Beruflich Dokumente
Kultur Dokumente
Executive Engineer
Road Construction Division
Lahore.
1 x 10 x 10 = 100 Sft.
0.75" sand for leveling purpose and 0.25" for joints filling etc.
1 x 1 = 1.00 Job.
@ Rs.230.00 P. Hr = Rs.230.00
1 x 10 x 10 = 100.00 Sft.
Executive Engineer
Road Construction Division
Lahore.
1
S/O Precast Paving Blocks (Paving Tiles) Size 60
mm thick of approved colour and shape as
directed by the Engineer Incharge at the site of
work i/c carriage etc complete.
1 x 10 x 10 = 100 Sft.
2" sand for leveling purpose and 1/2" for joints filliing etc.
1 x 1 = 1.00 Job.
1 x 10 x 10 = 100.00 Sft.
Executive Engineer
Road Construction Division
Lahore.
2 Read made Kerb Stone 14" high ( Tuff / Izhar with compressive strength )
size 12" long & 14" high of approved shape -
1 x 10 = 10.00 No
( Note: Each Kerb stone will be 12" long )
Haunching
1 x 10 x 0.21 x 0.50 = 1.05 Cft.
(0.25+0.17)/2
5 Preparing surface and painting of small detached articles, not exceeding one sq. ft.
(Sq.m) of painted surface (03 coats):-
1 x 10 = 10 Nos.
Executive Engineer
Road Construction Division
Lahore.
Unit =
Weight of Liner for 1 meter length, 5' dia pile and 10 mm thick.
Length
1 x 3.28 = 3.28 Rft
Circumfrence 2 R
2 x 3.14 x 2.5 = 15.70 Ft
Thickness
10 / 25.4 / 12 = 0.033 Ft
@ Rs.11,324.15 P%Kg. =
(MRS Chap-25, Page 153, item No.10)
= 1 Job.
@ Rs.5,000.00 P.Job. =
= 2 Hrs.
@ Rs.1,953.00 P.Hrs. =
@ Rs.678.50 P%Kg. =
(MRS Chap-25, Page 153, item No.11)
Total =
Executive Engineer
Road Construction Division
Lahore.
%Kg.
Rs.128,584
Rs.5,000
Rs.3,906
Rs.145,194
Total
Sundries 10 Percent on ###
Total
Contractor's Profit 20 Percent
on Rs. ###
Total for 100 Rft
ITEM RATES
Labour rate per Rft Rs. ### Say
Labour rate per L.M Rs. ### Say
Executive Engineer
Road Construction Division
Lahore.
Amount (Rs.)
29469.57
5114.51
8846.72
2946.96
933
47310.76
9462.15
56772.91
5000.00
5000.00
52250.00
570.00
2968.75
65788.75
35000.00
2500.00
13000.00
550.00
###
6578.88
###
14473.53
###
Item No. 7 Providing and casting in situ bored reinforced concrete pile with type 'C'
concrete (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., which
will be paid separately, including screening and washing of shingle and
curing.
Total
Contractor's Profit & Overheads 20 Percent
Total
LABOUR
Labour for 60" dia pile
1 Mason 1963.49 Cft. 209.41 P.Cft.
2 Cooly skilled
3 Coolies un-skilled
4 Bahisthi
5 Fitter
Total
Sundries 10 Percent on R###
Total
Contractor's Profit & Overheads 20 Percent
Total
ITEM RATES
Labour rate per Rft Rs. 7,088.00 Say
Labour rate per L.M Rs. 23,248.65 Say
Or Rs. 38,902.59 LM
Amount (Rs.)
234425.00
30512.63
52778.61
23442.50
933.00
###
68418.35
###
411174.44
###
41117.44
###
90458.38
###
150000.00
2500.00
13000.00
550.00
###
6 Boring hole 60" dia 100.00 Rft 1,500.00 per foot 150000.00
7 Working of rig during casting 2.50 hrs. 1,000.00 per hour 2500.00
8 Constructin of Temparary Island L.S 13000.00
9 Carriage of material to site of work
(Boaring Material) L.S 550.00
Total for 100 Rft ###
ITEM RATES
Labour rate per Rft Rs. 6,913.06 Say
Labour rate per L.M Rs. 22,674.82 Say
Or Rs. 37,825.57 LM
Executive Engineer
Item No. 7 Providing and casting in situ bored reinforced concrete pile with type 'C'
concrete (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., which
will be paid separately, including screening and washing of shingle and
curing.
