Members of the Zero Waste SA
Board approving this Business Plan
Member
Mr Allan Holmes (Chair)
Mr Frank Brennan
Ms Megan Dyson
Ms Cheryl Hill
Mr Lachlan Jeffries
Ms Sally Neville
Dr Anne Sharp
Mr Mark Withers
The Zero Waste SA Board (the Board) is the governing body of Zero Waste SA and must consist of six to
10 members. The Board’s membership must include persons who together have, in the Governor’s opinion,
practical knowledge of, and experience in:
• environmental sustainability
• local government
• regional affairs
The Board members, as listed above, satisfy the requirements of section 9(6) Zero Waste SA Act 2004.
Contents
1 Introduction 2
2 Our direction 4
7.5 Priority area: Problematic and hazardous waste 24
7.5.1 Program: Household hazardous waste and farm chemical collections 24
7.5.2 Program: Support implementation of the Waste EPP 24
7.5.3 Program: Contaminated soil strategy – remediation and reuse opportunities 25
7.5.4 Program: National and State policies 25
10 Budget 39
This Business Plan sets out South Australia’s Waste Strategy 2011-2015 has two key
actions for the next three years objectives: ‘maximising the useful life of resources
through reuse and recycling’ and ‘avoid and reduce
which address the objectives waste’. The strategy outlines priorities for action and
in South Australia’s new waste sets targets for diverting waste from landfill.
strategy–the State’s second The vision of zero waste remains fundamental to the
such strategy. new strategy and continues to be reflected in this
Business Plan. This concept challenges ‘end of pipe’
solutions and encourages the cyclical use of materials
in our economy.
Building on Zero Waste SA’s work to date, as well
as addressing the more challenging areas of ‘reuse’
and ‘waste avoidance’ are the key directions in this
Business Plan.
Financial incentives, such as grants, continue to
be central to Zero Waste SA’s work, stimulating
investment in new technology, infrastructure,
research and development. Education and finding
better ways to engage with the community is equally
important as we encourage individuals to play their
own role in the journey towards zero waste.
Developing new relationships and networks and
nurturing existing partnerships remain critical to our
work. We continue to capitalise on our strengths
and share our wealth of world-class knowledge and
experience to drive changes for a more sustainable
approach towards resource management.
We can always do more, and find smarter ways of
realising our zero waste goals. With this Business
Plan we have a blueprint which will help guide the
efforts of Zero Waste SA and the South Australian
community.
To our partners, supporters, program participants
and passionate advocates for the zero waste mission,
thank you. We are creating a more sustainable
future for South Australians through improved, and,
at times, leading edge practices.
Allan Holmes
Chair, Board of Zero Waste SA
1
1
2
1 Introduction
2 Our direction
Treat
Dispose
Least Preferable
Environment and Water Ministerial Council
Department of Sustainability, Environment, Water, Population and Communities
National Waste Policy
Resource management
and recycling industry
Manages resource recovery
and residual waste activities
Individuals
Are responsible for changing wasteful consumption practices, such as through better buying decisions
* Estimated from Recycling Activity Report 2008–09: assumes 30% MSW disposed to landfill; also supported by ZWSA-funded kerbside audit data
of 3-bin system from 2008 and 2009 with collection frequency (all tenements) of weekly residual waste, and fortnightly co-mingled and fortnightly
green organics: these audits typically find diversion in mid-50% range
** Estimated from Recycling Activity Report 2008–09: assumes 43% C&I disposed to landfill
*** Estimated from Recycling Activity Report 2008–09: assumes 27% C&D disposed to landfill
5
11
12
The 2010–11 SA Recycling Activity This significant increase appears to have occurred
Report (Rawtec) shows that due to the substantial resource recovery of waste
fill – about an extra one million tonnes – which took
South Australia remains a strong place during 2010-11 at several major infrastructure
performer in recycling and projects in South Australia, including the Adelaide
recovery of resources. Desalination Plant and new Royal Adelaide Hospital.
