Sie sind auf Seite 1von 4

• news • events • cover story • concrete applications •

• concrete feature • concrete equipment • concrete materials •

Save
time and
money on
Mass Concrete
Construction
By John Gajda, P.E.

On a recent bridge foundation the use of 55 MPa concrete. Speci- laborated effectively with the con-
construction project in Northern fications also limited the maxi- tractor from 3,000 km away,
California near an Francisco, CTL’s mum concrete temperature during optimising concrete mix character-
concrete construction consultants curing to 65°C, and the maximum istics for the mass concrete place-
significantly have reduced the time temperature difference (between ments. CTL also utilised its own
and cost for the construction of a any surface and the centre) to a software to conduct precise ther-
series of mass concrete footings. maximum of 20°C at any time af- mal modelling and simulation of
The footing (Fig. 1) is 18.5 m wide ter placement. Insulation was re- concrete during and after place-
by 18.5 m long by 4.75 m deep. quired to remain in place until the ment.
hottest portion of the concrete

Specifications
cooled to within 20°C of the daily
low air temperature. Thermal
Cement and
Although the specifications re- cracking was also prohibited by Concrete
quired that the concrete achieve 35 specification. The concrete mix constituents and
MPa in 28 days, other require- Drawing on its experience pro- quantities were selected to mini-
ments regarding the minimum viding mass concrete consulting mise the temperature rise of the
cementitious content and water- services on more than 100 previ- concrete, meet the project speci-
to-cementitious ratio resulted in ous occasions worldwide, CTL col- fications, and rapidly achieve

Sept-Dec 2003 34
• news • events • cover story • concrete applications •

• concrete feature • concrete equipment • concrete materials •

Figure 1a (above), 1b (below) - Overview of footing and pier prior to concrete placement

35 Sept-Dec 2003
• news • events • cover story • concrete applications •

• concrete feature • concrete equipment • concrete materials •

Figure 2 - Comparison of the specified and calculated allowable temperature differences

strength. The cementitious materials consisted of 250 liquid nitrogen precooling. Thermal modelling of the
kg/cu m of low-heat Type II cement and 135 kg/cu m footing showed that insulation would be required for
of class F fly ash. The coarse aggregate was basaltic, approximately 40 days. During this time, little to no
with a low coefficient of thermal expansion. CTL work could be done on the pier and other structures
measured the heat of hydration of the cementitious that needed to be constructed on the footing.
materials and the thermal expansion of the concrete.
Modified plan
Original plan Confident of CTL’s knowledge in this area, the owner
The simplest way to construct the footing within the allowed the specifications to be modified. In particu-
temperature specifications would have been to deter- lar, the use of a calculated allowable temperature dif-
mine the required initial concrete temperature, ference was substituted for the 20°C temperature dif-
precool the concrete to this temperature, and insu- ference. This change took into account the increased
late the surface until the hottest portion of the con- ability of the concrete to resist thermal cracking as
crete cooled to within 20°C of the ambient air tem- its compressive strength increases. The allowable tem-
perature. Preliminary calculations indicated that this perature difference specific to the footing was calcu-
concrete mix could be expected to increase in tem- lated based on the concrete mix design and footing
perature by 55°C after placement. This meant that the design, and is shown in Fig. 2. Additionally, because
concrete would have to be precooled to a tempera- the contractor wanted to eliminate the costs of
ture of less than 10°C. precooling and also minimise the time of insulation,
Given the project location and placement date, CTL designed an internal post-cooling pipe system
this would have cost approximately US$ 40,000 for to rapidly cool the concrete after placement.

Sept-Dec 2003 36
• news • events • cover story • concrete applications •

• concrete feature • concrete equipment • concrete materials •

Figure 3 - Measured tem-


peratures in the footing

Results ing are seen in Fig. 3. With CTL’s assistance, the con-
tractor was able to complete the footing in nine days,
Eventually the concrete was placed without precooling
shaving 31 days off the schedule. Additionally, CTL’s
at a temperature of 22°C. Through the use of the cool-
expertise eliminated the need for approximately US$
ing pipe system and the calculated allowable tempera-
40,000 in precooling expenses. Similar results were
ture difference, the concrete had cooled enough to
achieved for other footings on this project.
remove the surface insulation 9 days after placement.
Measured temperature profiles from within the foot- Enquiry No: CTT***/3/2003

About the author


John Gajda, P.E., is Senior Engineer with Construction Technology Laboratories. In his 11 years with CTL
he has been involved in a wide variety of projects. Specific to mass concrete, he has been involved in
more than 100 projects throughout the world, most of which were on large bridges, buildings, and mat
foundations. He was also involved in the roughly US$ 2 billion replacement of the San Francisco - Oakland
Bay Bridge, where the piles, pile caps, piers, and pier tables are high strength mass concrete.

37 Sept-Dec 2003

Das könnte Ihnen auch gefallen