(i) 1000 mm dia pile.
6 Boring hole 60" dia 100.00 Rft 1,500.00 per foot 150000.00
7 Working of rig during casting 2.50 hrs. 1,000.00 per hour 2500.00
8 Constructin of Temparary Island L.S 13000.00
9 Carriage of material to site of work
(Boaring Material) L.S 550.00
Total for 100 Rft ###
ITEM RATES
Labour rate per Rft Rs. 3,994.96 Say
Labour rate per L.M Rs. 13,103.47 Say
Composite rate per Rft Rs. 5,767.01 Say
Composite rate per L.M Rs. 18,915.80 Say
Or Rs. 19,857.07 LM
Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored piles
including cutting bending, laying in position, welding and fastening,
including cost of binding wire and labour charges for binding of steel
reinforcement (also includes removal of rust from the bars).
Total 177032.25
Contractor's Profit & Overheads 20 Percent 35406.45
Total 212438.70
Material cost per Cwt 4425.81
Total 2275.00
Sundries 10 Percent 227.50
Total 2502.50
Contractor's Profit & Overheads 20 Percent 500.50
Total 3003.00
ITEM RATES
Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored piles
including cutting bending, laying in position, welding and fastening,
including cost of binding wire and labour charges for binding of steel
reinforcement (also includes removal of rust from the bars).
Total 185582.75
Contractor's Profit & Overheads 20 Percent 37116.55
Total 222699.30
Material cost per Cwt 4639.57
Total 2275.00
Sundries 10 Percent 227.50
Total 2502.50
Contractor's Profit & Overheads 20 Percent 500.50
Total 3003.00
ITEM RATES
Or Rs.120,887.18 P. Ton
Executive Engineer
Road Construction Division
Lahore.
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.
1 Cost of lifting machinery including carriage 1.00 No. 1,150,000 each 1150000.00
2 Cost of trollies 3.00 Nos. 46,000.00 each 138000.00
3 Cost of steel rope 1" Ø 450.00 Rft 70.00 Rft 31500.00
4 U Clamp i/c 5/8" bolts & nuts 3.00 Nos. 60.00 each 180.00
5 Steel rope ¾" (3 x 20) 60.00 Rft 55.00 Rft 3300.00
6 Railway track 200 ft. including sleepers bolts
& nuts complete 200' x 2 = 400 Rft @
235/-P-Rft 400.00 Rft 242.00 Rft 96800.00
7 Crow bar 6.00 Nos. 440.00 each 2640.00
Total 1422420.00
Assume life of machinery = 5 years
depreciation for one year
1422420 ÷ 5 = ### 284484.00
Contractor's Profit & Overheads 20 Percent 56896.80
Total 341380.80
ITEM RATES
Labour rate per 100 Cft Rs. 1,322.99 Say
Labour rater per Cum Rs. 467.28 Say
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.
EQUIPMENT
Total 14189.70
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.
(iii) Beam above 75 ft. upto 100 ft (23 metre to 30 metre) length.
EQUIPMENT
Total 25534.56
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.
(iv) Beam above 100 ft. upto 150 ft (23 metre to 30 metre) length.
EQUIPMENT
Total 39689.76
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.
(v) Beam above 150 ft. upto 175 ft (46 metre to 53 metre) length.
EQUIPMENT
Total 71726.81
ITEM RATES
Unit = P.Cft.
Lead = 180 Km.
Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)
Total = Rs.374.52
Total = Rs.282.07
Total = Rs.402.00
Executive Engineer
Road Construction Division
(MRS 1st Bi-Annual 2017)
Lahore.
Unit = P.Cft.
Lead = 180 Km.
1 P/L R.C.C 1:1:2 with horizontal shuttering.
Qty of Bajri
For %Cft. RCC 78.00 Cft.
For One Cft RCC 0.78 P.Cft.
4047.55 / 100 x 0.78 = 31.57
(As per same carriage of base course)
Total = Rs.453.72
Or = Rs.16,025.39 P.CM
Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.402.00
Or = Rs.14,198.64 P.CM
Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)
Total = Rs.374.52
Or = Rs.13,228.05 P.CM
Executive Engineer
(MRS 1st Bi-Annual 2017)
Road Construction Division
Lahore.
