Solve the objective function for , which is the size of
where is the market price; TUCC includes the dispatchable BESS. Minimize the total cost in (21) for the islanded MGs
generator costs (start-up cost, online spinning reserve cost, and or maximize the total benefit in (22) for the grid-connected
generating energy cost) and renewable energy cost (wind and MG.
PV energy cost). 4) If , update using ,
The same constraints used in the islanded MG could also be and go to step 3. The algorithm will stop when
considered for the problem in (20). .
CHEN et al.: SIZING OF ENERGY STORAGE FOR MICROGRIDS 147

TABLE II
MARKET PRICES OF UPSTREAM POWER SYSTEM

Fig. 5. Forecast load, PV power, and wind power.

TABLE I
DISTRIBUTED GENERATOR DATA

Fig. 6. Benefit in one day of different size of BESS in scenario one.


IV. COST-BENEFIT ANALYSIS—CASE STUDIES
These case studies attempt to determine the optimal BESS or discharged in 2 h [33]. The parameter for the spinning re-
ratings for the MG which is shown in Fig. 1. Forecasting tech- serve capacity factor can be as low as 0.25 [34] and is set to 0.8
niques based on time series method and FNN are used to ob- in this paper.
tain the forecast wind speed and solar radiation of a chosen
day separately. Their forecasted errors are also considered in A. Scenario One
this paper. An energy storage system may have different be- The MG is connected with the upstream power grid in this
haviors under different operating modes of MGs. Two scenarios scenario, which means that it can buy power from the power
are introduced here. The optimal BESS capacity problem of the market during the peak load period and sell power to the power
grid-connected mode is addressed in scenario one while that of market during the valley load period. The upstream grid can
the islanded mode is considered in scenario two. also support system reserve for the MG. The limit of the power
The parameters of the wind generator are: kW, transfer between the MG and the upstream grid is set at 1000
m/s, m/s, and m/s. The parameters of kW. The market price is shown in in Table II.
the PV source are: % and m . The forecast As discussed in Section II-D, the cost of BESS (TCPD) in-
wind speed and solar radiation is shown in Figs. 2 and 3 respec- creases with a larger size, which is shown in Fig. 6, the incre-
tively. Then the output of the wind generator can be obtained ment for the cost of BESS is $67 per 100 kWh in one day. Mean-
by (1) and the PV power is calculated by (2). They are shown in while, as shown in Fig. 6, the market benefit (MB) obtained in
Fig. 5. The forecast load is also shown in Fig. 5. The load fore- (20) also increases with a larger size of BESS. The benefit of in-
cast error factor is assumed at 3% [31]. The renewable power creasing investment on BESS is to increase the market benefit
curve is the total power supplied by the PV and wind generator. (MB), but there is a trade-off between the benefit and the in-
There are two MTs and one FC in this microgrid and the details vestment cost in this case. When the increment for MB and the
are shown in Table I, where MT is the microturbine and FC is cost increment of BESS is the same value, the optimal size of
the fuel cell unit. BESS may be found. This relationship is shown in Fig. 6. The
The interest rate for financing the installed BESS is set at total benefit (TB) includes the cost of BESS and market benefit.
6% in this paper. From [32], the cost for BESS of 100 kWh is As shown in Fig. 6. The maximum value of TB is obtained at
about $60 000 and it will drop very fast when the BESS tech- $10 990 when the size of BESS is 500 kWh.
nology is widely adopted in the future. The maintenance cost for Considering this system without BESS, TB will be $10 774.
this BESS is $2000. The lifetime of BESS is set to three years. In this grid-connected MG, the minimum size of BESS is ob-
For this MG system, the maximum capacity is 2900 kWh and tained as zero, which means that there is no need to install BESS
the charge rate and discharge rate are the same and set at 90%. in this MG if TB does not increase after installing it. From Fig. 6,
The maximum charge and discharge power limits are set as 50% TB is less than $10 774 when the size of BESS is greater than
of its full capacity, which means that BESS can be fully charged 1200 kWh and it is greater than $10 774 when the size of BESS
148 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 1, MARCH 2012

