REPORT OF ASSESSMENT CARRIED OUT

AGAINST BS EN ISO 3834

REPORT OF AN ASSESSMENT CARRIED OUT AGAINST


BS EN ISO 3834-2:2005

Quality requirements for fusion welding of metallic materials –


Part2: Comprehensivequality requirements

Company Report No.

Address

Tel:
Description of Business

Quality Related Welding Personnel

Welding Coordination Personnel

Personnel Involved in Assessment Process

Assessment carried out by

Date of Assessment

Signature and Date:

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 1 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No N/a Comments Yes No N/a Comments
5 Review of Requirements &
Technical Review
5.1 General
a) Are the contractual
requirements and technical
data, provided by the
purchaser or in-house,
reviewed by competent staff?
b) Does the manufacturer affirm
its capability to meet all the
requirements?

c) Does the manufacturer verify


that the work content is within
its capability?

d) Does the manufacturer


identify variations between
the contract and previous
quotations, and notify the
purchaser of any resulting
programme, cost or
engineering changes?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 2 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2QUESTIONNAIRE
Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
5.2 Review of Requirements
Are the following considered?

a) The product standard to be


used and any supplementary
requirements.
b) Statutory and regulatory
requirements.

c) Additional requirements
determined by the
manufacturer.
d) The capability of the
manufacturer to meet the
prescribed requirements.
5.3 Technical Review
Are the following considered?
a) Parent material specifications
and welded joint properties.

b) Quality and acceptance


requirements for welds.

c) Location, access and


sequence of welds, including
access for inspection and
non-destructive testing
(NDT).

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 3 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
d) Specification of welding
procedures, NDT procedures
and heat treatment
procedures.
e) Means of qualifying welding
procedures.

f) Qualification of personnel.

g) Selection, identification and


traceability of materials,
welds etc.
h) Quality control arrangements,
including independent
inspection body involvement.
i) Inspection and testing.

j) Sub-contracting.

k) Post weld heat treatment.

l) Welding requirements
e.g. consumable batch
testing, hydrogen content,
backing, surface finish, weld
profile etc.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 4 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
m) Special welding methods.

n) Details of joint preparations


and completed welds.

o) Location at which welds are


to be made.

p) Environmental conditions
E.g. low ambient
temperature.

q) Handling of non-
conformances.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 5 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
6 Sub-contracting
a) Are any activities sub-
contracted by the
manufacturer?
b) Are sub-contractors provided
with the necessary
information to meet the
applicable requirements?
c) Does the sub-contractor
provide records and
manufacturing documentation
to the manufacturer?
d) Does the manufacturer
ensure that the sub-
contractor can comply with
the specified quality
requirements?
e) Is the sub-contractor
provided with the results of
any reviews carried out by
the manufacturer?
f) If the design of the product is
sub-contracted are
supplementary requirements
(if necessary) specified to the
sub-contractors?
g) Has the manufacturer a
written procedure, which
describes how the sub-

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 6 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

contracted activities comply


with the requirements of the
contract/design specification?
h) Does the procedure above
define the tasks and
responsibilities of the welding
co-ordinator?
7 Welding personnel
7.1 General
Does the manufacturer have
sufficient competent
personnel for the planning,
performing and supervising of
the welding production
according to specified
requirements?
BS EN ISO 3834-2 QUESTIONNAIRE
Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
7.2 Welders and welding
operators
Are welders and welding
operators qualified by
appropriate tests? Please
quote standards being used
in the comment collum.
7.3 Welding coordination
personnel
a) Does the manufacturer have
sufficient appropriate welding
coordination personnel at his
disposal?
b) Do welding coordination
personnel have sufficient

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 7 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

authority to enable necessary


actions to be taken?
c) Are the tasks and
responsibilities of welding
coordination personnel
clearly defined?
8 Inspection and testing
personnel
8.1 General
Does the manufacturer have
sufficient competent
personnel for the planning,
performing and supervising
the inspection and testing of
the welding production
according to specified
requirements?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 8 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
8.2 Non-destructive testing
personnel
Are NDT personnel suitably
qualified?

9 Equipment
9.1 Production and testing
equipment
The following equipment shall
be available, as necessary -
a) Power sources and other
machines.

b) Equipment for joint and


surface preparation and
cutting, including thermal
cutting.
c) Preheating and post weld
heat treatment equipment,
including temperature
indicators.
d) Jigs and fixtures.

e) Cranes and handling


equipment.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 9 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
f) Personal protective
equipment and other safety
equipment associated with
the manufacturing process.
g) Ovens, quivers etc. for
treatment of welding
consumables.
h) Surface cleaning equipment.

i) Destructive and non-


destructive testing facilities.

9.2 Description of equipment


The manufacturer shall
maintain a list of essential
equipment used for
manufacturing production,
typically -
a) Maximum capacity of
crane(s).

b) Maximum size of components


that can be handled.

c) Capability of mechanised or
automated welding
equipment.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 10 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref Yes No n/a Comments Yes No n/a Comments
.
d) Size and temperature
capability of furnaces for
post-weld heat treatment.
e) Capacity of rolling, bending
and cutting equipments.
9.3 Suitability of equipment
The manufacturer shall ensure
that the equipment is adequate
for the intended application.
9.4 New equipment
Are appropriate tests carried
out and documented following
the installation of new or
refurbished equipment?
9.5 Equipment maintenance
a) Does the manufacturer have
documented plans for the
maintenance of equipment,
ensuring checks of those items
which control variables listed
in the relevant procedure
specifications e.g.
b) Condition of guides in thermal
cutting equipment,
mechanised fixtures etc.
c) Condition of ammeters,
voltmeters, flow meters etc.
used with welding equipment.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 11 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
d) Condition of cables, hoses,
connectors etc.

e) Condition of control systems


in mechanised/automated
welding units.
f) Condition of temperature
measurement instruments.

g) Condition of wire feeders and


conduits.

h) Procedure which prevents the


use of defective equipment.