Unit = P.Cft.
Lead = 224 Km.
Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.437.35
Or = Rs.15,447.20 P.CM
Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.344.96
Or = Rs.12,183.99 P.CM
Executive Engineer
Road Construction Division
Lahore.
Coarse sand 21 CM
21 x 35.32 = 741.72 Cft. 42.00
Bajri 42 CM
42 x 35.32 = 1483.44 Cft. 84.00
Executive Engineer
Road Construction Division
Lahore.
Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, girders
and other structural members laid in situ or pre cast laid in position or pre
stressed members cast in situ complete in all respect.
4 Shuttering
Total 19745.22
Contractor's Profit 20 Percent 3949.04
Total 23694.26
LABOUR
Total 9927.50
Sundries 10 Percent 992.75
Total 10920.25
Contractor's Profit 20 Percent 2184.05
Total for 100 Cft 13104.30
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. 131.04 Say
Labour rate per Cum Rs. Say
Or Rs. 15,447.20 CM
Executive Engineer
Road Construction Division
Lahore.
Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).
Total 16646.60
Contractor's Profit 20 Percent 3329.32
Total 19975.92
LABOUR
Total 5745.00
Sundries 10 Percent 574.50
Total 6319.50
Contractor's Profit 20 Percent 1263.90
Total rate for 100 Cft 7583.40
Rate per Cft 27559.32
ITEM RATES
Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).
Total 19593.79
Contractor's Profit 20 Percent 3918.76
Total 23512.55
LABOUR
Total 5745.00
Sundries 10 Percent 574.50
Total 6319.50
Contractor's Profit 20 Percent 1263.90
Total rate for 100 Cft 7583.40
Rate per Cft 31095.95
ITEM RATES
Labour rate per Cft Rs. 75.83 Say
Labour rate per Cum Rs. Say
Or Rs. 12,183.99 CM
Unit = P.Cft.
Lead = 180 Km.
1 P/L R.C.C 1:1:2 without horizontal shuttering.
Qty of Bajri
For %Cft. RCC 78.00 Cft.
For One Cft RCC 0.78 P.Cft.
4047.55 / 100 x 0.78 = 31.57
(As per same carriage of base course)
Total = Rs.366.22
Or = Rs.12,934.89 P.CM
Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.309.60
Or = Rs.10,935.07 P.CM
Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)
Total = Rs.282.07
Or = Rs.9,962.71 P.CM
Executive Engineer
(MRS 1st Bi-Annual 2017)
Road Construction Division
Lahore.
Unit = P%Cft.
Lead = 180
Total = Rs.21,811.00
Or = 7703.65 P.CM
Executive Engineer
Road Construction Division
Lahore.
Unit = P%Cft.
Lead = 180
Total = Rs.24,411.24
Total = Rs.19,978.25
Executive Engineer
Road Construction Division
Lahore.
3 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'
4 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile
Total = Rs.365.83
Executive Engineer
Road Construction Division
Lahore.
Sft.
Km
Analysis of Rate for Disposal of Unsuitable Material with 3 Km Lead.
2 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'
3 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile
Executive Engineer
Road Construction Division
Lahore.
Unit = P%Sft.
Lead = 180 Km.
Total = Rs.2,977.06
Total = Rs.3,152.36
Executive Engineer
Road Construction Division
Lahore.
S.Total Rs.4,047.55
Total = Rs.8,510.31
Rate Per CM = Rs.3,005.84
2 Base Course
S.Total Rs.4,047.55
Total = Rs.10,948.96
Executive Engineer
= Rs. 1320.00
Executive Engineer
Road Construction Division
Lahore.
3 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'
4 Subsequent lead beyond I Mile upto (5 Km) for every 1/4 Mile
Executive Engineer
Road Construction Division
Lahore.
2 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'
3 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile
Executive Engineer
Road Construction Division
Lahore.