Fig. 8. Energy stored in BESS at the optimal size in scenario one.

by MT #1 during these hours in the MG without BESS. In the 7th


hour, the ouput of MT #1 is not fully covered by the increment
of power from the upstream grid. The difference can be found
Fig. 7. Comparison of dispatchable generator outputs between the MG without in BESS, which is shown in Fig. 8. BESS discharges 104.6 kWh
BESS and the MG with BESS of optimal size in scenario one. to the MG in the 7th hour. Considering the charge efficiency of
BESS, the MG can get 94.1 kWh from BESS, which is exactly
TABLE III
SCHEDULE OFDISPATCHABLE GENERATORS WHEN 500 KWH BESS IS the difference between the two power outputs of the MG with/
INSTALLED FOR THE MG IN SCENARIO ONE without BESS at the 7th hour in Fig. 7. The same thing happens
to MT #2 and FC. MT #2 is shut down at the 9th, 10th, 11th,
and 15th hour and FC is shut down at the 17th hour. The output
of MT #1 is increased at the 8th, 19th, and 22th hour to cover
the changes from the upstream grid and BESS.
Fig. 8 shows the energy stored in BESS. For an effective com-
parison with different BESS sizes, the starting and ending limits
of BESS in this paper are set as the full capacity of BESS. This
will make sure that BESS only balances the power in the MG
and it does not supply/absorb the extra energy to/from the MG.
The minimum capacity is set at 10% of the full capacity and
the maximum capacity is the full capacity of BESS, which are
50 and 500 kWh respectively in this case. The energy stored
is less than 1200 kWh. Hence, the range of the available size for in BESS is under these limits and it supplies power to the MG
BESS in this grid-connected MG is from 0 to 1200 kWh. This during the peak load period. For most time during these 24 h,
is because TB is higher than that without BESS installed when the energy stored in BESS is unchanged, which means the BESS
the size of BESS is between 0 and 1200 kWh. The maximum does not charge or discharge frequently. Considering the charge
increment point of TB will also be the point of the maximum and discharge efficiencies, the process will waste energy during
size for BESS. It is 500 kWh and the maximum increment of every charge or discharge cycle. Hence, BESS only discharges
TB is $216 in one day. energy to the MG during peak load period and is charged up
The schedule of dispatchable generators when 500 kWh during the low market price period, which are reflected in the
BESS is installed for the MG is shown in Table III. With the results shown in Fig. 8. The energy stored in BESS will remain
help of the optimal size of BESS, the dispatchable generators unchanged for the remaining time.
can be shut down during some time periods to save cost under Beside covering the power output of the dispatchable gener-
the same system constraints. The outputs of dispatchable gener- ators, BESS also supports the MG as a source of spinning re-
ators and the power transfer between the upstream gird and the serve. It will help to reduce the cost of spinning reserve gener-
MG are shown in Fig. 7. In the grid-connected MG, it can buy ated by dispatchable distributed generators. The forecast error
power from the upstream gird during the low price period and of renewable energy is considered in both the spinning reserve
sell power to the upstream grid during the high price period, and 10-min operating reserve constraints. The reserve require-
which is also shown in Fig. 7 for both the MGs without BESS ment will vary hourly and BESS will attempt to balance this
and with BESS of 500 kWh. variation.
From Fig. 7. one can tell that the small output of dispatchable
generators can be shifted to the upstream grid or the biggest B. Scenario Two
generator due to the presence of BESS. The MT #1 is shut down A MG in islanded mode is considered in this scenario. The
in the first 7 h when BESS of 500 kWh is installed in the MG. data for dispatchable distributed generator, renewable energy
The output of MT #1 is covered by buying more power from the resources and forecasted load is the same as that in scenario one.
upstream grid due to its low market price in the first 6 h. BESS Unlike grid-connected MGs, the islanded MG needs to meet all
can supply the spinning reserve which was previously supplied the constraints in (15)–(19) without any external help. Besides,
CHEN et al.: SIZING OF ENERGY STORAGE FOR MICROGRIDS 149

Fig. 9. Cost in one day of different size of BESS in scenario two.

