Institute of Environmental Engineering & Research (IEER)
(IEER is a WHO Collaborating Center)
University of Engineering & Technology, Lahore
Ph: 042-89029248
Web: wirw.uet edu ok/facuesfacutesinfo/denartment RI
introductionsid=13
:
Iie
The Registrar, y
UET, Lahore,
No, _IEER-UET-2016-227
Dated: 8-04-2016
Subject Annotated/temized reply to the petition file by M/S Worldwide Scientific in
Honourable Court of Syed Faheem ul Hassan Shah, Senior Civil Judge, Lahore
(MIS Worldwide Scientific Vs UET, Lahore)
Dear Sir,
This is with reference to the above cited court case. Find attached the annotated/itemized reply to the points
raised by M/S Worldwide Scientific, in his application to the hourable court
All relevant record, in support of our viewpoint is also annexed with this letter. The next date of hearing is 15-
04-2016
Itis requested to depute legal advisor of UET to plead the case in the above cited court at the said date
Sincerely yours
7 a
a (Prof. Dr. Sajjad H. Sheikh)
°< DIRECTOR
ce
1. Mr Abdus Salam, Senior Law Officer PPRA. It is with reference to his telephonic request
to send the reply to the petition of plaintiff and the relevant record.Itemized response by UET to the notice of WWS in the honorable court of Syed
Faheem ul Hassan, Senior Civil Judge
It is submitted to the honourable court that the pray of the plaintiff is not based on facts. He has
misrepresented the facts and trying to evade his contractual obligation which he is legally bound
to fulfill. Delay in supply of equipment has done irreparable loss to the educational and research
activities of the University. The itemized response to_plaintiff_observation are presented
hereunder:
Para-I
That plaintiff is @ proprietary concern and deals in supply of scientific instruments from
abroad and till date have an experience of 20 years in providing and fulfilling the
demands/requirements agreed between the parties for its supply. Needless to mention here
that plaintiff has a blotless carrier in arranging and providing different instruments as per the
demand. It may also be not out of place to mention here that services provided by the
plaintiff have been up to the mark and commendable.
WWS did not fulfill its contract in current case.
That defendant number 2, through its publication in PPRA website invite tenders for the
purchase and supply of different items, hence, plaintiff having good experience submitted
tender regarding provision of different items according to requirement of defendant number
2. Plaintiff being lowest in rate, defendant no. 2 after opening the tender, decided to issue
contract later to the plaintiff so as to provide the equipment as per details given in the
contract. Finally, the defendant no. 2 agreed with the plaintiff for the provision of the
following equipment ie. 1) Water purification system, 2) benchtop pH/conduetivity/DO
meter; 3) Kjeldhal analysis system; 4) BOD incubator.
response
Itis correct
(Purchase Order was issued on 19-11-2014 through PO No. IR/X1-4/544.)
Para-3
‘That defendant no, 2 and 3 having decided to provide job to the plaintiff, executed contract
agreement dated 16-03-2015 regarding different items having contract no. 950 and 946 in
whieh terms and conditions for import of equipment was finally determined.
response
Itis correct.
(WWS signed CONTRACT (contract No. 946 & 950) with defendant No. 1-3 dated 16-03-
2015 for the supply of items at serial No. 1, 2 & 4)
Para-4
That plaintiff after completion of the formalities, defendant no. 2 and 3, opened different
LCs for procuring of equipment as per demand of the defendant no. 1 to 3. Since, item
detailed at serial no. 3 was complete in-details and no misquotation or mistake existed
thereto hence the said item was imported into Pakistan and supplied to the defendant no. 2
and 3. It is important to mention here that the equipment i.e. Kjeldhal analysis system was
delivered to the consignee within the stipulated period as per agreement, imported from
Germany under this HS code 9027.8000.