Calculation Backup
Bill # 1 Earthwork and Allied Activities
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
101 Clearing & Grubbing SM
From Nazi Chowk & Toll Plaza Ramps 2 100 19.6 3,920
Total 5,520
Say 6,080
From Nazi Chowk & Toll Plaza Ramps 2 100 19.6 3,920
Total 5,520
Say 6,080
From Nazi Chowk & Toll Plaza Ramps 2 100 2.5 1 500
Total 61,875
Say 68,070
From Nazi Chowk & Toll Plaza Ramps 2 500 2.5 1 2,500
Total 2,500
Say 2,750
Calculation Backup
Bill # 1 Earthwork and Allied Activities
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
Formation of embankment from Borrow
108c CM
Excavation in Common Material
From Nazi Chowk & Toll Plaza Ramps 2 100 19.8 5 19,800
Total 19,800
Add 10% 1,980
Net Total 21,780
Say 21,780
Total 4,370
Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.20 672.00
Total 1,445
Total 2,197.00
From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.15 504.00
Total 4,254.00
Total 4,254
Say 4,680
From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.25 840.00
(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
Total 7,469
Say 8,220
2 10 5.0 100.00
Total 100.00
2 10 5.0 100.00
Total 100.00
Say 6,410
(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
Total 100.00
(1102+110.2)
Total 3,201.00
Total 12,120
Say 13,340
Total 800
Add 10% 80
Say 880
(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 3 Surface Courses and Pavement
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
302 Bituminous Prime Coat SM
From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 3,360.00
From Nazi Chowk & Toll Plaza Ramps 4 100 16.80 6,720.00
From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.05 168.00
Calculation Backup
Bill # 3 Surface Courses and Pavement
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
Slip Lane from Ring Road 1 50 10.40 0.05 26.00
(Bill No.30
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations
401 a (ii) Concrete Bearing Pads, Concrete Class A1 CM 0.6 0.7 0.15 168 10.58
Reinforcement @ 100 kg/CM ton 1.06
401 b (ii) Deck Slab Concrete Class A2 CM 493 19.6 0.225 1 2,174.13
Reinforcement @ 120 kg/CM 260.90
405 a Tendons (0.5 " dia) Prestressed steel Wires in Girders Ton 309.91
@ 80 kg/CM
401 b (ii) Abutment Girder Seat , Concrete Class A2 CM 19.6 2 1.5 2 117.60
CM 19.6 0.3 2.25 2 26.46
CM 19.6 0.3 0.525 2 6.17
Reinforcement @ 150 kg/CM ton 22.54
CM 65 A= 1.77 10 1,148.55
CM 65 A= 1.77 55 6,327.75
Test Pile CM 65 A= 1.77 2 230.10
Reinforcement @ 200 kg/CM Ton 1,541.28
cubic
406 c Elastomeric Bearing Pads centi 50 60 8.7 168 4,384,800.00
meter
49.69
17.64
246.50
10.58
564.57
2,174.13
3,873.90
310.00
11,157.00
637.76
689.17
150.23
18.30
2,849.03
4,355.00
1.00
2.00
254.80
TION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations
5,040.00
TION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations
4,384,800.00
300.00
1,972.00
493.00
346.50
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m
107a Structural Excavation CM
New Drain Wall 2 100 2.23 1.4 624.4
Total 624
Add 10% 62
Net Total 687
Say 690
Total 60
Add 10% 6
Net Total 66
Say 70
Total 241
Add 10% 24
Net Total 265
Say 270
Total 883
Add 10% 88
Say 980
Both Side of MBS slip form Barrier Double Face 2 500 0.307 307.00
Both Side of MBS slip form Barrier Double Face 1 200 0.307 61.40
Total 368
Add 10% 37
(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m
Say 410
Both Side of MBS slip form Barrier Double Face 2 500 0.70 0.050 35.00
Both Side of MBS slip form Barrier Double Face 1 100 0.70 0.050 3.50
Total 135
Add 10% 14
Say 150
Total 40.80
12.5 4 50.00
Total 50
Add 10% 5
Net Total 55
Say 60
66.67 66.67
Total 67
Add 10% 7
Net Total 73
Say 80
(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m
Total 150
Add 10% 15
Say 170
(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Total 1,900.30
Say 2,100.00
Total 100.00
Say 110.00
Total 490.00
Say 540.00
Total 1,050.00
Say 1,160.00
Total 600.00
Add 10% 60.00
Net Total 660.00
Say 660.00
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
Total 2,300
Say 2,530
Total 1,300
Add 10% 130
Net Total 1,430
Say 1,430
607b Traffic Signs, Circular dia 1200 mm with Post Each 5.00
White Line
From Nazi Chowk & Toll Plaza Ramps 0.66 100 66.00
(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
Total 9,136
Say 10,060
Total 100
Add 10% 10
Say 110
Total 2,168
Say 2,390
Total 800
Add 10% 80
Say 880
Total 2,200
Say 2,420
Total 1,600
(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
Say 1,760
Total 1,600
Add 10% 160
Net Total 1,760
Say 1,760
Total 800
Add 10% 80
Say 880
Total 800
Add 10% 80
Say 880
Total 100.00
2 400 800.00
1 500 500.00
Total 1,300
Say 1,430
(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
ENGINEER'S ESTIMATE
SUMMARY
Amount
Bill No. Description
(Rs.)
