Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: _____________________________________

Section A: General Information Please Indicate if not applicable or available for proposed project
1 Project Name:

2a Primary Contact Name


Title:
Phone:
Email:

2b Secondary Contact Name


Title:
Phone:
Email:

3 Project Location:
Street Address
City, County

Latitude
Longitude
Provide in degree/minute/second (DMS) format

4 Point of Interconnection
Is POI located on the Site?
If not what is distance to POI?
Is easement needed to access POI?

5 Commercial Operations Date (COD):


RFP limited to facilities with 2019 or 2020 COD
6 Max Guaranteed Capacity (MW ac):
RFP limited to facilities 10 to 150 MW ac
7 Experience - Affiliate developed and/or constructed generation facilities:

Name & Location Developer Constructor Current Owner Size (MW ac) Fuel type COD

Page 1
Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: _____________________________________

Section B: Price & Terms Summary Please Indicate if not applicable or available for proposed project

1 PPA Base Price ($/MWh)

Please provide Base Price applicable for the first contract year, subject to 2.5% escalation factor
for subsequent years. FOR SOLAR ONLY: Assume NO duty is imposed on foreign-manufactured
solar panel modules as a result of the 9/22/2017 US International Trade Commission "injury"
finding.

2 SOLAR ONLY: Solar Panel Price reflected in PPA Base Price (₵/watt)

Please provide the Solar Panel Price assuming NO duty is imposed on foreign-manufactured solar
panel modules as a result of the 9/22/2017 US International Trade Commission "Injury" finding.

3 SOLAR ONLY: PPA Adder for Each Incremental 10₵ per watt duty ($/MWh)

Please provide adder to the PPA Base Price applicable for the first contract year, subject to 2.5%
escalation factor for subsequent years, for each 10₵ per watt duty ultimately imposed (if any) on
foreign-manufactured solar panel modules as a result of the 9/22/2017 US International Trade
Commission "injury" finding.

4 Asset Acquisition - Development Project Price ($ millions)


Please provide Price applicable for acquisition of project prior to start of construction. Consistent
with terms proposed in the Form Acquisition Purchase Agreement.

5 Annual Production Estimates (Total MWh/year) Please provide annual net energy after degredation, excluding hours of net usage by project
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
Year 10
Year 11
Year 12
Year 13
Year 14
Year 15
Year 16
Year 17
Year 18
Year 19
Year 20

Page 2
Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: ______________________________________

Section C1: Technical Information for Solar Projects Please Indicate if not applicable or available for proposed project

Production
Number Workmanship Warranty
1 Equipment Information: Description / Notes Manufacturer Model Capability Installed Warranty (yrs) (yrs)
PV Panels
Tracking System
Inverters
Transformers
Monitoring System
Other Key Equipment

2 Maximum Generating Capability (MW):


DC Output: Under standard conditions (STC) of 1000 watts/square meter, 77 degrees F, and Atmospheric Density of 1.5 kg/m 3
AC Gross Output: Under standard conditions (STC) of 1000 watts/square meter, 77 degrees F, and Atmospheric Density of 1.5 kg/m 3
AC Net Output: At point of Interconnection

3 Panel Design Orientation Tilt (degrees):


Azimuth (degrees) Zero degrees equals due South
Rotation Angle (+/- degrees) Applicable for Trackers

4 Expected 12 X 24 Generation Profile (P50 Average % Capacity Factor)


Expected generation profile should reflect specific site and equipment and use Solar Prospector meteorological data to calculate average power
output using each individual years' available data from 1998-2009. Exclude hours of net power usage by the Facility.

Hour
(Eastern Prevailing Time) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
24:00-1:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
1:00 - 2:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
2:00 - 3:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
3:00 - 4:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
4:00 - 5:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
5:00 - 6:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
6:00 - 7:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
7:00 - 8:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
8:00 - 9:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
9:00 - 10:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
10:00 - 11:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
11:00 - 12:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
12:00 - 13:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
13:00 - 14:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
14:00 - 15:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
15:00 - 16:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
16:00 - 17:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
17:00 - 18:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
18:00 - 19:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
19:00 - 20:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
20:00 - 21:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
21:00 - 22:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
22:00 - 23:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
23:00 - 24:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

5 Expected 8760 Generation Profile (P50 Average % Capacity Factor) - please upload to Bidder eRoom as a separate file in MS Excel format.
Expected generation profile should reflect specific site and equipment and use Solar Prospector meteorological data to calculate average power
output using each individual years' available data from 1998-2009. Exclude hours of net power usage by the Facility.