Fig. 11. Energy stored in BESS at the optimal size in Scenario Two.

In Fig. 11, the energy stored in BESS remains unchanged for


most of the time because of the charge and discharge efficien-
cies. BESS also serves as a source of online reserve, which is
the same as in scenario one. One also can easily find that the
system attempts to maintain BESS at its full capacity, which
means that BESS will get charged as soon as possible after it
has discharged, i.e., BESS is fully charged within 2 h after 18:00
in Fig. 11. This is because the upstream grid is not considered
in this islanded MG. BESS does not need to wait to charge up
energy when the market price is cheap. BESS maintained at its
Fig. 10. Comparison of dispatchable generator outputs between the MG full capacity will help to carry a higher spinning reserve share,
without BESS and the MG with BESS of optimal size in Scenario Two. which will lower TUCC.
The lowest energy stored in BESS is 566 kWh in the 19th
a minimum size of BESS requirement needs to be considered in hour in Fig. 11. It covers the spinning reserve which is con-
the islanded MG. The minimum size of BESS is obtained at 0 tributed by MT #1 when BESS is not installed. The lowest en-
kWh. ergy stored in BESS is much higher than that of scenario one.
The cost of different sizes of BESS is shown in Fig. 9. TCPD This is because the upstream power grid can support the same
is the same as that in scenario one. It increases as the BESS size MG as a source of spinning reserve, which could lower the op-
increases. The total UC schedule cost (TUCC) reduces when timal size of BESS. Whether or not BESS would discharge par-
the size of BESS increases, which is shown in Fig. 9. However, tially/fully its stored energy in the 19th hour or other hours very
the decrement of TUCC is getting smaller and smaller when the much depends on the cooptimization between the energy and
size of BESS is greater than 1400 kWh. TC includes TCPD and reserve.
TUCC, and its optimal value is obtained by a trade-off between
TUCC and TCPD. From Fig. 9, TC reduces when the size of V. CONCLUSION
BESS is small and increases when the size of BESS is greater The problem of determining the optimal BESS size can be
than 1400 kWh. Hence, the optimal size of BESS can be found solved by the method presented in this paper. This method is
at 1400 kWh where TC is the minimum value at $7370. The tested using the forecast data over a day in a MG shown in
maximum value of TC is $8067 at zero kWh of BESS installa- Fig. 1. Time series and FNN techniques are used for forecasting
tion. the wind speed and solar radiation respectively. The errors as-
The outputs of dispatchable generators in both the MG sociated with forecasting wind speed, PV radiation, and system
without BESS and the MG with BESS of optimal size are load are also considered in this paper. The proposed approach
shown in Fig. 10. The corresponding energy stored in BESS is employs a cost-benefit analytical technique to estimate the eco-
shown in Fig. 11. The start and end limits of energy storage are nomic feasibility of the BESS deployment for both the grid-con-
the same as those of scenario one, which are the full capacity nected and islanded modes. Based on the results obtained the
of BESS. The minimum capacity of BESS is also set at 10% of following points can be concluded.
its full capacity and the maximum capacity is its full capacity, First, the quantitative results of the case study in both sce-
which are 140 kWh and 1400 kWh, respectively. narios show that BESS for the MG could increase the benefit of
The behaviors of the dispatchable generators are very similar the MG (increase MB in scenario one) or decrease the schedule
to those of the grid-connected MG. MT #2 shuts down during cost of the MG (decrease TUCC in scenario two). As the size
the 8th–12th, 14th, 15th, and 20th hours and the outputs during of BESS increases, the benefit increases or the cost decreases.
these hours are shifted to the cheapest generator, MT #1, and However, the rate of the increment of benefit or the rate of the
BESS. It also happens for FC during the 13th and 16th–18th decrement of cost is getting smaller and smaller. Considering
hours. that the TCPD increases in a constant rate and when the size of
150 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 1, MARCH 2012