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
203a Asphaltic Base Course Plant Mix (Class B) CM 4,680.00 12,617.97 59,052,100
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
305 Asphaltic Wearing Course Plant Mix (Class A) CM 2,650.00 13,360.96 35,406,544
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
401 b (ii) Concrete Class A2 (4000 psi) Transom and Wing Wall CM 656.00 15,447.20 10,133,363
401 b (ii) Concrete Class A2(4000 psi) Diaphragms and Deck slab CM 2,739.00 15,447.20 42,309,881
401 a(i) Concrete Class A1 (3000 psi) Approach Slab CM 50.00 10,935.07 546,754
401 b(ii) Concrete Class A2( 4000 psi) Piers CM 690.00 15,447.20 10,658,568
401 b(ii) Concrete Class A2 (4000 psi) Abutment Girder Seat CM 151.00 15,447.20 2,332,527
401 b(ii) Concrete Bearing Pads, Concrete Class A2 CM 11.00 12,183.99 134,024
407 m Pile Load Test (upto 2.5 times the design load) Each 1.00 780,000 780,000
407 n Pile Proof Load Test (upto 1.5 times the design load) Each 2.00 540,000 1,080,000
407 p MS Steel Linner for Piles 1500mm dia 10mm thick LM 347.00 48,398 16,794,106
SP 418 a Galvanized Iron Drain pipe, 100mm dia LM 138.00 2,468.45 340,646
SP 419b Provide and Fixing Steel Hand Railng LM 493.00 4,749.65 2,341,577
ENGINEER'S ESTIMATE
Bill No.4.1a Structure (Widening of Existing Bridge at Niazi Interchange)
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Excavate Unsuitable/Surplus Common Material and
106 a CM 4,200.00 216.39 908,838
removal upto 3 Km Lead.
107 a Structural excavation in common material CM 7,000.00 216.50 1,515,500
401 b(ii) Deck Slab and Diaphragms, Concrete Class A2 CM 420.00 15,447.20 6,487,824
401 a(ii) Transom Pier Cap, Concrete Class A1 CM 110.00 14,198.64 1,561,850
401 a(ii) Girder Seat on Abutment, Concrete Class A1 CM 415.00 14,198.64 5,892,436
407 c Proof Load Test (up to 1.5 times the design load) Each 1.00 336,000.00 336,000
SP-616a 100 mm dia class "B" PVC Pipe LM 132.00 379.60 50,107
SP 418 a Galvanized Iron Drain pipe, 100mm dia LM 9.15 2,468.45 22,577
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
SP 419b Provide and Fixing Steel Hand Railng LM 128.00 4,749.65 607,955
ENGINEER'S ESTIMATE
Bill No.4.2 Structure (Drain / NJB)
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
401b(i) Concrete Class A2 for NJB With Slipform Paver CM 410.00 12,183.99 4,995,436
404b Reinforcement As per AASHTO M-31 Grade -60 Ton 40.80 104,350.00 4,257,480
ENGINEER'S ESTIMATE
Bill No 5 Drainage & Erosion Works
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
401a(i) Concrete Class "A1" in haunches around PVC pipes CM 20.00 10,935.07 218,701
607a Traffic Signs, Triangular sides 900 mm with Post Each 5.00 10,830.74 54,154
607b Traffic Signs, Circular dia 900 mm with Post Each 5.00 13,361.33 66,807
607c(i) Traffic Signs, with single post assembly SM 25.00 16,995.67 424,892
607c(ii) Traffic Signs, with double post assembly SM 25.00 20,552.73 513,818
609c Reflectorized pavement Studs (raised Profile Type - Single) Each 2,390.00 395.94 946,297
SP-619 Providing and Fixing of MBS Fencing L.M 880.00 14,641.89 12,884,863
607d Manufacture & Installation of Gantry Sign Type-I Each 2.00 1,531,948 3,063,896
607f Manufacture & Installation of Gantry Sign Type-IV Each 2.00 561,549 1,123,098
SP 618(i) Reuse of Kerb stone after removal i/c painting M 100.00 404.26 40,426
ENGINEER'S ESTIMATE
Bill No. 7 General Items
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
702c Operational Cost of Engineer's & Client's Offices Month 10 175,000 1,750,000
703b Operational Cost of Project Laboratory (including Helpers) Month 10 125,000 1,250,000
ENGINEER'S ESTIMATE
Bill No.8 Electrical Works
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Supply, installation, testing and commissioning of the
following items of work, including all material, labour, tools
and accessories etc. required for proper completion of each
item as per specification, drawings and/or as directed by
the Engineer.