‘SrNo. ‘Equipment PON. Tssue date
|_| Water purification system TRIXI-/S44 19-11-2014
2. | Bench top pH/conductivity/DO | IRIXI-4/544 19-11-2014
meter
3._| Kjeldhal analysis system TRIXIASaS 19-11-2018
4. | BOD incubator IRXIAISAa 19-11-2014
Page 1 of 4response
‘The details given in this para do not pertain to the case raised by the plaintiff
(Kjeldhal Analysis System was supplied through HS. Code 9027.8000. It is important to
mention here that at the time of opening of LC, this HS. Code was mentioned in LC
document with the mutual understanding of WWS & defendant No. 2 & 3)
Para-5
‘That as far as item no. 1, 2 and 4 as detailed in para 4 above is concerned, the supplier who
was from Latvia and Poland country had demanded certain corrections through their email
letter dated 12-05-2015 and demanded the correction of HS code no, 8421.2100 despite of
9027.8000 which according to the said supplier was incorrect, hence, in the presence of the
said fault, until and unless no remedial measures were taken the said item could not be
supplied as per international custom tariff rules
Correction demanded by the exporter
LC fied 31D Latest shipment date
LC field 4C Date of expiry
[LC field 47A point 1 Provide the information about the insurance
company’s data
LC field 47A point 4 Shipment deliver this HS code 84212100
It is also important to mention here, that, under the international custom tariff rules, codes
are provided to items, may be of any origin, the reason being that against the said code,
custom authorities and import policies certain taxes, which are leviable against the said
equipment and there are no chances of evasion of tax in presence of the correct HS code
numbers while as per policy in the government sectors/institutions are exempted from tax
Needless to mention here that, if items are exported or imported against wrong HS code
number in LC, hence, in the said circumstance, the importing country or the person would
not accept the same and shipment could not be delivered.
response
‘After the acceptance of Purchase Order (PO No. IR/XI-4/544) by WWS and after signing of
contract agreement, two LCs were opened. LC No. 012800245015 dated 19-03-2015 for
equipment at serial No. 1 and LC No, 012800419615 dated 07-05-2015 for equipment at
serial No. 2 & 4, It is important to mention here that LCs are always opened when some
firm/contractor accept all terms & conditions laid down in contract. In this regard, these LCs
contain LC expiry dates, details of insurance company and HS, Code as well. It is important
to again mention here that at the time of opening of LC, this HS. Code 9027.8000 was
mentioned in LC document with the mutual understanding of WWS & defendant No. 2 & 3
(Copy of LCs attached). This HS. Code 9027.8000 is for the import of “OTHER
INSTRUMENTS AND APPARATUS”. Since the Tender from defendant No. 2. was titled
“Purchase of Lab Equipment on C & F basis for IEER”, therefore this HS. Code was
mentioned in LC document. This HS code is used for import of all scientific equipment by
UET and on the same code the plaintiff provided equipment at serial no. 3. Hence objection
is not valid.
Para-6
That plaintiff through its letter 4-06-2015, after having received objection from the exporter |
| through email dated 12-05-2015 made a request to defendant no. 3 for doing the needful,
letter written by the supplier objections are reproduced as preceding para. Needless to
Page 2 of 4mention here till date the requirement/correction/change in HS code no. demanded by the
supplier at till date has not been attended to by the defendant no. 1 to 3, with the result that
the equipment to be supplied to them could not be undertaken, The reasons have already
been explained in the preceding para,
response
It is pertinent to mention here that LC for Water Purification System was opened on 19-03-
2015. Plaintiff never objected to it during two and a half month and wrote letter just 15 days
before the expiry of LC. This clearly shows that he was not serious in supplying the
equipment. In addition, no such objection was raised for equipment at serial no. 2 and 4
meaning thereby that he has no such objection, though baseless, for these two equipment.
(Note: Plaintiff's letter dated 04-06-2015 was only for “Water Purification System and not
for other equipment at serial No 2 & 4)
Para-7
That plaintiif through its letters dated 4-06-2015 had requested the defendant no. 1 to 3 to
meet with the requirement of the principle company/exporter i.e. to correct the existing
faults so that the exporting party can deliver the equipment after its process in Pakistan for
the use of the defendants as per their demand.
response
These demand of the plaintiff was not in line with the agreement signed and conditions
agreed by him with the respondent no. 2 and 3.