BESS is greater than some optimal BESS value, the total ben- [9] H. T. Le and T. Q. Nguyen, “Sizing energy storage systems for wind
efit TB in scenario one will reduce and the total cost TC in sce- power firming: An analytical approach and a cost-benefit analysis,” in
Proc. Power Energy Soc. Gen. Meet., Jul. 2008, pp. 1–8.
nario two will increase as shown in Figs. 7 and 10 respectively. [10] J. Kaldellis, D. Zafirakis, and E. Kondili, “Optimum sizing of photo-
Hence, the optimal size of BESS exists and differs in both the voltaic-energy storage systems for autonomous small islands,” Int. J.
grid-connected and islanded MGs in this paper. Electr. Power Energ. Syst., vol. 32, no. 1, pp. 24–36, 2010.
[11] R. Billinton, H. Chen, and R. Ghajar, “Time-series models for relia-
Second, the decrement of TUCC includes two components in bility evaluation of power systems including wind energy,” Microelec-
scenario two. The first component is that BESS can store the tron. Reliab., vol. 36, no. 9, pp. 1253–1261, 1996.
surplus renewable energy and redispatch it appropriately. This [12] B. Ernst, B. Oakleaf, M. Ahlstrom, M. Lange, C. Moehrlen, B. Lange,
U. Focken, and K. Rohrig, “Predicting the wind,” IEEE Power Energy
could smoothen the power supplied by intermittent distributed Mag., vol. 5, no. 6, pp. 78–89, Nov. 2007.
generators, which could make the generators operate at a stable [13] G. Sideratos and N. Hatziargyriou, “An advanced statistical method for
condition and lower their cost by reducing the shutdown and wind power forecasting,” IEEE Trans. Power Syst., vol. 22, no. 1, pp.
258–265, Feb. 2007.
startup frequency. The intermittency of the renewable energy [14] J. Taylor, P. McSharry, and R. Buizza, “Wind power density fore-
and load is somewhat represented by their hourly average in- casting using ensemble predictions and time series models,” IEEE
tegrated energy forecast errors. BESS could be considered as a Trans. Energy Convers., vol. 24, no. 3, pp. 775–782, Sep. 2009.
[15] R.-H. Liang and J.-H. Liao, “A fuzzy-optimization approach for gen-
source of fast spinning reserve or a fast unit which participates eration scheduling with wind and solar energy systems,” IEEE Trans.
in frequency regulation to compensate the forecast deficiency Power Syst., vol. 22, no. 4, pp. 1665–1674, Nov. 2007.
and to drive the real-time area control error (ACE) to zero. The [16] T. Barbounis, J. Theocharis, M. Alexiadis, and P. Dokopoulos, “Long-
term wind speed and power forecasting using local recurrent neural
second component is that energy stored in BESS can be consid- network models,” IEEE Trans. Energy Convers., vol. 21, no. 1, pp.
ered as a form of reserve to help the MG meet the reserve con- 273–284, Mar. 2006.
straints, which will reduce the reserve cost of the MG. These [17] B. Borowy and Z. Salameh, “Optimum photovoltaic array size for a
hybrid wind/pv system,” IEEE Trans. Energy Convers., vol. 9, no. 3,
two components also increase MB in scenario one. Besides, the pp. 482–488, Sep. 1994.
BESS in scenario one can store energy when the market price is [18] L. Soder, “Simulation of wind speed forecast errors for operation plan-
low and redispatch it during the peak load period. This helps to ning of multiarea power systems,” in Proc. Probabil. Methods Applied
Power Syst., Sep. 2004, pp. 723–728.
increase MB. [19] R. Perez, R. Seals, P. Ineichen, R. Stewart, and D. Menicucci, “A new
Third, from the results of scenarios one and two, one can simplified version of the perez diffuse irradiance model for tilted sur-
easily say that installing BESS with optimal size could increase faces,” Solar Energy, vol. 39, no. 3, pp. 221–231, 1987.
[20] W. Xiao, M. Lind, W. Dunford, and A. Capel, “Real-time identifica-
TB for the grid-connected MG and reduce TC for the islanded tion of optimal operating points in photovoltaic power systems,” IEEE
MG. Comparing with the grid-connected MG without BESS, Trans. Ind. Electron., vol. 53, no. 4, pp. 1017–1026, Jun. 2006.
installing an optimal size of 400 kWh BESS will increase TB [21] P. Kirawanich and R. O’Connell, “Potential harmonic impact of a resi-