Even if the effects of these infrastructure projects
were removed from South Australia’s 2010-11
In 2010–11, 4.31 million tonnes
resource recovery data, the increase in diversion
of materials was diverted from would be 20%.
landfill to recycling in South
South Australia’s Waste Strategy 2011–2015 sets
Australia – a 57% increase from further stretch targets for kerbside recycling and,
the 2.76 million tonnes recycled to achieve them, the Business Plan encourages local
in 2009–10. The South Australian government to embrace food waste collection and
per capita recycling rate has reduce contamination of recyclables.
increased to the second highest South Australia performs well in C&D, beverage
level of the last seven years at container and steel recycling, and leads the way in
the recycling of some plastics (mainly PET and HDPE
2,600 kg/capita.
polymers from the beverage sector).
South Australia has a large network of privately
operated drop-off centres (some 115 across the
State). Local councils are committed to working
with State Government and industry towards
sustainability and resource conservation. The State
also has industry leaders in the composting and C&D
recycling sectors.
6
13
14
This Business Plan is aligned with the Waste Strategy’s two key
objectives illustrated in Figure 3 below.
Each objective is addressed separately in sections 7 and 8 of this Business Plan. Actions for each objective
are listed by priority areas including waste (resource) streams. Each area lists actions from the Waste Strategy
and sets an indicative expenditure budget for each program with desired outcomes.
Figure 3. Relationship between South Australia’s Waste Strategy 2011 to 2015 and this business plan.
7
15
PROGRAM
16
analysis, evaluation and reporting ZEUS currently stores data on illegal dumping,
household hazardous waste and farm chemicals,
to support targets and assess the municipal solid waste, composted organics, container
adequacy of the Waste Strategy deposit, litter, landfill, grants and incentives. In future,
ZEUS will:
Building our knowledge and data about waste and
recycling is essential to support the achievement • report on waste and recycling data at a State,
of the Waste Strategy’s targets and to assess its metropolitan and regional level, and at an
adequacy. To monitor how effective our programs individual council/organisation level as this level of
are, and to identify areas for additional attention, we data becomes available
need to know and understand what is happening with • include data about organic waste composted and
waste streams, recycling performance, markets and recycling from material recycling facilities and
consumption. Several studies prepared for ZWSA transfer stations
have highlighted the lack of quality data about the
sector, which the following programs aim to rectify. • capture data online from councils, recyclers and
landfill operators in regular reports and audits.
7.1.1 Program: Waste audits and
recycling activities study • Additional modules will be planned as modelling
requirements change or as external requirements
This annual survey collects data from South need spatial analysis modelling.
Australian recyclers and reprocessors to provide
stream by stream and waste type recycling tonnages. Budget for the next three years:
The data summarises the current market, including
its market size and strength. Previous surveys 2012-2013 2013-2014 2014-2015
have shown a steady increase in recycling. The (indicative) (indicative)
South Australian Recycling Industry Investment Review
$308,000 $310,000 $312,000
(Rawtec, 2009) identified the areas of greatest need
and best return on investment.
17
Budget for the next three years: • Commercial incentives program – Recycling at
Work (see program 7.3.2) seeks to introduce
2012-2013 2013-2014 2014-2015 robust collection systems in commercial and
(indicative) (indicative) industrial premises.
$419,000 $150,000 $50,000 • Kerbside incentive program – including food waste
(see program 7.2.2) is focused on the introduction
of food waste collection in households.
ZWSA will prepare a map of food activities to
identify points on the value chain where food waste
is generated and quantify volumes. This will open
opportunities not yet explored and inform current
intervention programs. Monitoring and review of
kerbside collection systems will be undertaken to
ensure maximum performance.
2012-2013 2013-2014 2014-2015 The program has been reviewed and undergone
(indicative) (indicative) continuous improvement, and is strongly supported
by regional councils. ZWSA will support local
$300,000 $300,000 $300,000 government to review regional waste management
plans in the future. In 2011–12, 19 regional
infrastructure projects were successful in receiving
a total of $1.7 million in funding under this program,
mostly directed to new or improved transfer stations
and recycling facilities in rural areas. Funding in 2012-
13 is allocated to projects awarded in 2011-12 as
projects gain approvals and achieve milestones.