801(a) 10 m high single arm conical octagonal (hot dip) galvanized Each 99 65,100 6,444,900
steel pole with extension arm luminaire arrangement, base
plate, J-rag bolts and earthing etc. as shown on drawing.
802 Road Lighting LED Luminaries 120W make Philips, GE or No. 99 50,975 5,046,525
equivalent suitable for M-2 & M-3 roads of wattage suitable
for the project requirements, fully IP 66 with corrosion
resistant die cast aluminum housing, silicon gas kit,
thermally hardened glass complete with LED drivers, surge
protection and all accessories/ components required for the
proper operation of the system. The luminaries shall be fully
flexible for future upgrades and easy replacements for
maintenance purposes. Contractor to submit lighting design
calculation to determine the adequacy of the wattage and
should adjust the number of LEDs/wattage as per project
lighting requirements.
803(a) PVC pipe/conduit Class-D 100 mm dia with accessories Rm 300 1,158.00 347,400
suitable for laying multi-core cables on road crossings.
803(b) PVC pipe/conduit Class-B 100 mm dia with accessories Rm 3,200 732.00 2,342,400
suitable for laying multi-core cables in new Jersey barriers.
804(a) 4-core 16 mm2 PVC insulated and PVC overall sheathed Rm 3,600 887.95 3,196,620
600/1000 Volt grade unarmoured copper cable (Newage,
Pioneer, Fast or Pakistan Cables) laid direct in ground or
pulled in PVC pipe already laid.
804(b) Single core 16 mm2 PVC insulated 450/750 Volt grade Rm 3,600 254.35 915,660
unarmoured copper cable (Newage, Pioneer, Fast or
Pakistan Cables) laid direct in ground or pulled in PVC pipe
already laid as CPC.
804© 4 Core 25mm2 Cu. PVC/PVC 600/1000V Unarmored Cable Rm 100 1,653.15 165,315
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
804(d) 3-core 2.5 mm2 PVC insulated and PVC overall sheathed Rm 3,897 166.80 649,960
450/750 Volt grade copper cable (stranded conductor)
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing) from junction box to the fitting
through the hollow of pole.
805 Road lighting control panel with angle iron frame claded 14 Job 2 260,000 520,000
SWG, sheet steel enclosure having high quality powder
coated paint, color RAL 7032. The LCP shall be complete
with incoming and outgoing MCCBs, Cu busbars, magnetic
contactors, photo-electric switches, meters, indication
lights, construction with IP 54 protection class, door, locking
arrangement etc. and all other accessories as required for
quality work
807(a) 25 mm2 PVC insulated copper earth wires including all Rm 40 457 18,280
fixing accessories as required for earthing of lighting control
panels.
807(b) Earth point comprising of 10 ft. 5/8" dia. (16 mm dia) copper Each 4 6,720 26,880
coated M.S. rods driven in ground near each lighting
control panel. The earthing rods shall be completed with
fixing clamps etc.
807 Supply of 25 kVA, 11/0.415 kV pole mounted transformer, Job 2 325,000 650,000
As per earthing arrangement and all accessories, Installation and
WAPDA Connection Charges with energy meter as per WAPDA
Specs. standards and practice.