dential utility-interactive photovoltaic system,” in Proc. 9th Harmonics
about 2% per day in scenario one. Comparing with the islanded Quality Power Conf., 2000, vol. 3, pp. 983–987.
MG without BESS, installing an optimal size of 1400 kWh [22] C. Tao, D. Shanxu, and C. Changsong, “Forecasting power output for
BESS will reduce TC about 8.64% per day in scenario two. The grid-connected photovoltaic power system without using solar radia-
tion measurement,” in Proc. 2nd IEEE Int. Symp. Power Electron. Dis-
charging and discharging efficiency of BESS is considered in trib. Gener. Syst. (PEDG), Jun. 2010, pp. 773–777.
this paper. With the charging and discharging rates, the optimal [23] A. Yona, T. Senjyu, and T. Funabashi, “Application of recurrent neural
solution will also minimize the frequency of charging or dis- network to short-term-ahead generating power forecasting for photo-
voltaic system,” in Proc. Power Energy Soc. Gen. Meet., Jun. 2007, pp.
charging for BESS. This will increase the operating life of bat- 1–6.
teries. [24] J. Hoff, L. Townsend, and J. Hines, “Prediction of energetic solar par-
ticle event dose-time profiles using artificial neural networks,” IEEE
Trans. Nucl. Sci., vol. 50, no. 6, pp. 2296–2300, Dec. 2003.
REFERENCES [25] A. Iga and Y. Ishihara, “Characteristics and embodiment of the prac-
tical use method of monthly temperature coefficient of the photovoltaic
[1] Microgrid Energy Management Framework Jul. 2009 [Online]. Avail- generation system,” IEEJ Trans. Power Energy, vol. 126, no. 8, pp.
able: http://bit.ly/f98iSX 767–775, 2006.
[2] H. T. Le and T. Q. Nguyen, “Sizing energy storage systems for wind [26] G. Pepermans, J. Driesen, D. Haeseldonckx, R. Belmans, and W.
power firming: An analytical approach and a cost-benefit analysis,” in D’haeseleer, “Distributed generation: Definition, benefits and issues,”
Proc. Power Energy Soc. Gen. Meet., 2008, pp. 20–24. Energy Policy, vol. 33, no. 6, pp. 787–798, 2005.
[3] S. Chen and H. Gooi, “Scheduling of energy storage in a grid-con- [27] L. Gao, S. Liu, and R. Dougal, “Dynamic lithium-ion battery model for
nected pv/battery system via simplorer,” in Proc. TENCON IEEE Re- system simulation,” IEEE Trans. Compon. Packag. Technol., vol. 25,
gion 10 Conf., Nov. 2009, pp. 1–5. no. 3, pp. 495–505, Sep. 2002.
[4] X. Wang, D. M. Vilathgamuwa, and S. Choi, “Determination of battery [28] S. X. Chen, K. J. Tseng, and S. S. Choi, “Modeling of lithium-ion bat-
storage capacity in energy buffer for wind farm,” IEEE Trans. Energy tery for energy storage system simulation,” in Proc. Power Energy Eng.
Convers., vol. 23, no. 3, pp. 868–878, Sep. 2008. Conf., Asia-Pacific, Mar. 2009, pp. 1–4.
[5] S. Chiang, K. Chang, and C. Yen, “Residential photovoltaic energy [29] B. Venkatesh, P. Yu, H. Gooi, and D. Choling, “Fuzzy milp unit com-
storage system,” IEEE Trans. Energy Convers., vol. 45, no. 3, pp. mitment incorporating wind generators,” IEEE Trans. Power Syst., vol.
385–394, Jun. 1998. 23, no. 4, pp. 1738–1746, Nov. 2008.
[6] C. Venu, Y. Riffonneau, S. Bacha, and Y. Baghzouz, “Battery storage [30] R. Fourer, D. M. Gay, and B. W. Kernighan, AMPL: A Modeling Lan-
system sizing in distribution feeders with distributed photovoltaic sys- guage for Mathematical Programming. Pacific Grove, CA: Thomson
tems,” in Proc. IEEE Bucharest PowerTech, Jun. 2009. Brooks/Cole, 2003.
[7] J. Mitra, “Reliability-based sizing of backup storage,” IEEE Trans. [31] Y. Chen, P. Luh, C. Guan, Y. Zhao, L. Michel, M. Coolbeth, P. Fried-
Power Syst., vol. 25, no. 2, pp. 1198–1199, 2010. land, and S. Rourke, “Short-term load forecasting: Similar day-based
[8] T.-Y. Lee and N. Chen, “Determination of optimal contract capacities wavelet neural networks,” IEEE Trans. Power Syst., vol. 25, no. 1, pp.
and optimal sizes of battery energy storage systems for time-of-use 322–330, Feb. 2010.
rates industrial customers,” IEEE Trans. Energy Convers., vol. 10, no. [32] “Battery and electric vehicle report” Jul. 2010 [Online]. Available:
3, pp. 562–568, Sep. 1995. http://bit.ly/fGaZPB
CHEN et al.: SIZING OF ENERGY STORAGE FOR MICROGRIDS 151