Para-8
That instead of meeting with the requirement and accepting the fault on their behalf thereby
correcting the same, the defendants had been adamant and had been avoiding to do the
needful which has resulted in nonfulfillment of the contract granted to the plaintiff.
response
The pray of the plaintiff is in grave contradiction with the already signed agreement with
defendant no. 2 and 3. Hence not acceptable.
Para-9
That plaintiff through their letter 22-03-2016 informed the defendants no. I to 3 that for a
number of times we look up the matter with defendants no. 1 to 3, but for reasons best
known, they failed to undertake the request made for change of HS code from 9027.8000 to
8421.2100. hence, due to delay in adamant attitude defendants no. 1 to 3, the exporting party
‘was now reluctant even accepting the LC but on our insistence, they agreed to send the
equipment provided we send them cash for the import of required equipment but on the
other side in spite of best efforts defendants no. 1 to 3 did not agree with this proposal even
though we had requested them in order to show our bonafides that plaintiff are willing and
ready to purchase the said item on cash payment if an undertaking is given by the defendants
that they would accept the equipment and make payment the moment itis delivered to them.
Because the principal company/importer is reluctant/disagree said shipmenvequipment due
to the elapse of period
response
This demand of the plaintiff is in grave violation of the clause 8 of the contract agreement,
signed by him, that states that the equipment will be supplied on Cost and Freight (C&P)
basis. Now that the plaintiff demands that he will supply the equipment by other means,
which is a violation of his already signed agreement, Hence not lawful,
Para-10
That defendant no. 2 has now issued a letter dated 28-03-2016 thereby putting the plaintiff
to notice that in case of failure to meet the contractual obligation of their behalf, defendant
no. 2 will be well within his rights to forfeit the bid security already held by them on the
ground of unfurnished equipment supply as detailed in section 17 of the agreement. Needles
to mention here that in spite of the fact, the defendants no, 1 to 3 were and are at fault, but
even then, they have issued a show cause notice extending their intentions to dilute the
contract and as a result of that forfeit the security amount which they could not do otherwise
Page 3 of 4as no fault of the plaintiff. It has also been observed through letter dated 28-03-2016 that in
case of non-fulfillment of the contract, defendant no. 1 to 3 reserve the right to issue to
defendant no. 4 to blacklist the plaintiff for all future so that they cannot even early their
livelihood through lawful means.
It is important to mention here that as per terms and conditions of tender, the defendants no.
1 to 3 were bound to open LC in favor of the principal for a minimum sum of Rs 4000 Euro,
otherwise the same would not be acceptable, which has been violated by the above stated
defendant,
response [It is important to mention here that plaintiff was given ample time to resolve the issue. In
this regard, Minutes of Meeting dated 18-03-2016 were issued to them demanding their final
decision for the supply of equipment at serial No. 1, 2 & 4. In that response plaintiff in his
letter dated 22-03-2016 refused to supply equipment through LC which was clear violation
of contract.
LC on which plaintiff had objections (for Water Purification System) was worth of 4500
Euro, and not less than 4000 Euro as plaintiff mentioned. Thus plaintiff is misleading the
honourable court and wasting time of both the honourable court and the UET employees.
Para-11 | That cause of action accrued to the plaintiff firstly when the contract was executed between
plaintiff and defendant no. 1,23 and thereafter on 28-03-2016 through which they have
vividly shown their intention of firstly cancelling the contract of the plaintiff and as a result
thereof for forfeiting the amount held by them as security without any fault on the part of
plaintiff and also making a demand to defendant no. 4 to blacklist the plaintiff.
response — | The statement of plaintiff is not based on facts. Defendant No 2 did not mention anything
regarding “Cancelling the Contract” in his letter dated 28-03-2016, However, defendant No
1 to 3 can forfeit the Bid Security and can recommend blacklisting the WWS, to PPRA, due
to the fact that it failed to meet its written agreement and resulted in irreparable damage to
the research and teaching activity of the University of Engineering & Technology, Lahore
In view of the above submissions, it is prayed
1. The case of the plaintiff may be discharged
2. The honourable court is requested to direct the plaintiff to supply the unfurnished
equipment as per his contract obligations and conditions laid down thereof in the
signed contract agreement without further loss of time. This delay has already
resulted in irreparable loss to the educational and research activities of this
department
Page 4 of 4