The project will investigate waste management • encourage better contracting and monitoring of
options to meet the requirements for all waste household collection services
streams produced in the Unincorporated and
Outback Areas of South Australia. The report • coordinate and advocate for national solutions to
and strategy will provide guidance as to how best problematic waste eg packaging; and hazardous
support improved waste management practices, waste
infrastructure and services to reduce the
• support the implementation of the Waste EPP
environmental, social and financial burden associated
with waste generation in Outback Areas. • facilitating local government discussion of key
issues of relevance to ZWSA.
Budget for the next three years:
Budget for the next three years:
2012-2013 2013-2014 2014-2015
(indicative) (indicative) 2012-2013 2013-2014 2014-2015
$10,000 $0 $0 (indicative) (indicative)
$54,000 $54,000 $54,000
21
7.3 Priority area: Commercial Successful projects will be provided funding from
$50,000 to a maximum of $300,000 (excluding GST).
and industrial waste Funds will also be spent on projects awarded in
The Waste Strategy identifies the following priority 2010–11 and 2011-12 as projects gain approvals and
actions for ‘maximising the useful life of materials achieve milestones.
through reuse and recycling’ in C&I waste:
Budget for the next three years:
• improving source separation, collection systems
and sorting infrastructure 2012-2013 2013-2014 2014-2015
(indicative) (indicative)
• improving waste management and recycling
service delivery by the private sector $900,000 $900,000 $900,000
• reducing barriers to the use of recycled materials 7.3.2 Program: Commercial incentives
in projects or products (Recycling at Work)
• identifying solutions to achieve diversion of C&I in ZWSA’s Recycling at Work program aims to
regional areas encourage and support effective recycling collection
systems for small to medium businesses in
• supporting development of guidance for metropolitan Adelaide. ZWSA works with waste
management of farm generated waste streams collection companies to introduce source separated
co-mingled dry recycling systems and/or organics
• supporting implementation of the Waste EPP collection systems.
• identifying chemical hazard reduction and related Recycling from C&I sector enterprises is now well
opportunities in government and business, and established in most large businesses and many
identifying business leaders who can assist with medium sized businesses in all metropolitan centres
education and change across Australia. In small to medium enterprises
(SMEs), recycling is much less common and significant
• identifying recycling systems, resources and tools quantities of potentially valuable resources are
for workplaces to assist with ongoing awareness discarded to landfill. Waste reduction in the C&I
• working with economic development agencies to sector needs sustained emphasis on developing
look at growing resource recovery sectors (e.g. and implementing practical strategies for collecting
e‑waste sector) recyclable material.
The program (launched in January 2009) provides
• monitoring energy recovery enterprises to ensure 11 waste collection companies with funding to
that viable options for higher-order beneficial uses enable new recycling services to be introduced
are not circumvented, consistent with the waste into businesses. The program was supported by
hierarchy. $576,800 in Australian Packaging Covenant funding
from 2009 to 2012. The program has been reviewed
7.3.1 Program: Metropolitan
with recommendations to improve the program’s
infrastructure (industry investment
performance to be introduced in 2012-13.
incentives)
The highly fragmented C&I sector has many
The Metropolitan Infrastructure Grants program
very competitive small, medium and large scale
aims to increase the ability of local reprocessors
enterprises serviced by several waste and recycling
to produce high value end-use products from
providers. It presents challenges in the diversity of
recyclables by investing in infrastructure that enables
activities and wastes generated. The sector must be
greater reuse of waste materials and reduces
approached with a range of complementary tactics,
waste sent to landfill. The State Government has
including placing more responsibility on producers
committed to providing $7.3 million over four
and manufacturers to manage their products beyond
years for investment in key waste infrastructure
the point of manufacture or sale; and implement
across South Australia. ZWSA has provided six
improved waste handling, collecting and processing.
rounds of grant funding for metropolitan recycling
infrastructure projects during the past seven years. ZWSA continues to invest in this area to gain
Priority projects will be determined based on the knowledge and achieve significant diversion of
findings from the investment review in 2009–10 and a materials such as packaging and organics to more
multi-criteria analysis. beneficial uses, and identify recycling systems,
resources and tools for workplaces to assist with
In 2009–10, ZWSA commissioned the Recycling
ongoing awareness. In delivering Recycling at Work,
Industry Investment Review, which projected future
ZWSA maintains strong links with business and
recycling infrastructure needs and considered
industry and with ZWSA’s Industry Program (see
investment opportunities. In line with the findings
program 8.3.1).
of the review, priority areas for investment were
identified and have been incorporated into the
Metropolitan Infrastructure Grants program.