10 Welding and related


activities
10.1 Production planning
Does the manufacturer carry
out adequate production
planning and consider, as a
minimum -
a) Sequence of fabrication.

b) The individual processes


required for manufacture.
c) Appropriate procedure
specifications.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 12 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
d) Inspection and testing
requirements, including
independent inspection body
requirements.
e) Environmental conditions.

f) Batch/component/part
identification.
g) Production test requirements.

10.2 Welding procedure


specifications
a) Are procedures prepared in
accordance with BS EN ISO
15609-1?
b) Is the correct use of welding
procedures verified in
production?
10.3 Qualification of welding
procedures
Are welding procedures
qualified prior to use in
production? Please quote
relevant standards being
used.
10.4 Work instructions
Are work instructions/welding
procedure specifications used
for instruction?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 13 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
10.5 Procedures for preparation
and control of documents
Does the manufacturer have
procedures for the
preparation and control of the
following?
a) Welding procedure
specifications.

b) Welding procedure
qualification records.

c) Welder/welding operator
qualification certificates.

11 Welding consumables
11.1 General
Are responsibilities and
procedures for control of
welding consumables
specified?
11.2 Batch testing
Is batch testing of welding
consumables specified?
11.3 Storage and handling
a) Are procedures in place for
the storage, handling,
identification and use of
welding consumables?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 14 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
b) Are these procedures in
accordance with the
supplier’s recommendations?
12 Storage of parent materials
Are all materials, including
those supplied by the client,
stored and identified in a
satisfactory manner?
13 Post weld heat treatment
a) Where appropriate, are
procedures in place, which
are compatible with the
parent materials, welded
joints and application
standards/requirements?
b) Does the manufacturer
maintain adequate and
traceable post weld heat
treatment records?
14 Inspection and testing
14.1 General
a) Are inspections and tests
scheduled for appropriate
points in the manufacturing
process to assure conformity
with specified requirements?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 15 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
14.2 Inspection and testing
before welding
Are the following checked
before welding commences?
b) Suitability/validity of
welder/welding operator
approval certificates.
c) Suitability of welding
procedure specification.

d) Identity of parent material(s).

e) Identity of welding
consumables(s).

f) Joint preparation.

g) Fit-up, jigging and backing.

h) Special requirements from


the welding procedure
specification.
i) Suitability of working
conditions including
environment.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 16 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2QUESTIONNAIRE
Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
14.3 Inspection and testing
during welding
During welding the following EN ISO 3834-5:2005 Table 7 refers. .
should be checked at suitable
intervals or by continuous
monitoring.
a) Essential welding parameters
e.g. current, voltage, travel
speed.
b) Preheat/interpass
temperatures.

c) Cleaning, shape of weld


beads and layers of weld
metal.
d) Back gouging.

e) Welding sequence.

f) Correct use and handling of


welding consumables.

g) Control of distortion.

h) Intermediate examination (i.e.


checking of dimensions)

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 17 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
14.4 Inspection and testing after
welding
Compliance with the relevant EN ISO 3834-5:2005 Table 8 refers.
acceptance criteria shall be
checked by -
i) Visual inspection

j) Non-destructive testing

k) Destructive testing.

l) Form, shape and dimensions


of the construction.

m) Results and records of post-


weld operations e.g. post
weld heat treatment, ageing
etc.
14.5 Inspection and test status
Are measures taken, as
appropriate, to indicate the
status of inspection and test
during manufacture of the
construction?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 18 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
15 Non-conformances and
corrective actions
a) Are measures in place to
prevent non-conforming items
from being used?
b) Are suitable procedures
available at workstations for
repair/rectification?
c) Following repair/rectification,
are items re-inspected and
tested in accordance with
original requirements?
d) Are procedures in place to
avoid recurrence of non-
conformances?
16 Calibration
Does the manufacturer have
appropriate procedures for
the calibration/validation of
measuring, inspection and
testing equipment?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 19 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
17 Identification and
traceability
Where appropriate, is
identification and traceability
maintained during the
manufacturing process?
Do documented systems
include, if necessary,
reference to the following?
Production plans.

Routing cards.

Weld locations.

NDT procedures and


personnel.

Welding consumables.

Parent material.

Location of repairs.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 20 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
Location of temporary
attachments.

Traceability of fully
mechanised and automated
welding units to specific
welds.
Traceability of welders and
welding operators to specific
welds.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 21 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
18 Quality records
These shall include, when
applicable -
Record of requirement and
technical reviews.

Material inspection
documents.

Welding consumable
inspection documents.

Welding procedure
specifications.

Equipment maintenance
records.

Welding procedure
qualification records.

Welder and welding operator


qualification certificates.

Production plan.

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 22 of 23 Uncontrolled when printed
REPORT OF ASSESSMENT CARRIED OUT AGAINST BS EN ISO 3834
Company Name:
Project Number:

BS EN ISO 3834-2 QUESTIONNAIRE


Requirement By the Manufacturer By the Assessor
Ref. Yes No n/a Comments Yes No n/a Comments
18 NDT personnel certificates.

Heat treatment procedure


specifications and records.

NDT testing and destructive


testing procedures and
reports.
Dimensional reports.

Records of repairs and non-


conformance reports.

Other documents as required.

Are quality records retained


for a minimum period of 5
years, or longer if specified?

Prepared by: Reviewed by: Authorised by: Document ID: Date: Revision:
S Brown P Ward R Thomsen QA021F002 20/06/2012 1
© 2011 TÜV UK Ltd. Page 23 of 23 Uncontrolled when printed