[33] Ubi-2590 Smbus (Part no. ubbl10) Battery Specification Aug. 2009 H. B. Gooi (SM’95) received the B.S. degree from
[Online]. Available: http://bit.ly/gLgVY0 National Taiwan University in 1978, M.S. degree
[34] Northeast Power Coordinating Council (NPCC) Operating Reserve from the University of New Brunswick, Fredericton,
Criteria Dec. 2008 [Online]. Available: http://is.gd/b6xbb NB, Canada, in 1980, and the Ph.D. degree from
Ohio State University, Columbus, in 1983.
From 1983 to 1985, he was an Assistant Professor
in the EE Department at Lafayette College, Easton,
PA. From 1985 to 1991, he was a Senior Engineer
with Empros (now Siemens), Minneapolis, MN,
where he was responsible for the design and testing
coordination of domestic and international energy
management system (EMS) projects. In 1991, he joined the School of Electrical
and Electronic Engineering, Nanyang Technological University (NTU), Singa-
pore, as a Senior Lecturer. Since 1999, he has been an Associate Professor at
NTU. His current research focuses on microgrid energy management systems,
electricity markets, spinning reserve, energy efficiency, and renewable energy
sources.

S. X. Chen (S’09) received the B.S. dual degree M. Q. Wang (S’08) received the B.S. and M.Eng.
in power engineering and business administration degrees in electrical engineering from Shandong
from Wuhan University, China, in 2007 and the University, Jinan, China, in 2004 and 2007 respec-
M.S. degree in power engineering from Nanyang tively. He is now working toward the Ph.D. degree
Technological University, Singapore, in 2008. He is at Nanyang Technological University, Singapore.
now working toward the Ph.D. degree at Nanyang His research interests are power system economic
Technological University. operation and microgrids.
His research interests are smart energy manage-
ment systems, energy efficiency, renewable energy
sources, and energy storage systems.

View publication stats

Das könnte Ihnen auch gefallen