22
Budget for the next three years: 7.3.4 Waste Management Association of
Australia
2012-2013 2013-2014 2014-2015
(indicative) (indicative) The Waste Management Association of Australia
(WMAA) SA Branch represents and advocates its
$335,000 $500,000 $500,000 members’ issues. The Waste Strategy recognises
that ZWSA’s partnership with the WMAA provides
7.3.3 Program: Explore opportunities valuable input into decision-making processes.
for industrial symbiosis This continued partnership will help WMAA link
Industrial symbiosis is based on the premise that one the industry with ZWSA. ZWSA will continue to
industry’s waste can be a valuable input to another support WMAA to:
organisation. For example, in 2006-07 ZWSA • hold events to improve industry knowledge and
provided financial support to the Adelaide Brighton expertise, and provide networking opportunities
Cement and ResourceCo fuel substitution program
for cement manufacturing. • administer working groups and distribute ZWSA
Significant progress has been made internationally information to members.
with governments establishing a structured approach The WMAA holds briefing sessions on a range of
to facilitate industrial symbiosis. The most successful ZWSA issues each year.
example is the United Kingdom’s National Industrial
Symbiosis Program (NISP) established in 2005. From South Australia will host the 2012 and 2014
a total of £23 million in funding (over five years), the Enviro Conference and Exhibition at the Adelaide
NISP has diverted 5.2 million tonnes of industrial Convention Centre. Enviro is Australia’s peak
waste from landfill; generated £151m in new environmental and sustainability gathering convened
investment; saved participants over £131 million and every two years. The Conference is organised
reduced carbon emissions by over 5.2 million tonnes. by Enviro Connections, a joint venture between
The UK NISP model is being implemented by other the Australian Water Association and the Waste
EU countries, the USA, China and Japan. Management Association of Australia. Additional
support to the Conference is also provided by the
ZWSA will continue to identify opportunities in Clean Energy Council, Environmental Institute of
South Australia to develop a broader industrial Australia and New Zealand and Sustainable Business
symbiosis program in South Australia. Funding will be Australia. ZWSA will provide funding support of
used to conduct practical studies that can generate $40,000 for each Enviro Conference to be held in
examples of projects and provide insight into Adelaide in 2012 and 2014 through its agreement
whether an industrial symbiosis program is feasible in with WMAA.
South Australia.
Budget for the next three years:
Industrial symbiosis, as with ZWSA’s Industry
Program, is likely to be more successful with an 2012-2013 2013-2014 2014-2015
integrated approach that addresses solid waste, (indicative) (indicative)
energy, water and lean processes. ZWSA will
collaborate with other government agencies through $68,000 $68,000 $68,000
the Business Sustainability Alliance to determine
government wide support for industrial symbiosis.
7.4 Priority area: Construction Key actions that KESAB has committed to include:
and demolition waste • development and pilot of a clean site module, run
frequently by at least one training provider by 2014
South Australia’s Waste Strategy 2011–2015 identifies
the following priority actions for ‘maximising the • deliver up to six rural/regional workshops per
useful life of materials through reuse and recycling’ in annum
C&D waste:
• four demonstration best practice sites in
• developing markets and removing barriers to the metropolitan and rural areas
responsible use of secondary materials such as
concrete, aggregates, fill materials • four on-site best practice demonstration days.
• improving the quality of recycled materials Budget for the next three years:
ensuring fit for purpose
2012-2013 2013-2014 2014-2015
• promoting source separation wherever feasible (indicative) (indicative)
• supporting the implementation of the Waste EPP $10,000 $10,000 review
• embedding waste reduction and management 7.4.2 Program: Markets for construction
practices in vocational training courses and demolition materials
• encouraging salvaging and reuse of building The Sustainable Markets and Innovation (industry
materials. investment incentives) program will also provide
Significant change in this sector during the past opportunities to the C&D sector to develop and
six years has seen large investment in new improve markets for secondary materials (see
infrastructure and innovation. Nevertheless, program 7.7.1).
specifications are needed for products to improve
their acceptance in civil works and other applications.
