Beruflich Dokumente
Kultur Dokumente
M ay 2016
Contents
Location and Topography
Geology and History
Reserves and Strategic Timing
Timeline/Mine Overview
Conveyor Decline Redesign
Caving Update
Conclusions
2
East Ertsberg Skarn System – Geology & History
3
Grasberg Minerals District & Reserves
Tonnes Grades Payable Metal
Plan View
Cu Au Cu Au
(millions) (%) (g/t) (Bn lbs) (MM Ozs)
Grasberg &
Kucing Liar
Grasberg Block Cave 962 1.03% 0.78 18.4 15.6 Grasberg
open pit
Kucing Liar 395 1.27% 1.09 9.4 6.4
DMLZ
Big Gossan 54 2.26% 0.99 2.5 1.1
Deep MLZ 460 Big
0.89% 0.74 7.9 8.7
Gossan DOZ
Deep Ore Zone 115 0.56% 0.69 1.2 2.0
Underground Total 1,987 1.05% 0.83 39.4 33.8 Grasberg
Block Cave
Kucing
Liar Amole
N
Grasberg Open Pit 144 1.02% 1.20 2.7 4.5
2,900 m elev DOZ
District Total 2,130 1.05% 0.86 42.1 38.3
Big
Kucing Liar Spur
Gossan Grasberg
MLA DMLZ
Big Gossan Spur BC Spur
N DMLZ Spur
Portals
(at Ridge Camp) Common Infrastructure
2,500 m elev
Deep MLZ - Timeline
Prefeasibility DMLZ Spur Feasibility Undercutting
Study Started Study (August)
(AB Adits) Completed 80,000tpd
Completed
First Drawbell
Conveyor (September)
& Service
Decline
Trade-off Studies & Started Mine Development & Production
Value Engineering Construction Ramp-Up
2021
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2022
5
Deep MLZ Mine – Overview
View Looking West
Surface (3020 mL) Primary Exhaust Fans
(DOZ & DMLZ)
To Ridge Camp
Vent Raises
(530 m long)
AB Adits (2500 mL)
DOZ (3100 mL)
8
Major Project Impacts – Conveyor Declines
Re-Route Re-Design
Surface (3020 mL)
Water Intersect
10
Major Project Impacts – Conveyor Declines
12
Major Project Impacts – Conveyor Declines
“Wrong side”
Drawbelling: 15 open
Undercut area: 12,500 m2
HR: 28m
Airgap: 10-15m (two holes)
Constructed D/P’s: 180
Three chutes installed
Some initial issues on drawbell
design and execution
14
Conclusions
The DMLZ mine is critical in the transition from open pit to underground
Early start allowed for some “time” contingency and reduced risk
DMLZ: 7 years to initial caving; 7 years to sustained full production
Flexible approach delivered by the Engineering and Operations teams
Good collaboration, rapid response and some heated debates
The feasibility plan was adhered to in concept but significant changes
were discussed and applied as required
Mitigating schedule risk was a priority
Caving has started – so the work is just beginning
15
Questions?
16