Part 2
Edy Saputro
Mining Engineer
PT. Thiess Contractors Indonesia
Satui Coal Mine Project
HOW TO SETING UP THE
SCHEDULLING Click Here
Creating Calendar (Give any Names)
Click Here
Setting up the Level
Level 1 Set as YEAR
Level 2 (Month), Level 3 (Week)
and Level 4 (Day)
Click Finish
Productive Activities. Example (No 1 at Parting)
Precedence Means no. 2 (Parting) can’t be schedule after no 1 (OB) has finished
Put 1 at Parting
(Precedence)
Create Productive Activity
Create Dependency Rules
Click Here
There are Five Type of Dependency Rules.
You just choose one of all.
If You have Script type of
Dependency Rules, Then click
Script
If you want to use Absolute Address, then
put Successor and Predecessor.
n Means : Block 14 West\W01\1 can’t be schedule
if block 12 East\E02\2 not yet scheduled.
Relative Address Means at level 5 (Bench) always
mining down
Absolute Bearing
Relative Bearing
Proximity Constrain
Proximity constraints are used to control the interaction between resources
where they have been assigned the same input path steps, either using a
common input path or by having common steps within their own
paths. Proximity constraints are used to define the impact that resources have
on each other.
Preschedule
Means If there are block available on
the database will not included to the
scheduling
n Adding Records to the Preschedule
Table
n When you first create a scenario, there
will be no Preschedule Table attached to
it. Create a new Preschedule Table or
assign an existing table to the scenario.
To add records to the Preschedule Table,
you must edit it.
n
n Stock Piles, Dump and Dump Path will be
explain at Tutorial XPAC Part 3………..…..
n Be Patience…
Click Here
Displaying Screen when you
adding the equipments, After
already add, Back to Scenario
Click Here
Click on the equipments, edit the
activity that you want