• encourage the recovery and treatment of oils, Budget for the next three years:
solvents and other valuable materials for reuse
2012-2013 2013-2014 2014-2015
• reduce hazards through hazardous waste (indicative) (indicative)
collection, recycling and appropriate disposal
$793,000 $763,000 $790,000
• encourage remediation of low level and high level
contaminated soils for reuse. 7.5.2 Program: Support implementation
Household chemicals can be dangerous without safe of the Waste EPP
storage and disposal. ZWSA, with the assistance The Waste EPP will progressively ban certain wastes
of local government, undertakes free household to landfill including computers, oil, lead acid batteries
hazardous waste collections to help the public and compact fluorescent lights. ZWSA will take a
dispose of unwanted chemicals in an environmentally supporting role to enable the Waste EPP. Strategies
safe way. will be developed for banned materials including
Licensed professional waste management contractors high volume/low toxicity materials such as compact
set up temporary collection points in metropolitan fluorescent lighting, mercury lights, tyres, lead acid
and regional areas of the State and householders are batteries, gas bottles, paints, waste oil and all plastics.
asked to deliver unwanted chemicals to collection ZWSA has already made progress in some of
points. The collection timetable is on the ZWSA these areas. ZWSA has helped householders safely
website. Following a State Government commitment, dispose of the mercury contained in the new energy
$2.8 million was allocated for the collection of efficient lights through the BackLight Household
household and farm hazardous waste across the Light Globe Recycling Program. Householders can
State for a further four years (starting 2010–11). drop off a range of used fluoro globes for recycling
at metropolitan and regional Mitre 10 and True Value
7.5.1 Program: Household hazardous stores across the State, free of charge. The globes
waste and farm chemical collections are then recycled by Chemsal Resource Recovery.
In line with the Waste Strategy, in 2012‑13 ZWSA will: See program 7.2.1 for details of ZWSA’s e-waste
strategy.
• continue to fund a household and farm hazardous
waste collection program across South Australia, ZWSA will work closely with the EPA, local
and monitor and report the results government, recycling industry (including container
deposit operators), lighting industry, plastics
• investigate and progress the establishment of industries, tyre industry, major retailers and other
permanent facilities key stakeholders.
• educate the community on proper household Budget for the next three years:
hazardous waste management practices and
better inform stakeholders and the community on 2012- 2013-2014 2014-2015
household and farm chemical collection facilities 2013 (indicative) (indicative)
• encourage the recovery and treatment of oils, BackLight $60,000 $60,000 $60,000
program
solvents and other valuable materials for reuse
Associated $190,000 $140,000 $140,000
• reduce hazards through hazardous waste strategies
collection, recycling and appropriate disposal
• integrating with Keep Australia Beautiful National 7.7 Priority area: Research and
Litter Index and Branded Litter Study
development
• developing litter reduction strategies and
South Australia’s Waste Strategy 2011–2015 recognises
resources based on litter count data
that research will underpin and inform how we
• achieving measureable reduction in targeted litter address new challenges of wasteful consumption,
and change behaviours. Research priorities will be
• regularly reporting to, engaging and informing evaluated from time to time. As we extend our
stakeholders knowledge and focus on sustainable use of resources,
we begin to extend beyond known approaches to
• continuing ongoing public awareness and media traditional recycling and reuse.
management
PROGRAM
29
• embed this new learning within our education In response to the new Waste Strategy which
systems places more emphasis on ‘avoid’, ‘reduce’ and ‘reuse’
strategies, as well as outlining new community-based
• support consumers to make informed programs or initiatives, new data will be collected in
purchasing decisions. 2011-12 which provides benchmarks for these newer
program areas such as green purchasing, waste
avoidance and sustainability.
