Sie sind auf Seite 1von 4

Inspection and Test Plan for Process Piping 

Activity By Remark
No. Inspection and Test Plan Reference Document  Acceptance Criteria Verifying Document
Contrac. TPI Client ‐

1 Pre‐Inspection Meeting Spec. Spec. MOM H H H ‐

Documention Control

2 Receiving Material Check ASME B31.3, Spec. ASME B31.3, Spec Related Forms H W A ‐

Material Certificate
3 ASME SEC II, Spec. ASME SEC II Certificates H W A ‐
 Control
4 WPS ASME IX, Spec. ASME IX WPS H H ‐ ‐

5 PQR ASME IX, Spec. ASME IX PQR H H A ‐

6 WPQ ASME IX, Spec. ASME IX WPQ Records H H ‐ ‐

7 NDT Operator Certificate ASME B31.3, Spec ASME B31.3 Certificates H H A ‐

Calibration Certificate 
8 ASME B31.3, Spec Spec. Records H H A ‐
Cotrol

SPOOL MAKING (SHOP)

Cutting and Beveling of
9 each parts & Check of WPS/Spec. ASME B31.3 ‐ H SW R ‐
identification

10 Fit up of spools WPS/Spec. ASME B31.3 Dialy Fit‐Up Report H W R ‐

11 Monitoring of Welding WPS/Spec. ASME B31.3 Dialy Welding Report H W R ‐

1
12 PWHT (If Any) WPS/Spec. ASME B31.3 PWHT Report H W R ‐

13 Final Inspection WPS/Spec. ASME B31.3 ‐ H H R ‐


Identification of Spools
14 Spec. Spec. ‐ H W R ‐
Control
Painting of Spools (Primer)
Daily Surface 
15 Surface Preparation SSPC, Spec. SSPC H W R ‐
Preparation Report
Daily Painting 
16 DFT Measurment SSPC, Spec. SSPC H W R ‐
Inspection Report

Field Assembly

Inspection of internal
17 cleaness prior of Spec. ASME B31.3, Spec ‐ H SW R ‐
installation

18 Fit up WPS/Spec. ASME B31.3 Daily Fit‐Up Report H W R ‐

Check that no significant
19 Spec. ASME B31.3 ‐ H W R ‐
stresses on line

20 Surverying Spec. ASME B31.3, Spec Surveing Report H W R ‐

21 Monitoring of welding WPS/Spec. ASME B31.3 Daily Welding Report H W R ‐

22 PWHT (If Any) WPS/Spec. ASME B31.3 PWHT Report H W R ‐

2
NDT Request Report
RT Test Report
23 NDT ASME B31.3, Spec ASME B31.3 H W R ‐
PT Test Report
UT Test Report

24 Pipe Support DWG/WPS DWG Pipe Support Report H W R ‐


Line Check (Punch List
25 WPS/DWG WPS/DWG Punch List Report H W R ‐
acc. to Isometric DWG)
ASME/NDT map/NDT
26 Pressure Test ASME VIII Pressure Test Report H R ‐
Procedure
Pipes History Report
Test Package Line List
27 Test Package  Spec./DWG Spec./DWG H R ‐
NDT Test Reports
Hydrostatic Test Report

28 Valve Installation Spec./DWG Spec./DWG Valve Installation Report W R ‐

Final Inspection
29 Spec./DWG Spec./DWG Reinstatment Certificate H H R ‐
(Reinstatement)

Final Field Coat
Daily Surface 
30 Surface Preparation SSPC, Spec. SSPC H W R ‐
Preparation Report
31 Wrapping for UG Piping SSPC, Spec. SSPC Wrapping Report H W R
Daily Painting 
32 DFT Measurment SSPC, Spec. SSPC H H R ‐
Inspection Report

Abbreviations: 

H: Hold Point = Hold on the production till TPI Inspector performs inspection and supervise the required test
W: Witness Point = Manufacture shall notify client and TPI Inspector but there is no hold on the production;
Client can waive this inspection based on his discretion and informs TPI Inspector accordingly.

3
R: Document Review = Review means Review document, which includes of material test certificates, WPS, PQR, NDT Procedures and etc.

A: Approval 
SW: Spot Witness = for items with spot witness manufacture shall notify TPI inspector as fulfilling the monitoring; 
For example one random visit for whole UT tests or one or two visits for whole surface preparation works for painting.

MOM: Minute of Meeting 