Beruflich Dokumente
Kultur Dokumente
The CGS stations are covered under ABT regulations i.e., three
part tariff where as there is no ABT for State generators.
While giving one day ahead schedule for generation dispatch duly
considering the variable cost in the order of Merit, there are certain time
blocks (mostly during night hours i.e., 10 PM to 04 AM) during which
backing down is necessitated in view of surplus availability and low
demand.
(A) AP has 11 generators in the state and 9 in the CGS. The generators
get backed down as follows:
NTS ( 169 ps ) at 49.90 HZ
RTPP ( 141 ps ) at 50.0 HZ
Lancco (127 ) at 50.04 HZ
Other generators (79 to 105 ps) are in narrow frequency band of
50.12 to 50.22 HZ and their backing down follows almost simultaneously.
(B) Backing down of generation is also resorted to when there are line
constraints as in the following cases.
(D) If hydel units are to be run to generate more energy than required
(at NSR, SLM) to meet irrigation demand or in case of spilling of
Reservoirs, we have to back down generators (State/CGS) to avoid high
frequency. Similarly, load crash in other States resulting in sustained
high frequency necessitates backing down of State Generators
immediately and later CGS.
Under the above conditions the shift incharge gives fax message
to the generators (from high variable cost to low variable cost) in the
order of Merit while taking backing down limits (as per PPA
conditions/technical limits) into consideration indicating the amount of
power to be backed down and duration.
(E) Due to the limitations on the number of backing down instructions
specified in the agreements and also when the demand fluctuates due to
weather conditions or for any other reasons the following conditions
arise :