8.1 Priority area: Measurement, Budget for the next three years:
analysis, evaluation and reporting
to support targets and assess the 2012-2013 2013-2014
(indicative)
2014-2015
(indicative)
adequacy of the Waste Strategy
$40,000 $45,000 $45,000
South Australia’s Waste Strategy 2011–2015 identifies
the following priority actions in building our
knowledge and data on waste and recycling:
• monitor infrastructure and identify gaps (to be
undertaken as part of the waste strategy review)
8.2 Priority area: Municipal ZWSA will continue to provide some support to
KESAB’s Sustainable Communities activities.
solid waste
Budget for the next three years:
South Australia’s Waste Strategy 2011–2015 identifies
the following priority actions to ‘avoid and reduce 2012-2013 2013-2014 2014-2015
waste’ in MSW: (indicative) (indicative)
• use innovative approaches to inform households,
$25,000 $25,000 $25,000
increase awareness of wasteful consumption and
effective recycling, and maintain awareness above
8.2.2 Program: Wipe Out Waste schools
80%
program
• promote green purchasing and waste avoidance The Wipe Out Waste (WOW) program provides
with householders and councils training and resources for teachers and helps drive
• explore links with emerging sustainability agendas positive change in schools. WOW was developed on
(e.g. sustainability in food policy) behalf of ZWSA by KESAB environmental solutions,
the Department of Environment and Natural
• engage the community in opportunities involving Resources, and Department of Education and
resources and sustainability Children’s Services (DECS). WOW is an integrated
comprehensive waste education program supported
• develop systems that assist purchasing decisions by curriculum resources and teacher training. It is
such as extended producer responsibility, the first program in Australia to span kindergarten
star-rating systems and the choice to leave through to primary and secondary schools.
packaging in-store.
These resources enable students to gain an
8.2.1 Program: KESAB Sustainable understanding of waste, litter, recycling and
Communities (city and country) related environmental issues as part of the school
curriculum. WOW is a fundamental adjunct to the
South Australia’s Waste Strategy 2011–2015 recognises DECS Sustainable Schools Program. The findings of
the importance of supporting local activities, a 2008 comprehensive evaluation of the program
including schools, to tap into the values of the continue to inform ZWSA’s funding provision and
community and encourage sustainable behaviour direction for the program.
change. KESAB has committed to ongoing
environmental education and action embracing In 2012–13, the program will continue with its focus
rural communities, local government, schools and on regional and metropolitan schools. In particular,
groups through a revamped Tidy Towns program, KESAB has committed to:
Sustainable Communities. • identifying a key performance indicator for the
KESAB encourages rural communities to adopt and number of additional schools in the strategic plan
implement sustainable environmental practices, • developing age-appropriate resources as needed
encouraging a whole of community approach through
environmental education and action. This includes • establishing community, council and industry
recognition of waste and recycling efforts through linkages and partnerships for each participating
annual awards, community action and councils. school
KESAB has committed to: • reducing waste in schools
• delivering the Sustainable Communities
program to a high standard with engagement • regular reporting to stakeholders.
by communities in each region evidenced by Budget for the next three years:
applications from a range of community-based
groups including councils, schools, natural 2012-2013 2013-2014 2014-2015
resources management boards, and service and (indicative) (indicative)
community groups
$240,000 $245,000 $246,000
• involving Adelaide communities, with at least five
urban entries in 2012, eight in 2013 and 10 in 2014
ZWSA is part of the Business Sustainability Alliance • Promote innovation and fund the expansion
(BSA) in partnership with the Department for of resource recovery initiatives to include
Manufacturing, Innovation, Trade, Resources and accreditation schemes. Support the development
Energy, SA Water and the Environment Protection and implementation of Climate change sector
Authority. The BSA provides key competencies agreements $100,000 of funding available in 2012-13
in the areas of waste, water, energy, lean
manufacturing, construction, compliance, climate
change and sustainability.
Consistent with priority actions in the Waste
Strategy, ZWSA is extending its work under the
Industry Program.
