MID EXAM

OPERATION FUNDAMENTAL

Disusun Oleh :

Marcelo Caetano Araujo


1600004181

BINUS UNIVERCITY JAKARTA

BINUS GRADUATE PROGRAM ONLINE

MASTER BUSINESS SCHOOL

2018

Prepared By: Marcelo Caetano Araujo/1600004181


Case Study
(Individual Assignment)

Topic: Project Management


Time: 1 Week

1. Describe the project network to build a house from the data below. Calculate the
time and critical path.
Activity Description Predecessor Time (Days)
Activity Description Predecessor Time (Days)
A A Clear the location - 1
B Bring the tool to the location - 2
C Conducting excavations A 1
D Pour the foundation C 2
E Plumbing installation from outside B,D 6
F Create a home frame D 10
G Installation of electric wire F 3
H Install the floor G 1
I Installing the roof F 1
J Installation of plumbing from inside E,H 5
K Installing the roof I 2
L Installation of the outer wall layers F,J 1
M Installing windows and outside doors F 2
N Build a wall L,M 4
O Isolate the walls and ceiling G,J 2
P Close the walls and ceiling O 2
Q Isolate the roof I,P 1
R Finish the interior P 7
S Finish the exterior I,N 7
T Build a garden S 3

Prepared By: Marcelo Caetano Araujo/1600004181


2. Calculate the time and critical path from the data below

3. Calculate the time and critical path from the data below
Activity Predecessor Time (Days)
A - 21
B A 14
C A 14
D B,C 3
E D 70
F D 70
G D 14
H G 1
I H 1
J D 1
K J 1
L D 7
M L 7
N D 7
O M 14
P O 1
Q E,F,P 1
R Q,I,K 1
S M,R 2

Prepared By: Marcelo Caetano Araujo/1600004181


The Answare :

Prepared By: Marcelo Caetano Araujo/1600004181


1. Calculate time and Critical Path for question number 1
a. Network Diagram AON

M,2

L,1
N,4

F,1 G,3 H,1

D,2
S,7
J,5
C,1

T,3
A,1
I,1 O,2

Start E,6

B,2
K,2

P,2
R,7

End

Q,7

Prepared By: Marcelo Caetano Araujo/1600004181


b. Calculate time and Critical Path

Based on the data in the question number 1, then the results of the analysis as shown above. The explanation of the results are
as follows:

1. The total length of work of the project is 63 days or 2 months.


2. Critical Path of the project is:
a. A Clear the location (A)
b. Conducting Excavation (B)
c. Pou the foundation (D)
d. Create a home frame (F)
e. Installation of electri wire (G)

Prepared By: Marcelo Caetano Araujo/1600004181


f. Installation the floor (H)
g. Installation of plumbing from inside (J)
h. Installation of the outer wall layers (I)
i. Finish the exterior (S) and
j. Built a garden (T)

2. Calculate time and Critical Path for question number 2


a. Diagram Network AON

D,3

C,1 J,2

E,2 G,1 H,1


A,3 K,2 L,2

Start I,3
B,14
F,2
N,4 M,2

O,2 End

Prepared By: Marcelo Caetano Araujo/1600004181


b. Calculate time and Critical Path

Based on the data in the question number 2, then the results of the analysis as shown above. The explanation of the results are
as follows:

1. The total length of work of the project is 43 days or 1 month 13 days.


2. Critical Path of the project are : Item G, H, I, K, L, M and O

Prepared By: Marcelo Caetano Araujo/1600004181


3. Calculate time and Critical Path for question number 3
a. Diagram Network AON

N,7 O,14

L,7 M,7

S,2 End

G,14 H,1 I,1 P,1


C,14

A,21 D,3 F,70

Q,1
Start
R,1
B,14 E,70

J,1 K,2

Prepared By: Marcelo Caetano Araujo/1600004181


b. Calculate time and Critical Path

Based on the data in the question number 3, then the results of the analysis as shown above. The explanation of the
results are as follows:

1. The total length of work of the project is 250 days or 8 months and 10 days.
2. Critical Path of the project are: Item A, B, D, E, F, Q, R and S

Prepared By: Marcelo Caetano Araujo/1600004181