Page 3
Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: ______________________________________

Section C2: Technical Information for Wind Projects Please Indicate if not applicable or available for proposed project

Production
Number Workmanship Warranty
1 Equipment Information: Description / Notes Manufacturer Model Capability Installed Warranty (yrs) (yrs)
Wind Turbine
Transformers
Monitoring System
Other Key Equipment

2 Maximum Generating Capability (MW):


AC Gross Output:
AC Net Output:

3 Expected 12 X 24 Generation Profile (P50 Average % Capacity Factor)


Expected generation profile should reflect average power output of proposed specific site and equipment. Exclude hours of net power usage by
the Facility.

Hour
(Eastern Prevailing Time) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
24:00-1:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
1:00 - 2:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
2:00 - 3:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
3:00 - 4:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
4:00 - 5:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
5:00 - 6:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
6:00 - 7:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
7:00 - 8:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
8:00 - 9:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
9:00 - 10:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
10:00 - 11:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
11:00 - 12:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
12:00 - 13:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
13:00 - 14:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
14:00 - 15:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
15:00 - 16:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
16:00 - 17:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
17:00 - 18:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
18:00 - 19:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
19:00 - 20:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
20:00 - 21:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
21:00 - 22:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
22:00 - 23:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
23:00 - 24:00 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

4 Expected 8760 Generation Profile - please upload to Bidder eRoom as a separate file in MS Excel format.
Expected generation profile should reflect average power output of proposed specific site and equipment. Exclude hours of net power usage by
the Facility.

Page 4
Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: ______________________________________

Section E: Financial Information Please Indicate if not applicable or available for proposed project

1 PPA/Acquisition Agreement Counterparty Entity Name

2 PPA/Acquisition Agreement Guarantor Entity Name

3 Guarantor's Relationship to Counterparty

4 Guarantor's Credit Rating


Sr. Unsecured or Equivalent Rating
S&P
Moody's
Fitch

5 Letter of Credit Provider

6 Proposed PPA Credit Package


Proposed Letter of Credit Amount ($ M)
Proposed Cash Deposit ($ M)
Proposed Guarantee Amount ($ M)
TOTAL PROPOSED TOTAL CREDIT AMOUNT ($ M)

7 Proposed Asset Acquisition Credit Package


Proposed Letter of Credit Amount ($ M)
Proposed Cash Deposit ($ M)
Proposed Guarantee Amount ($ M)
TOTAL PROPOSED TOTAL CREDIT AMOUNT ($ M)

8 Estimated All-in Cost to Develop & Construct ($ M)

Land Lease Costs ($/year & escalator if applicable)


Land Purchase Costs ($ millions)
Interconnection Costs ($ millions)
Expected Real Estate Taxes (If Leased, is Lessee Responsible Y/N )

9 Sources of Financing (Existing or Anticipated)


Source 1
Amount 1 ($ M)
Status and Commitment of Source 1

Source 2
Amount 2 ($ M)
Status and Commitment of Source 2

10 Equity Interests of Counterparty (if answer is no, please explain)


Description of Type of Equity Interests (if any)
Will Equity holders have substantive decision-making capabilities?
Are voting rights of equity holders proportionate to ownership interest?
Are investor returns capped (e.g., after a certain benchmark reached)?
Are equity investors guaranteed a minimum return?
Are future capital contributions by equity interest holders required or permitted?

11 Capital Structure of Counterparty ( Current & Projected Post-COD)


Senior Debt Component ($ M; are interest rates fixed or floating?)
Subordinated Debt Component ($ M; are interest rates fixed or floating?)

Page 5
Dominion Energy Virginia 2017 PV Solar/Onshore Wind RFP

Respondent Name: ______________________________________

Section E: Financial Information Please Indicate if not applicable or available for proposed project
Equity Interests ($ M; are interest rates fixed or floating?)

Page 6