2013‑2014 2014‑2015
2012‑2013 (indicative) (indicative)
Industry training, awareness, publications and promotion 300,000 310,00 300,000
Resource efficiency and supply chain initiatives 588,000 630,000 600,000
Government sustainability initiatives (including
procurement) 130,000 130,000 115,000
Innovation and accreditation schemes 100,000 100,000 100,000
$1,118,000 $1,170,000 $1,115,000
33
• help to guide social change towards models of • ensure planning decisions take into account of
sustainable consumption. waste generation and waste reduction
ZWSA’s support will help guide a transition to • promoting sustainable procurement, especially in
sustainable resource use in the economy. For the government sector
example, it may assist supply to meet a genuine
demand, or it may facilitate more sustainable • applying financial instruments to drive change
consumer choices.
• engaging industry training and association bodies to
Applicants are required to meet the following criteria include avoidance, reduction and recycling within a
for suitable projects to receive funding: sustainability context in apprentice training.
• are unique/innovative in South Australia
8.4.1 Program: Promote better design
• need seed or kick-start funding of the built environment
• need funding for an element essential to the Building and retrofitting of commercial and residential
initiative’s success (i.e. the initiative would not development and construction work can strengthen
proceed without the element) the ability to move towards a more sustainable use of
building materials and practices. This can be achieved
• operate at the ‘avoidance’, ‘reduction’ or ‘reuse’ by working within the legislative planning framework
levels of the hierarchy to develop principles and guidelines that:
• can demonstrate measurable outcomes and • promote better design of the built environment
return on investment and adoption of new and more sustainable building
materials
• are based on a model that has been proven
successful elsewhere • minimise or avoid waste in the construction
process
• deliver multiple benefits in addition to reduced
consumption and improved resource (social, • promote building design that supports
economic or environmental) future adaptability and maximises reuse and
redevelopment of existing infrastructure
• are consistent with Government policy directions
including targets for reduction of waste to landfill • incorporate material reuse, materials with
and the Waste Strategy 2011–2015 recycled content and materials that are recyclable
• can be implemented and reported within 18 • include on-site waste separation and recovery
months of initiation. systems during construction and demolition
ZWSA will offer this program in 2012–13 and assess • provide sufficient space to manage waste and
future rounds of funding in 2013–14 and 2014–15 recycling infrastructure in the design phase of
following review of the initial round of applicants and developments
initiatives proposed.
• where feasible, achieve the outcomes under
Budget for the next three years: ‘Management’ and ‘Materials’ in the Green Star
Rating tool (www.gbc.org.au).
2012-2013 2013-2014 2014-2015
(indicative) (indicative)
$130,000 $135,000 $135,000
34
ZWSA is working with the appropriate stakeholders, 8.5 Priority area: Problematic
such as the Department of the Premier and Cabinet’s
Green Building initiative, University of South hazardous waste
Australia, Housing Industry Association, Master In line with the Waste Strategy in 2012‑13 ZWSA will:
Builders Association of SA, Property Council,
developers, Department for Planning, Transport and • engage with producers, importers and
Infrastructure, Urban Development Authority , and manufacturers to educate, encourage and support
others, to promote better sustainable design of the product stewardship initiatives for e-waste, tyres
built environment. This will include adoption of new and batteries (see program 7.2.1 and 7.5.2)
and more sustainable building materials and practices.
• reduce hazards through hazardous waste
Budget for the next three years: collections, recycling and appropriate disposal (see
program 7.5.1)
2012-2013 2013-2014 2014-2015
(indicative) (indicative) • encourage less toxic materials (see program 7.5.1)
PROGRAM
37
PROGRAM
39
10 Budget
PROGRAM
43
$400,000 $1,118,000
Recycle Right Industry
Program
Expenditure by priority area and program $400,000
Kerbside
incentives
$419,000
E-waste
collections
$559,000
Regional
implementation
10%
44
5%
2010-11
0% 2011-12
MSW 2012-13
C&D C&I Litter
Haz waste Avoidance
10% 5%
10%
Data
analysis
&
repor7ng
Local
Government
2%
36%
Industry
30%
Budget breakdown by key project/activity
40%
35%
30%
25%
20%
15%
10%
5%
2010-11
0% 2011-12
MSW 2012-13
C&D C&I Litter
Haz waste Avoidance
10%
5%
Budget breakdown by priority area
10%
Data
analysis
&
repor7ng
Local
Government
2%
36%
Industry