WEEKLY ACTIVITY REPORT

DEPARTMENT : EMPLOYEE :
ENGINEERING
902 INDONESIA PROJECT CIVIL COORDINATOR
Date Project Specific Job

3-Jul-17 902 - Indonesia Revised Layout of PPI General Mill Layout EL. 0.00M

Site Observation, Taking Pictures and Record on Ongoing Activity at


Site

Updated Site Activity Log Book for July 3, 2017 activity.

Find PM1 Bottom Headbox container number on EPC Scotland


4-Jul-17 902 - Indonesia
loading activity report as per Mr. Yono's Request.
Site Observation, Taking Pictures and Record on Ongoing Activity at
Site

Updated Site Activity Log Book for July 4, 2017 activity.

Metting with DIP supplier Yunda Paper Machinery at PPI Wonogiri

Metting with DIP supplier Yunda Paper Machinery at PPI Solo Main
5-Jul-17 902 - Indonesia
Office

Updated Site Activity Log Book for July 5, 2017 activity.

Site Observation, Taking Pictures and Record on Ongoing Activity at


Site
Site Observation, Taking Pictures and Record on Ongoing Activity at
6-Jul-17 902 - Indonesia
Site

Updated Site Activity Log Book for July 6, 2017 activity.

Coordination meeting Mr. Bambang at PPI Project Site, Wonogiri.

Site Observation, Taking Pictures and Record on Ongoing Activity at


7-Jul-17 902 - Indonesia
Site

Updated Site Activity Log Book for July 7, 2017 activity.

Find PM1 Deflaker container number on EPC Scotland loading


activity report as per Mr. Anjar's Request.
Composed Extracted Drawing for PM3 Dry-end Winder section Civil
Guide Layout
Site Observation, Taking Pictures and Record on Ongoing Activity at
8-Jul-17 902 - Indonesia
Site

Updated Site Activity Log Book for July 8, 2017 activity.

Composed Extracted Drawing from 902-C465-00-U-05 rA - PM3


Top Layer Couch Pit Guide Detail.

Composed 902 Project Progress Pictures for July 8, 2017 Report.

379706720.xlsx Page 1 of 4
WEEKLY ACTIVITY REPORT
DEPARTMENT : EMPLOYEE :
ENGINEERING
902 INDONESIA PROJECT CIVIL COORDINATOR
Date Project Specific Job

Submitted By:

Approved By:

379706720.xlsx Page 2 of 4
Initial
Week No. 27
KLY ACTIVITY REPORT Date Cut-In 3-Jul-17
Date Cut-Off 8-Jul-17
Date Prepared 8-Jul-17
Checked by
PROJECT CIVIL COORDINATOR Submitted To
Worked Time Notes & Remarks

Done, Submitted to DLE

8:00 AM to 4:00 PM Done

Done

Done

Done
8:00 AM to 4:00 PM
Done

Start

Continue

8:00 AM to 4:00 PM Done

Done

Done

8:00 AM to 4:00 PM Done

Done

Done

Done
8:00 AM to 4:00 PM
Done

Hold

Done

Done
8:00 AM to 4:00 PM
Start/Done

Start

379706720.xlsx Page 3 of 4
Initial
Week No. 27
KLY ACTIVITY REPORT Date Cut-In 3-Jul-17
Date Cut-Off 8-Jul-17
Date Prepared 8-Jul-17
Checked by
PROJECT CIVIL COORDINATOR Submitted To
Worked Time Notes & Remarks

379706720.xlsx Page 4 of 4