Note:
The cost of security deposit and obtaining of 11 kV electrical connection with
installation material from WAPDA shall be finalized as per site requirement and
the cost for the same is not included in the above.
CONSTRUCTION OF NEW BRIDGE ALONG EXISTING RAVI BRIDGE (PHASE-II)
ENGINEER'S ESTIMATE
SUMMARY
Amount
Bill No Description
(Rs.)
ENGINEER'S ESTIMATE
Bill No.8 Electrical Works
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Supply, installation, testing and commissioning of the
following items of work, including all material, labour, tools
and accessories etc. required for proper completion of each
item as per specification, drawings and/or as directed by
the Engineer.
801(a) 10 m high single arm conical octagonal (hot dip) galvanized Each 99 65,100 6,444,900
steel pole with extension arm luminaire arrangement, base
plate, J-rag bolts and earthing etc. as shown on drawing.
802 Road Lighting LED Luminaries 120W make Philips, GE or No. 99 50,975 5,046,525
equivalent suitable for M-2 & M-3 roads of wattage suitable
for the project requirements, fully IP 66 with corrosion
resistant die cast aluminum housing, silicon gas kit,
thermally hardened glass complete with LED drivers, surge
protection and all accessories/ components required for the
proper operation of the system. The luminaries shall be fully
flexible for future upgrades and easy replacements for
maintenance purposes. Contractor to submit lighting design
calculation to determine the adequacy of the wattage and
should adjust the number of LEDs/wattage as per project
lighting requirements.
803(a) PVC pipe/conduit Class-D 100 mm dia with accessories Rm 300 1,158 347,400
suitable for laying multi-core cables on road crossings.
803(b) PVC pipe/conduit Class-B 100 mm dia with accessories Rm 3,200 732 2,342,400
suitable for laying multi-core cables in new Jersey barriers.
804(a) 4-core 16 mm2 PVC insulated and PVC overall sheathed Rm 3,600 1,164 4,190,400
600/1000 Volt grade unarmoured copper cable (Newage,
Pioneer, Fast or Pakistan Cables) laid direct in ground or
pulled in PVC pipe already laid.
804(b) Single core 16 mm2 PVC insulated 450/750 Volt grade Rm 3,600 293 1,054,800
unarmoured copper cable (Newage, Pioneer, Fast or
Pakistan Cables) laid direct in ground or pulled in PVC pipe
already laid as CPC.
804© 4 Core 25mm2 Cu. PVC/PVC 600/1000V Unarmored Cable Rm 100 1,920 192,000
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing)
CONSTRUCTION OF NEW BRIDGE ALONG EXISTING RAVI BRIDGE (PHASE-II)
ENGINEER'S ESTIMATE
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
804(d) 3-core 2.5 mm2 PVC insulated and PVC overall sheathed No. 99 2,820 279,180
450/750 Volt grade copper cable (stranded conductor)
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing) from junction box to the fitting
through the hollow of pole.
805 Road lighting control panel with angle iron frame claded 14 Job 2 260,000 520,000
SWG, sheet steel enclosure having high quality powder
coated paint, color RAL 7032. The LCP shall be complete
with incoming and outgoing MCCBs, Cu busbars, magnetic
contactors, photo-electric switches, meters, indication
lights, construction with IP 54 protection class, door, locking
arrangement etc. and all other accessories as required for
quality work
807(a) 25 mm2 PVC insulated copper earth wires including all Rm 40 457 18,280
fixing accessories as required for earthing of lighting control
panels.
807(b) Earth point comprising of 10 ft. 5/8" dia. (16 mm dia) copper Each 4 6,720 26,880
coated M.S. rods driven in ground near each lighting
control panel. The earthing rods shall be completed with
fixing clamps etc.
807 Supply of 25 kVA, 11/0.415 kV pole mounted transformer, Job 2 325,000 650,000
As per earthing arrangement and all accessories, Installation and
WAPDA Connection Charges with energy meter as per WAPDA
Specs. standards and practice.
Note:
The cost of security deposit and obtaining of 11 kV electrical connection with
installation material from WAPDA shall be finalized as per site requirement and
the cost for the same is not included in the above.